Run the Audit Trail Update Tables Concurrent Program
After you have defined CDR as the audit installation, run the Audit Trail Concurrent Program to enable auditing.
-
From the View menu, select Requests. The Find Requests pop-up appears.
-
Click Submit a New Request. The Submit a New Request pop-up appears.
-
Select Single Request and click OK.
-
From the Name drop-down list, select AuditTrail Update Tables and click OK. The system returns you to the Submit Request window with AuditTrail Update Tables displayed in the Name field.
-
Click Submit. A windows pops up if you want to proceed with the request submission or change the default request parameter value.
-
Click OK. A window pops up with the Request ID and asks if you want to submit another request.
-
Make a note of the Request ID and click No.
Monitor the Job: To monitor the job's progress:
Parent topic: Start Journaling Internal Tables