Complete the following checklist to ensure that the data center room requirements are met. For information about the data center requirements, see Flooring Requirements.
Data Center Room Checklist Items | Yes | No | N/A | Comment |
---|---|---|---|---|
Has the Exalogic machine location been allocated? |
||||
Is there a vacant location for the new equipment? |
||||
Does the floor layout meet the equipment maintenance access requirements? |
||||
Is there adequate space available for maintenance? |
||||
Will the equipment be positioned so that the exhaust air of one rack does not enter the air inlet of another rack? |
||||
Have cabinet stabilization measures been considered? |
||||
Does the raised floor satisfy the weight requirements for the new hardware? |
||||
Can floor tiles be removed without permission to accommodate service? |
||||
Are there cable routing channels or cutouts? |
||||
Are you providing any additional hardware? |
||||
Is the hardware you are providing fully compatible with the Exalogic machine? |
||||
Will the new hardware location require any non-standard cable lengths? |
||||
Is the floor to ceiling height a minimum of 2914 mm or 2.9 m (9.6 feet)? |
||||
Is the depth of the raised floor a minimum of 46 cm (18 inches)? |