Create and Edit a Storm Event

A storm event defines the actual restoration timeline of a storm that occurred in the past. You can then include this historical information in your calculations when creating an estimated restoration timeline (ERT) for a new storm model.

Storm event information may be imported from the Oracle Utilities Network Management System (NMS) or another third-party outage management software. Your Oracle Delivery Team will work with you to configure the import.

On this page:

Create a Storm Event

Tip: Be as accurate as possible about the storm event when you create it, since outage information is loaded based on the details you enter. If no outage information is loaded, then try updating the details you entered.

  1. Sign in to Storm ERT.
  2. From the Storm ERT dashboard, click Create Storm Event.
  3. On the Create Storm Event page, complete the required fields. See List of Storm Models and Events for more details about these fields.
    • Name: Add a distinct name for the storm event. For example, you can create a name that includes a month and year, such as Maggie June 2022.
    • Start Date: Set the date and time when the storm entered the service territory.
    • Cut-Off Date: Set the date and time after which new outages were excluded from the storm event.
    • Type (optional): Choose the type of storm. It is recommended that you choose a type so that you can more easily search by it later, or make comparisons to other storms of the same type.
    • Level (optional): Choose the severity level of the storm. The meaning for each level varies by utility due to regional differences in weather patterns, so consult your internal documentation if you need guidance on which level to choose. (For example, in some regions a few inches of snow is considered a major snow storm, while in other regions it is considered minor.) It is recommended that you choose a level so that you can more easily search by it later and make comparisons to other storms.
    • Exclude Single Customer Outages: Select this option if you want to exclude any outages that affect a single customer rather than multiple customers simultaneously. It is recommended that you select this option if you want to exclude outliers that may skew the results of a storm ERT.
  4. Click Continue.
  5. Select one or more zones in your service territory that were affected by the storm event. Affected zones are listed under the name of the operating company.

    Note: If there is more than one operating company, then you can only select affected zones for one of the operating companies. For example, if you select a zone for Operating Company A, you will not have the option to select zones for Operating Company B.

  6. Click Create Storm Event.

The storm event is created and added to the Storm ERT dashboard in the Historic state. Outage information from your connected outage management system is loaded into the storm event based on the start date, cut-off date, and zone information you entered. If no outage information is loaded, then it is probably because one of these pieces of information is incorrect and needs to be updated.

Back to Top

Edit a Storm Event

You can edit the details of a storm event to improve its usefulness and accuracy. You may also need to edit a storm event if no outage data loads into it after you create it. For example, you may need to adjust the start date, cut-off date, or zone information to ensure the right historical information is loaded.

  1. Sign in to Oracle Utilities Analytics Insights.
  2. Click Explore, Storm, and then ERT.
  3. From the Storm ERT dashboard, search for and click the name of the storm event you want to update.
  4. In the storm event view that opens, click Edit.
  5. Make any edits to the Storm Event Details and Affected Zones pages.
  6. Click Save.