Completing Operations and Recording Scrap

This chapter provides an overview of the online completions process and discusses how to:

Click to jump to parent topicUnderstanding Recording Completions and Scrap

Within a manufacturing enterprise, you need to track end items as they make their way through the production area. With PeopleSoft Manufacturing, you can manage production by orders, repetitive schedules, backflushing, or creating a schedule to record completions and scrap after you have completed production. Subcontracted operations are fully supported. You can assign serial and lot numbers to completed end items and complete end items to containers while moving them to inventory or to another production area. While recording completed operations, the system accumulates manufacturing costs and variances. You can also record actual machine and labor hours for each production order or production schedule.

PeopleSoft Manufacturing tracks the serial genealogy of production. This enables you to trace the movement of a specific serialized assembly and its components throughout the manufacturing process.

Note. During completions, you can choose from serial IDs previously associated with a production ID, or you can enter a new serial ID for which the system automatically creates the serial association. Additionally, lot auto numbering only applies to configured orders.

PeopleSoft Manufacturing tracks the costs of material, labor, outside processing, and machines used to manufacture a product and manages the transactions necessary to report and track the status of a particular order or schedule by day and shift. The system supports these order types:

If you're recording completions and scrap for a production ID with subcontracted operations, you record the operation completions for the subcontracted operations slightly differently than for in-house production.

You can also record completions and scrap using electronic data collection.

See Recording Completions and Scrap Using Electronic Data Collection.

Recording Completions with Multiple Outputs

You can also record completions and scrap for production IDs and production schedules that have multiple outputs. Multiple outputs consist of:

primary items

The main outputs from the manufacturing process.

co-products

Items, along with the primary item, that are planned for and produced as part of the manufacturing process. Co-products share the cost of the process; there may be independent demand in planning for the primary item.

by-products

Items that can be either waste by-products, which need to be disposed, or recycle by-products, which can be used as inputs to other processes. By-products are incidental to the process and have either a relief (negative) cost for recycle by-products or a disposal (positive) cost for waste by-products. There is typically not independent demand for by-products.

Expected Output When Using Yield by Operation

The system recalculates the expected output quantities when over-completions or over-scrap are performed. Over-scrap is when the scrap quantity exceeds the expected scrap, based on the operation yield. For example, the system recalculates a new output quantity if the actual scrap quantity exceeds the expected scrap quantity at an operation.

Transferring Completions Data to PeopleSoft Quality

If your installation includes PeopleSoft Quality, and you have defined quality configuration information and quality plans in PeopleSoft Quality for a manufactured item and its process, then the Quality link is active on the Record Completions/Scrap page. You click this link to transfer to PeopleSoft Quality to initiate a data entry session to record quality control information for the manufacturing process.

Completions Actions and Effects to Quantities on Hand

This table lists the results of completions actions:

Completions Action

Results

Recording positive completions

Decreases the business unit's on-hand quantity of the components, and increases the business unit's on-hand quantity of the completed end item.

Decreases the storage location's quantity for the components, and increases the storage location's quantity for the completed end item.

Decreases the lot quantity on-hand for lot-controlled components and increases the lot quantity on-hand for the completed end item, if it is lot-controlled.

Recording negative completions

Increases the business unit's on-hand quantity of the components, and decreases the business unit's on-hand quantity of the end item.

Increases the storage location's quantity for the components, and decreases the storage location's quantity for the end item.

Increases the lot quantity on-hand for lot-controlled components and decreases the lot quantity on-hand for the end item, if it is lot-controlled.

Recording completions to a non-WIP, nettable location

Increases the business unit's quantity available for the completed end item.

Recording negative completions to a non-WIP, nettable location

Decreases the business unit's quantity available for the end item, if the end item comes from a nettable, available, non-WIP location.

Recording positive completions to a nettable, available WIP location

Increases a business unit's quantity reserved for the completed end item.

Recording negative completions from a nettable, available WIP location

Decreases a business unit's quantity reserved for the end item.

