Projected Supply Usage

To view this report:

  1. Filter by region, country, type, or location ID.
  2. Select the number of days for the projection.
  3. Select whether to display only deficiencies.
  4. Click Recalculate Projection.

This report displays the following information about the projected supply usage.

This table describes all possible fields for the report. Data in the report appears only in fields applicable to the study. Some fields might not appear in your report, and some fields could have different names.

Column

Description

Region

Area where the site or depot is located (example: Asia).

Country

Country where the site or depot is located (example: Japan).

Type

Whether the data is for a depot or site.

Location ID

Unique identification number for the depot or site.

Name

Name of the depot, or the last name and first name of the Principal Investigator.

Unit Code

Code for the unit type (example: A, B, or C).

Unit Name

Description of the unit.

Projected Days

Number of days projected from the current date.

Required

Number of units required based on the project days. For depots, this quantity accounts for all sites that the depot supplies. Required quantities are calculated for active subjects who are randomized in the study.

Available

Number of available drug units excluding units in transit.

Difference

Number of units required minus available units and units in transit.

In Transit

Number of units in transit to the site or depot.

Resupply Type

Name of the resupply type.

Min Buffer

Minimum buffer per drug unit type.

Max Buffer

Maximum buffer per drug unit type.

Screened

Number of subjects screened and considered active. For depots, this number accounts for subjects screened at all sites that the depot supplies.

Randomized

Number of subjects who have been randomized and are considered to be active. For depots, this number accounts for subjects screened at all sites that the depot supplies.