WBS Attributes

Assignment Attribute Data Element Calculation
WBS Code uuu_P6WBSCode The unique identifier of the WBS for the associated activity.
WBS Name uuu_P6WBSName The name of the WBS Code for the associated activity.
WBS Path uuu_P6WBSPath The location of the activity on the WBS hierarchy.
WBS Type
ETC Technique uuu_P6ETC The field is populated with the formula used for the ETC calculation. ETC is the estimated cost to complete the activity, WBS, or project. Calculated as Remaining Total Cost for the activity or the Performance Factor multiplied by (Budget At Completion minus Earned Value), depending on the Earned Value technique selected for the activity's WBS (calculated from the primary baseline). Budget at Completion is calculated from the project baseline.