5.6.3 Setting Task Precedence
After you have created a task, you must indicate which tasks must be executed prior to the newly created task in a batch.
- Log in as the Alert Viewer Administrator. The OFSAAI Applications page is displayed.
- Click Financial Services Money Laundering.
- In the Navigation List, select Common Tasks, then select Operations, then Batch Maintenance. The Batch Maintenance page is displayed.
- In the Batch Name section, select the batch that you want to set task precedence for.
- In the Task Details section, click
. The Task Precedence Mapping window is displayed.
- Move the tasks which must be executed prior to this task from the Available Tasks pane to the Selected Tasks pane.
- Click OK after you have selected all tasks which must precede the task. The selected tasks are listed in the Precedence column of the Task Details section.