PreviousNext
JavaScript must be enabled to correctly display this content
Approving a Single Request
To approve an Oracle Access Request with the row level
action, click the ellipsis (“…”) under the Action column.
Click Approve Access.
An ‘Approve Access’ drawer opens and shows the access details.
The Access End Date is pre-populated with the date corresponding to
the requested duration of the support access. (Access start date will
be the point in time that the request is being approved in determined
by the approval.)
Confirm by clicking Approve request in the Approve Access drawer.
You have successfully granted the requested support access for
the selected row.
Note:
If the user already has access to a requested location
and role, an attempt is made to extend this existing access by the
requested access duration (with a maximum total access duration of
180 days). If the extended access exceeds 180 days, the request fails
and the existing access grant for the respective location and role
is not changed.
Note:
You can see all active support
access grants in the Oracle Support Access tile. This shows all the
currently active Oracle support access for locations to which you
have administrative access.