Duplicate Visualizations in Projects/Shells

Project/Shell Administrators can efficiently create visualizations by duplicating current visualizations and then modifying each as needed in the Visualizations log of projects/shells they have access to.

You must have the Setup permission enabled for visualizations in the specific project/shell to perform this task.

To duplicate visualizations from the Visualizations log of a project/shell:

  1. Sign in to Unifier with project/shell administration credentials.
  2. Go to the specific project/shell tab, and switch to Admin mode. For example, select a tab called Vision Corporation.
  3. In the left Navigator, select Setup, and then select Visualizations.
  4. In the Visualizations log (right pane), select the checkbox adjacent to the Name of a visualization you want to copy, and then select Duplicate.

    The name of the duplicate visualization is suffixed with "_Copy1". For example, RFI Summary Report_Copy1.