% Earned Calculation Method option is Manual activity % earned - updates resource % earned

If the entry method and option settings on the Budget and Progress Method Setup window are:

  • % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
  • % Complete Calculation Method option = Manual activity % complete - updates resource % complete
  • % Earned Calculation Method option = Manual activity % earned - updates resource % earned

This data entry method scenario results:

Activity or Resource Data Element Data Entry Method
Activity
  Activity % Complete Manual entry
Earned Progress Manual entry
Resource
  Progress Quantity

Calculated (read-only).

(Activity-level Activity % Complete * Quantity)

Earned Progress

Calculated (read-only).

(Activity-level Earned Progress * Quantity)