7.1 Current Status Report

This topic gives an overview on Current Status Report.

Current Status Report should be sent to the Head of Implementation every fortnight from the day you begin the project.

It should give the following information:
  • Work completed during the fortnight
  • Work scheduled for the next fortnight
  • Problems encountered during the fortnight
  • Billing details

Current Status Report Sample

The People:

Customer
  • Ms. Annabel Smith (IT Head)
  • Mr. Jim Hacker (Systems Manager)
Oracle Financial Services
  • Sylvia John
  • Ramkrishnan S

Reporting Period: 15/03/98 to 31/03/98

The Schedule:

Table 7-1 The Schedule

Activity Planned Start and End Date Actual Start and End Date Responsibility Remarks
S/W Installation

15/03

19/03

17/03

20/03

FCIS Given below
User Training

22/03

25/04

23/03

In progress

FCIS Given below
Database Set up

24/03

30/04

24/03

In progress

FCIS Given below

Remarks: Software installation was delayed because hardware was not available. User training was delayed because a few key users were on leave. Database set-up has begun.

Action Items:

Table 7-2 Action Items

Activity Planned Start and End Date Actual Start and End Date Responsibility Remarks
Code Structures

08/04

NA FCB NA
General Ledger

08/04

NA FCB NA
List of Customers

08/04

NA FCB NA

Achievements during the period:

Software installation completed.

User training for Data Entry module completed.

Outstanding Issues: None

Plan for the Next Fortnight: User training for Foreign Exchange and Money Markets. Database set-up for Branch Parameters, Customers, General Ledger.

Billing details:

Professional working days: 10 working days + 1 Saturday

Milestone achieved for billing: S/W installation

Expenses to be billed to client: Airfare and incidental expenses to Melbourne.