Creating a job schedule for an adapter

  1. Select Admin > System > Adapters.
    The Adapters page appears.
  2. Click the Get Requests or the Return Codes (This image depicts the Return Codes icon) icon for an adapter.

    Note:

    If a schedule already exists for the adapter, the icon appears blue (This image depicts the Return Code icon in blue. This happens if a schedule exists for the adapter.).
    The Schedule [Adapter Name] page appears.
  3. Create a schedule.
    • To create a schedule based on days of the week and time of day, complete the information on the page using the descriptions in Schedule [Adapter Name] Job—Basic page.
    • To create a schedule based on months, days of the week, and time of day:
      1. Click Advanced.

        The Schedule [Adapter Name]—Advanced page appears.

      2. Complete the information on the page using the descriptions in Schedule [Adapter Name] Job—Advanced page.
  4. Click Save.