7.1 Current Status Report
This topic gives an overview on Current Status Report.
Current Status Report should be sent to the Head of Implementation every fortnight from the day you begin the project.
- Work completed during the fortnight
- Work scheduled for the next fortnight
- Problems encountered during the fortnight
- Billing details
Current Status Report Sample
The People:
- Ms. Annabel Smith (IT Head)
- Mr. Jim Hacker (Systems Manager)
- Sylvia John
- Ramkrishnan S
Reporting Period: 15/03/98 to 31/03/98
Table 7-1 The Schedule
Activity | Planned Start and End Date | Actual Start and End Date | Responsibility | Remarks |
---|---|---|---|---|
S/W Installation | 15/03 19/03 | 17/03 20/03 | FCIS | Given below |
User Training | 22/03 25/04 | 23/03 In progress | FCIS | Given below |
Database Set up | 24/03 30/04 | 24/03 In progress | FCIS | Given below |
Remarks: Software installation was delayed because hardware was not available. User training was delayed because a few key users were on leave. Database set-up has begun.
Action Items:
Table 7-2 Action Items
Activity | Planned Start and End Date | Actual Start and End Date | Responsibility | Remarks |
---|---|---|---|---|
Code Structures | 08/04 | NA | FCB | NA |
General Ledger | 08/04 | NA | FCB | NA |
List of Customers | 08/04 | NA | FCB | NA |
Achievements during the period:
Software installation completed.
User training for Data Entry module completed.
Outstanding Issues: None
Plan for the Next Fortnight: User training for Foreign Exchange and Money Markets. Database set-up for Branch Parameters, Customers, General Ledger.
Billing details:
Professional working days: 10 working days + 1 Saturday
Milestone achieved for billing: S/W installation
Expenses to be billed to client: Airfare and incidental expenses to Melbourne.
Parent topic: Statutory Report