Unifier Activity Manager for Oracle Primavera Cloud Schedules

You can also integrate multiple Oracle Primavera Cloud projects into multiple Unifier projects.

In Oracle Primavera Cloud, if two or more projects have the same Project ID, then when integrating those projects into a single project, Unifier will randomly select only one of the Oracle Primavera Cloud projects that have same Project ID and integrate that project into Unifier.

Note:

You can access the Activity Manager module for setting up Oracle Primavera Cloud schedules the same way as accessing the Activity Manager module in a shell. The Activity Sheets log components (for setting up Oracle Primavera Cloud schedules) are also the same as the Activity Sheets log in a shell.

The following explains the information specific the Activity Sheets log for Oracle Primavera Cloud schedules.

Options and Tabs Description
Get Data

Use this option to:

  • Create an activity sheet for the first time.
  • Update an existing activity sheet with the most recent activity spread data from the Oracle Primavera Cloud project.

    Updating triggers a new OOTB import synchronizations if you have selected the Select Synchronization to Exchange Activity Data option in Gateway integration settings drop-down list.

    All the synchronized Oracle Primavera Cloud project activities, planned dates, actual, at completion dates, and associated WBS Code will be displayed in the activity sheet.

    If the shell is not active (inactive shell), Gateway integration will fail.

When you select this option (Get Data), the system checks for the Oracle Primavera Cloud project that as defined in the Integration tab and then brings the Oracle Primavera Cloud project activity data and their schedules into the activity sheet:

  • Based on the import synchronization defined in Gateway settings, and
  • If Oracle Primavera Cloud and Unifier projects are linked.

If you select this option and there is no Project ID added in the Integration tab, the system will display this message: Valid Project ID is not specified in the Shell Integration Tab.

Note:

Unifier does not bring the baseline (project data) from Oracle Primavera Cloud.
Send Data

Use this option to run the export synchronization to send the updated activities and schedules from an Activity Sheet to the Oracle Primavera Cloud.

The data elements in the business processes, or the Shell Attribute Form, which have been set to reverse auto-populate (RAP) back to the Oracle Primavera Cloud Activity Sheet (using P6 Activity Picker) will get the latest updates into the Oracle Primavera Cloud Activity Sheet.

You can send updated Activity Sheet data (such as: updated Actual Start Date or Finish Dates) to the Oracle Primavera Cloud project which is linked by way of the OOTB export synchronization option: Update Unifier Activity data in to Primavera Cloud.

The Schedule tab, in the Activity Sheet log, shows this option, and you can set the scheduled send data based on frequency.

Mapped Projects tab

The Mapped Projects tab has the following toolbar options:

  • Refresh: To refresh the log items for both the Mapped Projects tab and the History tab.
  • Find on Page: To conduct a search for items on the list.

The Mapped Projects tab displays a list of all the mapped Oracle Primavera Cloud projects. The following columns are available in this tab:

  • Project ID: Displays the linked Oracle Primavera Cloud Project ID.
  • Project Name: Displays the project name.
  • Project Type: Displays the value of either Current or Baseline. If you receive the current schedule information, the Project Type column shows: Current.
  • Project Start Date: Displays the start date of the project.
  • Data Date: Displays the last refreshed date from Oracle Primavera Cloud.
  • Schedule Type: Displays Duration as schedule type.
Schedule tab The Schedule tab enables you to set the frequency for Get Data along with a table that shows the schedules based on the frequency. This is applicable to all projects in the activity sheet. Other drop-down values for the Set Frequency for will be Send Data. You can select Send Data, but the OOTB synchronization option is not available for sending the updated activity data back to Oracle Primavera Cloud.
History tab The History tab displays the history of all the events that are being performed across the Oracle Primavera Cloud projects that are present in the activity sheet.

When you open an activity from the Activity Sheets log, the Activity Sheet overlay page opens.

The Activity Sheet overlay page displays all the activities data, in columns, such as:

  • Activity ID
  • Activity Name
  • Activity % Complete
  • Activity Status
  • Activity Type

The Activity Sheet overlay page displays the general information about an activity in the General tab (right pane), categorized by blocks, such as:

  • WBS Attributes
    • WBS Code (uuu_P6WBSCode): WBS Code associated to each Activity.
    • WBS Name (uuu_P6WBSName): WBS Name associated to each Activity.
    • WBS Path (uuu_P6WBSPath): WBS Path associated to each Activity.
    • Work Package (uuu_P6WorkPackage): This is the leaf node for every WBS structure and will have the values Yes/No.
  • Activity Attributes (General)
    • Activity ID (uuu_P6ActivityId)
    • Activity Name (uuu_P6ActivityName)
    • Status (uuu_P6ActivityStatus)
    • Type (uuu_P6ActivityType)
    • Performance % Complete (uuu_P6PercentComplete)
  • Activity Attributes (Scheduling)
    • Planned Start (uuu_P6PlannedStart)
    • Planned Finish (uuu_P6ActualFinish)
    • Planned Duration (uuu_P6Planned)
    • Actual Start (uuu_P6ActualStart)
    • Actual Finish (uuu_P6ActualFinish)
    • Actual Duration (uuu_P6ActualDuration)
    • Remaining Duration (uuu_P6RemainingDuration)
    • At Completion Duration (uuu_P6AtCompletionDuration)