Decreases the lot quantity available for the completed end item.

See Also

Collecting Quality Data

Subcontracting

Maintaining Bills of Material

Click to jump to top of pageClick to jump to parent topicManage Production Using Discrete Orders

You can manage discrete orders for regular, rework, or teardown production by creating production IDs for each production quantity that you want to track. Once you've created the production ID, you release production, and then either generate pick lists to issue material to production or maintain a maximum quantity on hand for components in a WIP location.

Once production begins on the shop floor, perform the following steps. These steps assume that all operations are performed in-house and none of the operations are subcontracted.

To record completions and scrap for in-house production IDs:

  1. Indicate whether the business unit will record completions and scrap production IDs using the online or deferred method by selecting the PID Completion option on the MFG BU Prdn Options page. Select one of these:

    1. Online: The background process calculates the associated production costs (such as earned labor and machine hours) and overhead conversion costs and consumes material utilizing the issue or replenishment issue methods.

    2. Deferred: This option indicates that you're running the completions process at a later time.

      All associated production costs are calculated when the completions update background process is run. You must run the Prdn Compl/Scrap process (production completions and scrap process) if you select this option.

  2. Record completions and scrap quantities for in-house production using the Record Completions/Scrap page.

    Record completions by operation, by count point, or for the entire production quantity, or perform a partial backflush of completed end items.

  3. (Optional) If you're completing a production ID with multiple outputs, the Outputs Detail area appears.

    You can complete planned or unplanned by-products at any operation. Scrapped end items are recorded at the batch level, but not for each output. You must record completions and scrap for primary items and co-products at the last operation.

  4. (Optional) Change component information using the Edit/Issue Components page.

  5. (Optional) Transfer completions data to PeopleSoft Quality by clicking the Quality link.

  6. (Optional) If you're using serial in production or serial- or lot-controlled items, and the components are issued to production using the Replenish or Issue method, select the serialized components or lots from which to consume the components.

    1. Automatically generate serial numbers by using the Rapid Serial Numbers page.

    2. Access the Edit/Issue Express page, or click the button next to the serial- or lot-controlled component on the Edit/Issue Components Summary page. For lot-controlled components you can use the backflush lot selection rule to automatically select lot IDs during backflush. For more information on the backflush lot selection rule, see the "Automatically Consuming Lot-Controlled Stock During a Backflush" section of this chapter.

    3. Use the Route-To PID/Stor Locations (route to production ID and storage locations) scroll area on the Record Completions/Scrap page to assign a lot if the completed end item is lot-controlled.

      Note. You can move end items to an existing lot or create a new lot.

  7. Move completed end items out of production.

    You may route them to a production ID, to another production area for further processing, or to a stores inventory location. You cannot route waste by-products.

    1. (Optional) Click the Apply Defaults link to route the end items to a default putaway location.

      Note. The completions process puts away items in their standard units of measure (UOM).

    2. (Optional) Select an alternate putaway location.

      Note. If you're routing the end item to another production ID, the putaway process is not required.

    3. If you are using serial genealogy, you must perform completions at the last operation.

      In addition, select the serial number for the appropriate assembly.

  8. (Optional) Run the Completions Update process.

    You run this process to update completions transactions that are staged by other processes, such as Edit Components updates, production completions, or subcontracted completions recorded through electronic data collection.

  9. (Optional) Make reversing entries to correct data entry errors.

    You can return components to their original storage location or to an alternate location. If you're returning lot- or serial-controlled components, you must select the serial IDs or lot IDs from which the components were originally consumed.

  10. (Optional) Move excess components out of WIP locations using the Maintain Inventory navigation.

    You can move these components to another production area or back to a stores inventory location. You can also move excess components from the production ID using the Kit issues transactions. Kit issue transactions are used for components whose issue method is Kit.

