Correcting Cross Installed Meters

Cross installed meters is the term for situations in which meters are deployed at an incorrect customer service point. Consider the following example: Meter  A is supposed to be installed at Service Point A and Meter B is supposed to be installed at Service Point B, but Meter B was mistakenly installed at Service Point A, and Meter A was mistakenly installed at Service Point B. This means that both customers will be billed incorrectly (customer at Service Point A will be billed for usage at Service Point B and vice versa) until the system can updated to reflect the correct meter installations.

The Cross Installed Meters process provides a tool to re-configure the meters through a correction process. When a user initiates the Cross Installed Meters process, the system will update device installation event details (like status, date and time of installation), device configurations, and measuring components with the correct information. Note that this process does NOT include changing the physical location of the meters. It only changes the relationship between the meters and service points in the application.

This process can also be used to issue financial adjustments and/or cancel/rebill any bill segments that are impacted by the change in meters, and create customer contacts related to the changes. See Adjustments and Cancel / Rebill Incorrect Bill Segments for more information about adjustments and rebilling.

Cross installed meter processing is initiated, monitored, and maintained using the Process Flow portal and functionality.

See Process Flows in the Administrative User Guide for more information regarding the process flow functionality.

See Configuring Cross Installed Meter Processing in the Administrative User Guide for information about configuring administrative data required by the Cross Installed Meter process.

Initiating a Cross Installed Meter Process

Use the following procedure to initiate a cross installed meter process:
  1. Select Menu, Device Installation, Cross Installed Meter Process, Add. The Cross Installed Meters process flow screen opens on the Swap Meters panel.

  2. Use the Cross Installed Meter Identification section to search for and select the first meter (Meter 1).

    1. Select Meter 1.

    2. Enter the search criteria for the meter. You can search by the service point's Address, City, or Postal code, or the device's Badge Number.

    3. Click Search.

    4. Select the appropriate meter. Information about the selected meter (including its service point, device, and device configuration) will appear in the Meter 1 box.

    5. To create a field activity to investigate the status of this meter (for instance, to confirm which meter is installed at the service point), click Investigate under the  Meter 1  section. This will create a field activity with a Field Task Type of that defined on the Cross Installed Meter Request Type. Note that you cannot proceed with the process flow until field activities created in this way have been completed.

  3. Use the Cross Installed Meter Identification section to search for and select the second meter (Meter 2).

    1. Select Meter 2.

    2. Enter the search criteria for the meter. You can search by the service point's Address, City, or Postal code, or the device's Badge Number.

    3. Click Search.

    4. Select the appropriate meter. Information about the selected meter (including its service point, device, and device configuration) will appear in the Meter 2 box.

    5. To create a field activity to investigate the status of this meter (for instance, to confirm which meter is installed at the service point), click Investigate under the  Meter 2  section. This will create a field activity with a Field Task Type of that defined on the Cross Installed Meter Request Type. Note that you cannot proceed with the process flow until field activities created in this way have been completed.

      Note: After selecting the second meter, the Insights box will display information about the meters based on the "Cross Installed Meters - Inline" (X1-CROSSEDMETER-INLINE) Insight Type.

  4. Click Save to save your selection before making any changes. You can return to this process at a later time using the Process Flow Query portal.

  5. Click Swap Meters to initiate the process of canceling/deleting the current incorrect install events, and creating new correct install events for each meter.

    Note: The Swap Meters button is disabled until all field activities created from the process flow are in the Completed state.

    This process also retrieves any impacted Accounts, Service Agreements, and frozen Bill Segments associated to the each meter's service point and device, and creates an Off Cycle Bill Generator for each service agreement based on the Swap Meters Service Script defined on the Cross Installed Meter Request Type.

    If the Create Customer Contact drop-down list on the Cross Installed Meter Request Type is "Yes", this process also creates customer contacts based on the Contact Class and Contact Type defined on the Cross Installed Meter Request Type.

    When the process completes the Insights box will display a "Swap Meters successfully performed." message, the Swap Meters button will be disabled, and the Next button will be enabled.

    If an error occurs, error information will be displayed above the Swap Meters button.

  6. Click Next to move to the Correct Bill Segments panel. Click Previous to return to the Swap Meters panel.

    The Correct Bill Segments panel displays a summary of impacted bill segments for each Off Cycle Bill Generator that can be corrected. To the right of each summary is a View Bill Segments link, and below each is a Skip button.