You can use this activity data in a business process using Activity Picker, and the updated dates can be reverse auto-populated into the activity sheet. The activity sheet data can be sent back to Oracle Primavera Cloud using the export synchronization selected in Gateway integration settings.

Activity Mappings in Gateway

The following activity attributes are displayed in the log:

Oracle Primavera Cloud Gateway Unifier
activityPercentComplete PercentComplete uuu_P6PercentComplete
actualDuration ActualDuration uuu_P6ActualDuration
actualFinishDate ActualFinishDate uuu_P6ActualFinish
actualStartDate ActualStartDate uuu_P6ActualStart
atCompletionDuration AtCompletionDuration uuu_P6AtCompletionDuration
finishDate FinishDate uuu_P6Finish
activityCode Id uuu_P6ActivityId
activityName Name uuu_P6ActivityName
plannedDuration PlannedDuration uuu_P6PlannedDuration
plannedFinishDate PlannedFinishDate uuu_P6PlannedFinish
plannedStartDate PlannedStartDate uuu_P6PlannedStart
projectId ProjectId uuu_int_p6_project_id
remainingDuration RemainingDuration uuu_P6RemainingDuration
remainingFinishDate RemainingFinishDate uuu_P6RemainingEarlyFinish
remainingStartDate RemainingStartDate uuu_P6RemainingEarlyStart
startDate StartDate uuu_P6Start
activityStatus Status uuu_P6ActivityStatus
activityType Type uuu_P6Activitytype
wbsCode WBSCode uuu_P6WBSCode
wbsId WBSObjectId uuu_P6WBSElementId
wbsPath WBSPath uuu_P6WBSPath
wbsName WBSName uuu_P6WBSName

The WBS Sheet will be created if the WBS Structure field mapping template is defined in Gateway. The WBS Sheet shows the WBS hierarchy, or structure, associated with the activities.

Note:

OOTB synchronization does not provide field mappings for the WBS Structure. You must define the WBS structure mapping in Gateway for the WBS sheet that has been created in Unifier.

The WBS Sheet lists the WBS structure. All the cost and units columns will be zeros (0s) in Unifier 20.7 and later. All the predefined eight columns are displayed by default, with cost and unit values as zeros (0s).

The System Data Elements that are available in the WBS Attribute Form are not editable, but you can add additional data elements in the WBS Attribute Form.

You can add additional columns based on type directly as a cell entry, formula, or from:

  • WBS Custom Attributes
  • Business Processes
  • Activity Sheet

    Note:

    For duration based schedules, the WBS Picker does not show the associated WBS Codes in the business processes when the EVA Sheet is not created.

Activity Picker in Business Process or Shells

When an Activity Picker that is based on P6 Activity Picker data definition is placed on a business process upper form or detail form, or in the Shell Attribute Form in uDesigner, you can use that picker to select activities from the Activity Sheet located within that shell.

When you select an activity by way of a P6 Activity Picker, the system displays the Activity Picker log, as defined in uDesigner. The Activity Picker log lists all the Oracle Primavera Cloud Projects in the Projects drop-down, where you can select the current schedule and select the activity sheet. After selecting the activity sheet, the hierarchy (similar to the one used in the activity sheet) will be displayed.

The list of activities from the picker is filtered according to the query conditions defined within the Data Picker configuration, in Admin mode.

The data elements that can be set to auto-populate from a picker will be populated from the selected activity in the picker.

The data elements that have been set to reverse auto-populate (RAP) to Oracle Primavera Cloud will RAP according to the RAP conditions, in uDesigner. If no RAP conditions are defined, the data elements that have been set to reverse auto-populate (RAP) to Oracle Primavera Cloud will RAP when the record is moved to next step (for Workflow BPs) and when the record is marked as: Finish Edited' (for Non-Workflow BPs).

The linked data elements using an activity picker get updated when the activity gets updated by way of integration.

The auto-population will take place if the picker is set to auto-populate from another picker, and also is set as a source to auto-populate into other data elements.

If a picked activity is deleted, the system will remove the picker value, and the data elements that hold auto-populated from that activity (the deleted activity) continue to display their values. In such scenario, the system will remove the data elements that hold dynamically linked values.