  11. Record actual labor and machine hours.

  12. Indicate that production is complete by using the Complete Production page.

Click to jump to top of pageClick to jump to parent topicManage Production by Day and Shift (Production Schedules)

PeopleSoft Manufacturing generates a schedule for processing by day and shift for regular production by:

  1. Record completions and scrap quantities for production schedules using the Record Completions/Scrap page.

    Record completions and scrap for the entire production quantity, or perform a partial backflush of completed end items. You can record completions for production schedules with multiple outputs. However, all multiple outputs and scrap must be completed at the last operation.

    Note. If a schedule for the production date and shift has not been created when recording end item completions and scrap, the system creates a production schedule and releases production.

  2. (Optional) If you're completing a production schedule with multiple outputs, the Outputs Detail area appears.

    You can add unplanned by-products. Scrapped end items are recorded at the batch level, but not for each output.

  3. (Optional) Change component information using the Edit/Issue Components page.

  4. (Optional) Transfer completions data to PeopleSoft Quality by clicking the Quality link.

  5. (Optional) If you're using serial- or lot-controlled items, and the components are issued to production using the Replenish or Issue method, you must select the serialized components or lots from which to consume the components.

    1. Automatically generate serial numbers by using the Rapid Serial Numbers page.

    2. Access the Edit/Issue Express page, or click the button next to the serial- or lot-controlled component on the Edit/Issue Components Summary page. For lot-controlled components you can use the backflush lot selection rule to automatically select lot IDs during backflush. For more information on the backflush lot selection rule, see the "Automatically Consuming Lot-Controlled Stock During a Backflush" section of this chapter.

    3. Use the Route-To PID/Stor Locations scroll area on the Record Completions/Scrap page to assign a lot if the completed end item is lot-controlled.

      Note. You can move end items to an existing lot or create a new lot.

  6. Move completed end items out of production.

    You may route them to a production ID, to another production area for further processing, or to a stores inventory location. You cannot route waste by-products.

    1. (Optional) Click the Apply Defaults link to route the end items to a default putaway location.

      Note. The completions process puts away items in their standard UOMs.

    2. (Optional) Select an alternate putaway location.

      Note. If you're routing the end item to another production ID, the putaway process is not required.

  7. (Optional) Run the Completions Update process.

    You run this process to update completions transactions that are staged by other processes, such as Edit Components updates, production completions, or subcontracted completions recorded through electronic data collection.

  8. (Optional) Make reversing entries to correct data entry errors.

    You can return components to their original storage location or to an alternate location. If you're returning lot- or serial-controlled components, you must select the serial IDs or lot IDs from which the components were originally consumed.

  9. (Optional) Move excess components out of WIP locations using the Maintain Inventory navigation.

    You can move these components to another production area or back to a stores inventory location.

  10. Record actual labor and machine hours.

  11. Run the Close Production SQR process to indicate that the production schedules are complete.

Click to jump to top of pageClick to jump to parent topicAutomatically Consuming Lot-Controlled Stock During a Backflush

Backflush is a method of consuming components for a production ID or production schedule. The system backflushes components with an issue method of Issue or Replenish. Typically, backflushing occurs when completion or scrap quantity is entered for an assembly. Backflushing consumes material from the WIP locations.

When consuming lot-controlled components, the backflushing process must decide which lot IDs to choose within the WIP location. The backflush lot selection rule enables you to determine which lot IDs are automatically selected for consumption when a backflush is performed. The backflush lot selection rule can be defined at:

The backflush lot selection rule defined at the business unit and item combination (the Define Business Unit Item - Manufacturing: General page) overrides the option selected at the business unit level (the MFG BU Prnd Options page).

See Defining Manufacturing Information for an Item.

See Setting Up Manufacturing Business Unit Production Options.

How the Backflush Process Uses the Backflush Lot Selection Rule

The backflush lot selection rule is used during the backflush process to determine the lots to consume from each WIP location for lot-controlled components. The Record Completions and Scrap-Edit/Issue Express page is one location where you can see some of the impacted fields:

If the backflush lot selection rule is Manual, then the backflush process does not default lot IDs. You must manually enter the specific lot IDs and the quantity from each lot for consumed lot-controlled components.

