Activity Attributes (Units)
| Assignment Attribute | Data Element | Calculation |
|---|---|---|
| Planned Total Units |
uuu_P6PlannedTotalUnits
|
The planned units of work for the activity. |
| Actual Total Units |
uuu_P6ActualTotalUnits
|
The exact number of units that have been expended on the selected activity. |
| Remaining Total Units |
uuu_P6RemainingTotalUnits
|
The remaining units of work to be performed by the resource on the activity. Calculated as Planned Units minus Actual Units. |
| At Completion Total Units |
uuu_P6AtCompletionTotalUnits
|
The sum of the actual units and remaining units for the resource assignment on the activity. Calculated as Actual Units plus Remaining Units. |