Item Start Date and End Date References
The bridge can be configured to include the PPM item start and end dates.
Under the project level WBS element, two milestone activities will be created: Start Date reference from Primavera Portfolio Management and End Date reference from Primavera Portfolio Management. These will reflect the start and end dates of the mapped item and will show up on the gantt chart. They can also be configured to be updated in future publish operations.
The bridge can be configured to include these start and end date references regardless of whether the sub-items or phases mapping mode is being used to publish the item.
In addition to the item start and end date references, each of the mapping modes has its own unique publishing defaults.