If the backflush lot selection rule is Earliest Expiration Date or Earliest Available Date, then the backflush process consumes lot-controlled components by choosing the lot IDs and quantities from each lot ID within the WIP locations. The following rules are applied:

The backflush lot selection rule cannot be applied to:

For these items, the backflush lot selection rule is set to the value of Manual.

Components Impacted by the Backflush Lot Selection Rule

The backflush lot selection rule is applied during backflush and impacts the following components:

The above components can be used in online or deferred mode. If you are using the online mode (PID Completion Option on the MFG BU Prdn Options page), the online pages display the results of the backflush lot selection rule; that is, the lot ID and quantity to be consumed from the WIP location. You can view and override the selected lot IDs and quantities. If you are using the deferred mode (PID Completion Option on the MFG BU Prdn Options page), the system does not consume the components until later; however, you can use the online pages to enter override lot IDs and quantities.

Using the online mode, if the backflush process has completed and then a field is changed that causes the pending quantities field to be recalculated, this causes a recalculation of backflush lot selection rule. Fields that trigger the recalculation of the pending quantities include:

In addition, entering a pending issue quantity or a pending yield loss quantity when there is no completion or scrap quantity triggers the calculation of the backflush lot selection rule. If the lot consumption fields have already been populated and then you manually change the pending issue quantity or a pending yield loss quantity, the system displays the following message:

Message Text: Recalculate the Lot IDs to consume (Y/N)?

Explanation: You have modified the pending issue or pending loss quantity for a component that contains values in its lot scroll. Select Yes to clear the lot scroll and repopulate based on the entered quantity - all other occurrences of this component on the component list which share the same WIP location will also have their Lot IDs recalculated. Select No to keep the pending quantity entered without changing the lot scroll - you will then need to modify the lot scroll so that its quantities correspond with the pending quantity entered. Select Cancel to cancel the action - the original pending quantity will be restored and the lot scroll will not be modified.

Using the Production Completions and Scrap Process with the Backflush Lot Selection Rule

Prdn Compl/Scrap (SFPDCDRV) process (Production Completions and Scrap process) can perform a backflush and looks to the backflush lot selection rule to determine the method for the lot consumption from the WIP locations. This Prdn Compl/Scrap process is located in both the SCM Integrations menu (SCM Integrations, Process Transactions, Manufacturing, Production Completions/Scrap) and the Production Control menu (Production Control, Process Production, Complete Production, Process Completions and Scrap). The Production Completions and Scrap process uses data stored in the BCT tables to update the production tables and can record completions and scrap for:

If you have selected the backflush lot selection rule of Earliest Expiration Date or Earliest Available Date, then the incoming files are not required to have a lot ID for consumed components. The lot ID is assigned during the Production Completions and Scrap process; therefore, the incoming files are not put in the error status for correction in the Transaction Maintenance component (SCM Integrations, Transaction Error Handling, Maintain Transactions, Transaction Maintenance). If the incoming file does contain some lot IDs for consumed components, then the Prdn Compl/Scrap process uses those entries rather than the backflush lot selection rule. In addition, the incoming files must contain the lot IDs for consumed components if you have selected the backflush lot selection rule of Manual.

See Running the Completions Update COBOL/SQR Process (SFPDCDRV).

Setting Up the Backflush Lot Selection Rule

Before changing the backflush lot selection rule in your PeopleSoft system, you should examine the physical movement in your WIP locations to:

Before changing the backflush lot selection rule, it is recommended that you process all pending transactions in the staging tables (BCT tables) that impact production completion. If pending transactions are in the BCT tables, use caution when changing the backflush lot selection rule on the MFG BU Prnd Options page or the Define Business Unit Item - Manufacturing: General page. Changing the rule can impact how the pending transactions are processed.

Click to jump to top of pageClick to jump to parent topicIntegrating PeopleSoft Manufacturing with a Third-Party System

You can integrate PeopleSoft Manufacturing with an electronic data collection system or a Manufacturing Execution System (MES), or both.

