% Earned Calculation Method option is Resource updates Activity - weighted average of resource costs
If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
- % Complete Calculation Method option = Manual activity % complete - updates resource % complete
- % Earned Calculation Method option = Resource updates Activity - weighted average of resource costs
then this data entry method scenario results:
| Activity or Resource | Data Element | Data Entry Method |
|---|---|---|
| Activity | ||
| Activity % Complete | Manual entry | |
| Earned Progress |
Calculated (Weighted Cost) {Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 |
|
| Resource | ||
| Progress Quantity |
Calculated (read-only). (Activity-level Activity % Complete * Quantity) |
|
| Earned Progress | Manual Entry | |