Table 5-2 Schedule Configuration

Field Description Modifiable?

First Run Business Date

Date when batch was run for the first time. See subsection "Business Date Explained" in the "System Configuration" section of the POM User Guide.

No

Data Retention Days

Number of days historic data is to be retained in POM.

Yes - Recommended value is 30 days.

Long Run Average Multiplier

Number which is multiplied by a job's average run time or Threshold Runtime (if provided) to determine the threshold which, when exceeded, the job is deemed long running.

Yes - Usually a number between one and three.

External Dependencies

Indicates whether POM will respect external dependencies or not. They are usually dependencies on customers' internal processes.

Yes - Valid values are Y or N.

Inter-schedule Dependencies

Indicates whether POM will respect external dependencies or not. Those are dependencies on other schedules.

Yes - Valid values are Y or N.

Callback mode

This is also known as External Status Update Mode. Depending on the value, the customer's system is notified of success or failure of any job in the entire schedule. The value set here is overridden by this same setting for any individual job defined on the other job-specific tabs.

Yes - Valid values are ALL, FAILED or NONE.

When value is NONE, no callback is made.

When value is ALL, callback is made on either success or failure.

When value is FAILED, callback is made only on failure