Phase Information
Date-associated activity information is updated from second level WBS elements that are mapped to Primavera Portfolio Management start and end dates. The update process searches for item phases that match the project’s second level WBS names. If your administrator has elected to update phase information to Primavera Portfolio Management, the update process copies new WBS information to Primavera Portfolio Management when it finds an exact phase name match. The following table shows the phase fields that are updated.
| P6 WBS Field | PPM Phase Field |
|---|---|
| BL1 Start date | Planned Start date |
| BL1 Finish date | Planned End date |
| Start date | Forecast Start date |
| Finish date | Forecast End date |
| Actual Start date | Actual Start date |
| Actual Finish date | Actual End date |
| Performance % Complete | % Complete |