Verify the Site is Ready for Installation

Survey the installation site and make sure it meets all requirements.

Ensure that the installation site has the following:

  • Sufficient space to install and maintain the servers.
  • Trained representatives to install the equipment. More than one person might be required to install equipment in the rack or to remove equipment from the rack.
  • Correct configuration and versions of firmware available for tape drive encryption end points (see Table 1-4).
  • Rack suitable for KMA installation.