Performance Percentage Completion Sheet

Select the corresponding button to open the Performance Percentage Completion sheet overlay in the EV Analysis log.

During each synchronization, the performance percentage completion value of an activity gets updated from P6. Unifier stores the values against corresponding data dates, which are then used to calculate earned value metrics.

Note:

The functionality is only applicable to the current schedule of a project.

Similar to performing Earned Value (EV) analysis on a System Activity Sheet, you can select active manual activity sheets and perform Earned Value analysis on those sheets; however, the following exception will apply when performing Earned Value analysis on the active manual activity sheets:

  • The Performance % Complete option is not required, or available, for EV analysis of active manual activity sheets.
  • The Cost Sheet columns for CBS type of BPs are not required, or available, for EV analysis of active manual activity sheets.
  • After you create an EV analysis sheet (see the Preview Tab) for active manual activity sheets, if you change the status of any of the activity sheets to inactive, you still can update the data through data refresh function, in the Schedule tab.
  • The Name column, in the Project picker window, displays the name of the manual activity sheets.
  • The WBS codes for the manual activity sheets appear in the WBS picker window, and the codes are not suffixed with any text.

When performing Earned Value analysis on the active manual activity sheets, you can get information about the:

  • Actuals within a created cost-based graph, where the costs that correspond to all of the EV metrices are included.
  • Actuals from the WBS sheet within a created unit-based graph, where the units that correspond to all the EV metrices are included.
  • WBS codes in the WBS sheet for the respective Manual Activity Sheet in the EV analysis graph, in the WBS code picker.