Electronic Data Collection

You can use electronic data collection to collect completions and scrap transactions, then import them to PeopleSoft Manufacturing. You can also collect and import actual hours transactions using electronic data collection.

For actual hours, the data collection method employs the same breakout of hour types as the online method such as setup, run, fixed run, and post-production. Electronic data collection allows for individual or crew reporting as well as single or multiple machine reporting.

Use the Actual Hours EIP to import actual hours information from a third-party system.

See Recording Completions and Scrap Using Electronic Data Collection.

Manufacturing Execution System (MES)

If you're integrating PeopleSoft Manufacturing to an MES, you can record operations completed, quantity completed, and scrap quantity in the MES. You can then import completion transactions to enable the optimization of production activities from production order launch to completion of finished goods. All production IDs, production schedules, and operations must be recognized in the PeopleSoft system; otherwise the system marks the transactions as errors in transaction maintenance. You then need to make corrections so that the transaction can be processed.

For multiple output transactions, you can record actual outputs in the MES, including completed quantities for co-products and by-products. You must send the completed output quantity if the batch quantity complete is not reported. You can report only unplanned by-products, not unplanned co-products.

You can also report the serial, lot, or container numbers for items produced or consumed in production. If the produced item requires lot, serial, or container details in the PeopleSoft system, the system marks transactions sent without this information as an error in transaction maintenance. For serial-controlled components or components that are both lot and serial-controlled, the serial numbers and lot IDs must be provided to the system or the transaction is marked in error to be corrected in transaction maintenance. For lot-controlled components, the incoming data must contain the lot IDs for consumed components if you have selected the backflush lot selection rule of Manual. If you have selected the backflush lot selection rule of Earliest Expiration Date or Earliest Available Date, then the incoming files are not required to have a lot ID for consumed components.

You can also report component consumption and communicate it to PeopleSoft Manufacturing using the Production Order Issue EIP. This EIP is a batch subscribe (inbound), asynchronous message.

When you pass component usage from the MES, all component consumption for a production order is sent, regardless of whether the quantity consumed was the default quantity. If components consumed are under serial or lot control, the lot or serial numbers are passed from the MES to update PeopleSoft Inventory. For lot-controlled components, the lot IDs can be automatically added by the Prdn Compl/Scrap (SFPDCDRV) process if you have selected the backflush lot selection rule of Earliest Expiration Date or Earliest Available Date.

The system validates component consumption transactions coming into the PeopleSoft system to ensure that the production IDs and items are valid in the business unit. The items must be valid for the BOM or as substitutes. If the consumption transaction would drive inventory negative in a business unit where negative inventory is not permitted, the system doesn't process the transaction.

See Also

Understanding SCM Integration

Recording Actual Machine and Labor Hours

Getting Started with PeopleSoft Manufacturing

Click to jump to parent topicPrerequisites

Before you begin production:

  1. Review the production documents, if available, to determine if any of the items are serial- or lot-controlled, or if there are any subcontracted operations.

  2. Verify that all items that you'll be manufacturing have been assigned to a production area.

  3. Verify that material has been issued directly to the production ID or that the production WIP locations have been stocked with adequate inventory.

    Use the Shortage report to identify any potential component shortages before beginning production.

Click to jump to parent topicCommon Elements Used in This Chapter

Production ID

The production order identifier.

Production Area

The area where the item is being manufactured.

Item ID

The name and description of the item being manufactured.

Op Seq (operation sequence)

The operation step where the item is being completed.

Config Code (configuration code)

A unique identifier for costing and inventory tracking purposes. The configuration code appears if the end item is a configured item.

Status

The current status of the production.

Prdn Type (production type)

The type of production being manufactured. Values are Production, Rework, or Teardown.

Prdn Start Qty (production start quantity)

The beginning quantity being produced for the selected production. The system considers any operation yield.

Prdn End Qty (production end quantity)

The ending quantity being produced for the selected production. The system considers any operation yield.

