Flow Manufacturing Setup

This chapter describes the processes involved in setting up Oracle Flow Manufacturing.

This chapter covers the following topics:

Setup Objectives

You first need to perform related product setup steps before implementing Oracle Flow Manufacturing setup steps.

Products and Parts

The objectives of products and parts setup are to create both finished goods and component items, and to group the products and parts in logical product families. This facilitates demand forecasting and production assembly. To implement Oracle Flow Manufacturing it is necessary to set up:

Work in Process

Set up parameters in the following tabbed regions of the Work in Process Parameters window:

Demand Management

In designing a flow line, a company analyzes the market forecast for the products and takes a look at the long term forecast. In demand management you can assign planning percentages to members of the product family, and use the relationship between a product family item and its members in:

Sales orders for member items consume the forecast for the member items as well as for the product family.

Setup Steps

The following flowchart depicts the steps that you need to perform to set up Flow Manufacturing. Some of the steps outlined in this flowchart are Required and some are Optional. Required Step with Defaults refers to setup functionality that comes with pre-seeded, default values. You should review the defaults and decide whether or not to change them to suit your business needs. You need to perform Optional steps only if you plan to use the related feature or complete certain business functions.

the picture is described in the document text

Flow Manufacturing Perquisite Steps

  1. Create Flow Assemblies and Components

    In Oracle Inventory you can define inventory organizations and the items to be produced. You need to define both finished goods and component item inventory records. Once defined, assign items to organizations. Templates are used to create similar items, and they simplify item definitions. See: Defining an Item, Oracle Inventory User's Guide, and Item Templates, Oracle Inventory User's Guide

  2. Define Product Families and Product Family Members

    You can plan based on the planning percentages and effectivity of the product family members. Product families are optional. Typically, a flow line is designed for one specific product family containing a mix of products. However, a flow line can be designed for multiple product families. See: Creating Product Families, Oracle Bills of Material User's Guide

  3. Define Flow Lines

    Flow lines are manufacturing work areas where you produce a flow assembly, usually associated with a routing. You can build many different assemblies on the same line, at the same time. See: Defining Production Lines, Oracle Work in Process User's Guide

  4. Create Product Synchronization

    The flow line is an organization of resources and departments. Once the flow line is defined, processes and activities (events) are applied to create operations on the flow line. Product Synchronization defines the processes used to make each product including flow routings, events, processes, and line operations. The Graphical Line Designer Workbench is used to create these records and network connections, and key calculations. See: Accessing Graphical Line Designer Workbench Windows

  5. Balance Flow Lines

    Oracle Flow Manufacturing provides a planning tool, the Mixed Model Map Workbench, to calculate process times and volumes to balance resources and events, and optimize flow line efficiency. The objective is to balance lines at the expected peak demand. See: Overview of the Mixed Model Map Workbench

  6. Create Pull Sequences

    Flow Manufacturing uses a kanban pull replenishment system to signal material requirements and pull material from its defined source for demand. Kanban pull sequences define the relationship between an item, its point of use and its point of supply. The attributes of a pull sequence define the kanban size, number of kanban containers, replenishment time, safety stock, lot multiplier and method of replenishment. See: Pull Sequence Window

  7. Setup Kanban Planning

    Kanban setup and planning uses the Graphical Kanban Workbench for transactions. The Graphical Kanban Workbench combines kanban setup, kanban planning, pull sequence definition, planning simulation, and kanban transactions. An item is pulled through the kanban system, rather than pushed by the planner. The kanban location for a kanban item is the designated location where that item is stored, and where replenishment is delivered. For every kanban item, there is a pull sequence—a series of kanban locations that models the actual replenishment network on the shop floor or external suppliers, specifying the sequence to follow to obtain the kanban item. See: Accessing the Production Region and Accessing the Planning Region

  8. Setup Scheduling Rules

    The primary objective of Line Scheduling is to synchronize production with customer demand. This objective is achieved through the Line Scheduling Workbench. You can use the system provided rules, or set up your own custom scheduling rules. See: Defining Scheduling Rules, Oracle Flow Manufacturing User's Guide

  9. Enable profile Option for Flow Sequencing

    The Flow Manufacturing profile option, FLM:Enable Flow Sequencing is required for new customers to Oracle Flow Manufacturing if you have Flow Sequencing installed. The profile option is not required for customers upgrading from previous versions of the software. See: Profile Option

  10. Setup Sequencing Constraints

    Sequencing is used to consider your demands and determine a sequence for building assembly items. You use attributes, constraints, and group them into rules for assigned production lines:

    • Attributes are a characteristic of your demand

    • A constraint is a restriction enforced on an attribute

    • Rules are a grouping of prioritized constraints defined for the attributes

    See: Overview of Flow Sequencing

  11. Setup Flow Execution Workstation

    The primary objective of setting up production execution is to meet daily production requirements. This objective is achieved through Flow Execution Workstation. You can use the Flow Execution Workstation to perform flow line transactions and track the flow of work throughout the shop floor. The Flow Execution Workstation provides a comprehensive set of features for completing assemblies, and viewing details of component and resource information. See: Overview of the Flow Execution Workstation

Profile Option

During implementation, you set a value for each user profile option to specify how to access and process data. You are required to provide a value for a Required profile option. An Optional profile option provides a default value, which you alone can change if you do not want to accept the default.

FLM:Enable Flow Sequencing

This site level profile option is required for new customers to Oracle Flow Manufacturing if Flow Sequencing is installed. Enable Flow Sequencing can legally be set to Yes for customers licensed for Oracle Flow Sequencing.

The profile option is not required for customers upgrading from previous versions of the software. The default value is No.

Fixed Component Usage

Flow Manufacturing supports fixed component usage for quantity calculations. You can define a fixed usage on a bill of material. For these components, the total quantity required remains the same without regard to the build quantity, and consumption quantity does not vary with the assembly quantity produced. This feature is used when a quantity of a component is used for manufacturing setup, production startup, or during the course of the manufacturing process.

Enable this feature in the Bills of Material window by setting the Basis field to Lot. For lot type basis, component usage is fixed per lot. See: Creating a Bill of Material, Oracle Bills of Material User's Guide

The fixed component usage feature is not available for components of:

Fixed component usage requirements affect kanban planning, replenishment, sequencing, and feeder line synchronization calculations: