Previous  Next          Contents  Index  Navigation  Glossary  Library

Required Hours

Required hours represents the number of resource hours required per resource unit to build one unit of an item at an operation. Required hours are derived from the usage rate and unit of measure you specify in Oracle Bills of Material. See: Resource Usage.

If you have defined a usage rate using a unit of measure other than hours, then the bill of resource load process converts it to an hourly rate. In the Bill of Resources Example, building one unit of C at operation 20 requires 8 hours per unit of D1, R2.


         Previous  Next          Contents  Index  Navigation  Glossary  Library