Activity Attributes (Cost)

Assignment Attribute Data Element Calculation
Planned Total Cost uuu_P6PlannedTotalCost The expected total cost of the activity, consolidating costs of all assignments.
Actual Total Cost uuu_P6ActualTotalCost The actual non-overtime plus overtime cost for all the resource assignments of the activity.
Remaining Total Cost uuu_P6RemainingTotalCost The remaining cost of all the resource assignments for the activity.
At Completion Total Cost uuu_P6AtCompletionTotalCost The sum of the actual costs plus remaining costs for the resource assignment on the activity. Calculated as Actual Costs plus Remaining Costs.