8.7.3 Utilities Failure
This topic gives the lists of Utilities failures that can occur.
- Power Supply failure
- Variation in Power Supply/Temperature/Humidity
Power Supply Failure
- If advanced warning of power failure is announced Data Center Manager should make alternative arrangements
- The Data Center Manager should contact technicians
- Power off all the machines
- Report to Fund Manager, the agencies and the REG
When the power is restored a refresh is needed for the system to start again. If power off is extended to such an extent that the AMC operations are hampered alternate arrangements like Gensets should be arranged so atleast the online branches are accessed.
Variation of Power Supply/Temperature/Humidity
- The Data Center Manager should contact technicians
- Power off all the machines
- Report to Fund Manager.
If variation in power/temperature/humidity is off to such an extent that the AMC operations are hampered, alternate arrangements like Gensets, stabilizers should be arranged so atleast the online branches are accessed.
Parent topic: Potential for Exposure and Containment Measures