Viewing RCCP
You can display the rough-cut capacity requirements for a master schedule you specify to compare the capacity requirements to available capacity and review the weekly capacity utilization. You can display capacity plans for individual resources, in hours per resource per week, or for production lines, by production rates per week per line.
Prerequisites
Before you can review the RCCP, you must load or manually enter at least one bill of resources.
To review routing-based rough cut capacity:
2. Select a master Schedule.
3. Select a Bill of Resources set to calculate the rough-cut capacity plan for the schedule.
4. Optionally, enter a Simulation Set to include the capacity modifications within the simulation set when calculating available capacity.
The plan horizon date you specified when you launched the plan is used if you do not enter a Cutoff Date.
Attention: To minimize the amount of processing time, enter an earlier date.
7. Optionally, enter a department class.
8. Optionally, enter a Department for which you want to display the rough-cut capacity plan.
9. Optionally, enter a Resource Type, such as Machine, Person, or Space.
10. Optionally, enter a Resource associated with the Department.
11. Choose Resource to display the available and required capacity for the department and resource for a given master schedule in the Resource window.
Attention: You can query in Utilization to see for which dates a department/resource is overloaded/underloaded. For example, specify ">100" in the query to see which weeks this department/resource is overloaded. See: Performing Query-by-Example and Query Count, Oracle Applications User's Guide.
To review rate-based rough cut capacity:
2. Select a master Schedule.
3. Select a Bill of Resources set to calculate the rough-cut capacity plan for the schedule.
4. Optionally, select a Simulation Set to include the capacity modifications within the simulation set when calculating available capacity.
5. Enter a Cutoff Date up to which to display the rough-cut capacity plan.
The plan horizon date you specified when you launched the plan is used if you do not enter a Cutoff Date.
Note: To minimize the amount of processing time, enter an earlier date.
7. Enter a production Line for which you want to display the rough-cut capacity plan.
8. Choose Resource to display the available and required capacity for the production line for a given master schedule in the Resource window.
Attention: You can query in Utilization to see for which dates a department/resource is overloaded/underloaded. For example, specify ">100" in the query to see which weeks this department/resource is overloaded. See: Performing Query-by-Example and Query Count, Oracle Applications User's Guide.
To generate a graphical display of capacity data
You can generate an Excel workbook for the CRP or RCCP information of one or more items. The workbook contains:
- a graph comparing load to capacity
- optionally, a pivot table
3. Choose Horizontal Capacity Plan.
See Also
Creating a Bill of Resources
Loading a Bill of Resources
Creating Simulation Sets
Defining Resource Groups
Routing-Based RCCP
Rate-Based RCCP
Overview of Repetitive Planning
Bill of Resources Example
RCCP Rate-Based Report
Defining RCCP Display Options
Defining CRP Display Options