General Tab

Contains all the details related to the activity sheet, which are defined in Activity Attribute Form including the WBS Details. The data elements and the order of the data elements, shown in the General tab, are based on the Activity Attribute Form. The hidden data elements are not shown in the General tab. You can dock this pane to the right side of the screen. If you dock the pane at bottom, or right side, manually, the system retains your choice after closing the Activity Sheet window. You can expand the bottom pane by using the Expand "" icon on the right side.

The General tab displays the attributes for the selected activity in groups:

  • WBS Attributes
  • Activity Attributes (General)
  • Activity Attributes (Schedule)
  • Activity Attributes (Units)
  • Activity Attributes (Cost)
  • Activity Attributes (Earned Value)

Actual Dates

  • An activity progress <uuu_P6PercentComplete> will be editable after the <uuu_P6ActualStart> has been entered, or the <uuu_P6ActivityStatus> has changed to 'In Progress'. If <uuu_P6ActualStart> has been entered, the uuu_P6ActivityStatus will be changed from 'Not Started' to 'In Progress' and conversely, automatically.
  • When <uuu_P6ActivityStatus> has changed from ' In Progress' to 'Completed' the <uuu_P6ActualFinish> will be populated with current date and conversely.
  • When <uuu_P6ActivityStatus> has changed from ' Not Started' to 'Completed' the <uuu_P6ActualStart> and <uuu_P6ActualFinish> will be populated with current date.
  • Actual Start Date <uuu_P6ActualStart> cannot be entered in future date (cannot be different from the current date).
  • Actual Finish Date <uuu_P6ActualFinish> cannot be entered in future date (cannot be different from the current date).