  7. Optional. Click View Bill Segments to view additional details about the Off Cycle Bill Generator. This displays a table that includes the calculated Original AmountRebill Amount, and Net Difference for each bill segment (and transitions the Off Cycle Bill Generator to the "In Review" state). Note: This process can take a few minutes to process, depending on the number of bill segments.

    If the Allow Adjustment drop-down list on the Cross Installed Meter Request Type is set to "Yes", the panel displays a Create Adjustment button.

    If the Allow Rebill drop-down list on the Cross Installed Meter Request Type is set to "Yes", the panel displays a Rebill button.

  8. Adjust, rebill, or skip each Off Cycle Bill Generator as appropriate:

    • Click Create Adjustment to create an adjustment for the total Net Difference, and transition the Off Cycle Bill Generator to the "Adjustment Created" state. Adjustments created in this way are based on the Adjustment Type defined on the Cross Installed Meter Request Type.

    • Click Rebill to rebill the impacted bills and bill segments and transitions the Off Cycle Bill Generator to the "Rebilled" state.

    • Click Skip to do nothing and transition the Off Cycle Bill Generator to the "Canceled" state.

    When all bill segments for both service points have been either rebilled, adjusted, or skipped (and the Off Cycle Bill Generators have been transitioned to either "Rebilled", "Adjustment Created", or "Canceled"), the Next button will be enabled.

  9. Click Next to move to the Summary panel. Click Previous to return to the Correct Bill Segments panel

    The Summary panel opens, displaying Corrected Meter Installation , Corrected Bill Segment Information, and Customer Contacts sections.

    The Corrected Meter Installation section displays the updated meter and service point information for each meter and service point, including new install events.

    The Corrected Bill Segment Information displays lists of corrected bill segments for each meter and service point.

    The Customer Contacts section displays the customer contacts created for each meter and service point.

  10. Click Finish to mark the process flow as “Closed”.

Opening a Cross Installed Meter Process

Use the following procedure to search for and open a previously-created cross installed meter process:
  1. Select Menu, Process Flow. The Process Flow Query portal opens.

  2. Select "Cross Installed Meter" from the Process Flow Type drop-down list.

  3. To search by user, enter a user ID in the User field.

  4. To search by date range, enter the appropriate start and end dates in the Update Date/Time Range fields.

  5. To include Completed process flows in your search, check the Include Completed checkbox.

  6. Click Search.

    The Process Flow Query portal displays a list of process flows that match your search criteria.

    The Resume column displays a Resume button for process flows currently in process. The Process Flow column displays an ID link for completed/closed process flows.

  7. To open an in-process process flow, click Resume for the process you wish to view and/or work with. The selected process flow opens on the Swap Meters panel in the Process Flow portal.

  8. To open a closed process flow, click in the ID link in the Process Flow. The selected process flow opens on the Summary panel in the Process Flow portal.

Initiating Cross Installed Meter Process Flows from Field Activities

There can be situations in which a field crew discovers that a meter is installed at an incorrect customer service point. For instance a crew might be taking a manual meter reading or performing some other field activity when they realize that the error. Field crews can initiate a Cross Installed Meter process flow by providing the correct meter information (the meter's badge number) as part of the completion information sent back to the field activity (via an Inbound Communication).

To create a a Cross Installed Meter process flow in this way, the inbound communication must include a "CROSSEDMETER" Field Activity Remark Type (from the Field Activity Remark Type extendable lookup) in the Completion Details/Completion Information/Remark Types section, and the Badge Number of the meter physically installed at the service point in the Response Details/Message Details/Utility Completion Information/Cross Installed Meter section.  When the inbound communication is received by the field activity and the field activity is completed, it creates a completion event based on the Create Meter Process Completion Event (X1-CreateCrossedMeterProcess) business object which instantiates a Cross Installed Meter process flow and an associated To Do entry. The Process Flow type and To Do type to create are derived from the Cross Installed Meter action method (See Configuring Cross Installed Meter Processing in the Administrative User Guide for information about configuring the Cross Installed Meter Action Method).

Inbound communications of this type can be created using the Field Activity Inbound Communication (D1-FieldActivityIBComm) Inbound Web Service or manually using the Communication portal.

When the new Cross Installed Meter process flow is created, the Service Point ID and Meter ID defined in the field activity are used to populate the "Meter 1" information. Note that the Investigate option is disabled for Meter 1 for process flows created this way. The actual meter badge number in the physical world and the service point where it's installed in the application are used to populate the "Meter 2" information.

See About Service Order Field Activities for more information about field activities. See About Communication In for more information about inbound communications. See Understanding Inbound Web Services in the Administrative User Guide for more information about using and invoking inbound web services.