Launching the Supply Chain Planning Process

Supply Chain Planning users can launch the planning process for a multiorganization material requirements plan (MRP) or master production schedule, or a distribution requirements plan (DRP). The planning process uses the input from a supply schedule (a DRP, an MPS, or an MRP) or a demand schedule to determine the quantities and timing of the items to be manufactured or purchased.

Prerequisites

Before you can launch the planning process, you must:

   To launch a supply chain planning process:

See Also

Overview of the Memory-based Planning Engine

Phases of the Planning Process.

Overview of Material Requirements Planning

Overview of Capacity Planning

Submitting a Request

Enabling the Memory-based Planning Engine