You can schedule a load plan by defining its ODI context, ODI local agent, a level of logging information, status of the schedule, and frequency of occurrence in Configuration Manager.
To schedule a load plan for execution:
- In the Tasks pane of Configuration Manager, select Manage Load Plans under Load Plans Administration.
The Manage Load Plans page is displayed.
- In the Load Plans list, select the load plan you want to schedule.
- Select the Schedules tab.
- Click Add in the Schedules tab toolbar.
The Schedule Load Plan dialog is displayed.
- Select:
- Click Schedule.
Note:
If the ODI Agent is already running at the time you define the schedule in
Oracle BI Applications Configuration Manager, then you must click the Update Schedules icon in the toolbar to add the schedule to the ODI Agent scheduler.