Recost - Assignment Attributes

Assignment Attribute Data Element Calculation
Planned Cost uuu_P6PlannedCost

Calculated at spread level.

Unifier Planned Units X Price/Unit.

If the rate source is Override, the system uses the rate present in the activity sheet (System or Manual) corresponding to that assignment.

Actual Cost uuu_P6ActualCost

Calculated at spread level.

Unifier Actual Units X Price/Unit.

If the rate source is Override, the system uses the rate present in the activity sheet (System or Manual) corresponding to that assignment.

Remaining Cost uuu_P6RemainingCost

Calculated at spread level.

Unifier Remaining Units X Price/Unit.

If the rate source is Override, the system uses the rate present in the activity sheet (System or Manual) corresponding to that assignment.

At Completion Cost uuu_P6AtCompletionCost

Calculated at spread level.

Unifier At Completion Cost is the sum of actual cost and remaining cost for that assignment.