Create or Edit Timeline Charts for Visualizations in Projects/Shells
To create or edit Timeline charts for visualizations in a project/shell (Admin mode):
- Sign in to Unifier with project/shell administration credentials.
- Select the specific project/shell tab, and switch to Admin mode.For example, select a tab called Vision Corporation.
- In the left Navigator, select Setup, and then select Visualizations.
- In the Visualizations log (right pane), perform one of the following actions:
- Select Create to add a new visualization in the project/shell. Then on the Create page, do the following to preview the data before creating the item:
- From the Data Source list, select the data source to use for creating the content item. The list shows published content in the alphabetical order.
- From the Preview Project list, select an active project/shell and then select Preview Data.
or
- Select a visualization in the log and select Edit. Then on the Edit page, select Edit
for a content item in the visualization layout.
- Select Create to add a new visualization in the project/shell. Then on the Create page, do the following to preview the data before creating the item:
- In the Create or Edit page, specify or update the following information:
- From the View Type list, select Timeline Chart.
- In the Name field, enter a name for the Timeline chart.
Note:
The combination of Name and View Type field values must be unique. - Optional: In the Description field, enter a short description about the Timeline chart.
- From the Event Type list, select Single Event (default) or Duration Event.
- If you chose Single Event, from the Category (Time Axis), select a date field that defines the event timeline.
- From the Event Title list, select a data element that can be used as the title for the timeline event.
- From the Event Detail list, select a maximum of two event details to track in the timeline chart.
- To add a another event detail, click Add.
- To remove an event detail and its associated data element, click Delete (x).
- If you chose a Duration Event, in the Event Duration field, select a date or date/time data element to choose the start date and end date of the duration of the Timeline chart.
- After populating the required fields for a Bar chart, you can allow your users to explore related data using dynamic content by selecting More Actions … and then selecting Configure Drill down.
For more information, see Configure Drill-down Content for View Types.
- From the Color By list, select a data element to measure using a color-code. To remove a color code and the associated data element, click Delete (x).
- If the data element selected in the Event Detail field represents a numeric or currency value, specify the display format for this value:
- From the Decimal Places list, select the number of decimal places following the decimal point to be used for numeric values. Choices include 0 through 8.
- From the Abbreviations list, select the abbreviated format to be used for currency values. Choices include: Auto (default), None, Thousands (K), Millions (M), Billions (B), and Trillions (T).
- From the Currency Options list, select the currency used by the project/shell. Choices include: None, Shell Currency, and Base Currency.
- From the Orientation list, select Vertical or Horizontal (default).
- In the Timeline Overview field, toggle to hide or display a compressed overview of the entire timeline.
- In the Tooltip field, toggle to hide or display tooltips when you hover over events on the Timeline chart.
- Make changes as needed to refine the above selections.
- After making all changes, perform any of the following actions:
- If you created a table, select Create, and return to the Edit page.
- To confirm all the changes made to the edited table, select Update, and return to the Edit page.
- On the Edit page, select Save to update the visualization with any created or edited content.