Activity Attributes (Units)

Assignment Attribute Data Element Calculation
Planned Total Units uuu_P6PlannedTotalUnits The planned units of work for the activity.
Actual Total Units uuu_P6ActualTotalUnits The exact number of units that have been expended on the selected activity.
Remaining Total Units uuu_P6RemainingTotalUnits The remaining units of work to be performed by the resource on the activity. Calculated as Planned Units minus Actual Units.
At Completion Total Units uuu_P6AtCompletionTotalUnits The sum of the actual units and remaining units for the resource assignment on the activity. Calculated as Actual Units plus Remaining Units.