| Previous | Next | Contents | Index | Navigation | Glossary | Library |
If you have defined a usage rate using a unit of measure other than hours, then the bill of resource load process converts it to an hourly rate. In the Bill of Resources Example, building one unit of C at operation 20 requires 8 hours per unit of D1, R2.