Turn On the Library

Turn on the library to start initialization.

  1. Open the rear doors of the Base Module (and any Drive Modules if present).
  2. If necessary, turn on the rail controller modules at the top of the Base module.
    Rail controller location
  3. Turn on the breaker for all PDUs.

    Note:

    You can turn on the PDU and rail controller breakers in any order. However, you must turn on all breakers within two minutes of turning on the first breaker.
  4. The initialization sequence will begin. If someone opened an access door while the library was off, the library performs a full audit (unless you selected bypass audit in the settings before turning off the library).