Viewing Assignment Unit and Cost Spreads

Use the spreadsheet to view live unit and cost spreads for an activity assignment for a resource or role.

To view the assignments usage spreadsheet:

  1. On the "" Navigation Menu, expand "" Resources and click Assignments.
  2. On the Assignments page:
    1. Click "" Spreadsheet View.

      Note:

      To customize the list of resources displayed in the table, click "" Customize View and either use an existing filter or add a new filter.

    2. Click "" Customize View and then click Spreadsheet.
    3. On the Spreadsheet tab of the Customize View dialog box:
      • Choose the columns to display in the view.
      • Choose the Start Date and Finish Date to define a range for the spreadsheet.
      • Select Calculate average for units and costs if you are dividing the unit and cost fields by a value, and then type a value in the Divide values by field.
      • Select a Timescale for the view.
    4. Click Apply.

Tip:

  • P6 includes only data in spreads. To see up to date spread data, select Actions, Run, Store Period Performance and then ensure that the project has been republished.
  • An application level setting determines whether cost spreads account for changes in resource and role rates over time.
  • You can export the data on this page to a Microsoft Excel file by clicking Export.