BOM Code

The BOM priority code used during the production of this item.

Routing Code

The routing priority code used during the production of this item.

Revision code

The default value appears if the item entered is revision-controlled.

Source Cd (source code)

Indicates if the production is Make or Buy.

Quality

Click this link to initiate a data entry session and access either the Data Entry - Subgroup Method page or the Data Entry - Sample Method page in PeopleSoft Quality, depending on the data entry method that you specified when creating the quality control plan. On the Data Entry pages in PeopleSoft Quality, you record quality control information for the manufacturing process for the item and then access the Record Completions/Scrap page.

Note. The Quality link is available for each end item in the Output Details scroll area. You can transfer completions data to PeopleSoft Quality for each end item.

Click to jump to parent topicRecording Completed Operations and Scrap for In-House Production IDs

At some point during the in-house production process, you must record completed operations and scrap. Using the Record Completions and Scrap component, you can:

Note. Primary items and co-products can be completed only at the last operation. By-products, such as recycle or waste, can be completed at any operation.

If you have enabled PeopleSoft Workflow, when you record end item scrap, the system sends notification to selected roles defined by you by using the Assembly PID Scrap Notification workflow. These roles might include a quality manager or a production control manager.

Click to jump to top of pageClick to jump to parent topicUnderstanding the Process of Recording Completions and Scrap for In-House Production IDs

With production IDs, you can:

Note. There is no difference between the method that you use to record completed and scrapped end items for regular production and the method that you use for rework production. When recording completions for teardown orders, you report the number of end items torn down. The system calculates the quantity of the teardown end items based on the quantity of the end items being torn down. As is the case with all production types, you can override the teardown quantity for each end item.

Using the Record Completions and Scrap component, you can record in-house operation or end item completions and scrap for production IDs with a status of:

Important! If you're using the production issue or production kit material issue method for regular production, you must still issue material to the WIP locations using the Pick Plan and Material Release components. If you're using the production replenishment method, ensure that sufficient inventory exists in the WIP location.

Click to jump to top of pageClick to jump to parent topicPages Used to Record Completions and Scrap for In-House Production IDs

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_COMPL_SELECTION

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection

Select a production ID to record completions and scrap.

You must define at least one production ID.

Record Completions/Scrap

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap

Enter completions and scrap information for production IDs.

In addition, use this page to move end items for production IDs with a single output or multiple outputs.

Production Scrap Details

SF_COMPL_SCRAP

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap

Click the Enter Scrap Data link.

Enter scrap quantities, if applicable.

Apply Defaults

SF_COMPL_DEFAULTS

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap

Click the Apply Defaults link.

Select the default putaway or alternate storage locations for completed end items.

Rapid Serial Numbers

MG_SERIALRG_PG_SBP

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap

Click the Generate Serial IDs link.

(Optional) Automatically generate serial numbers for production end items that are serial-controlled.

Note. You must define serial-controlled items in PeopleSoft Inventory.

Work Center Details

SF_WORK_CTR_SP

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap

Click a Work Center link in the Operations Data scroll area.

View work center-related information such as WIP locations.

Lot/Serial Number Selection

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Select the serial numbers of the serial-controlled components to be consumed during the completions process.

You must enter a pending quantity greater than zero for a serial-controlled component before the Lot/Serial scroll area becomes available.

Lot/Serial Number Selection scroll area

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Identify the lots from which you want to consume lot-controlled components.

You must enter a pending quantity greater than zero for a lot-controlled component before the Lot/Serial scroll area is available.

Complete Production

SF_COMPL_PRDN

Production Control, Process Production, Complete Production, Record Completions and Scrap

Click the Complete Production link.

Indicate that production has been completed for a selected production ID.

Production History

SF_TRANSHIST

Production Control, Define Production, Review Production Information, Production History

View production transaction history for production IDs.

Transaction History Details (inquiry)

SF_TXN_HIST_SP

Production Control, Define Production, Review Production Information, Production History

Click the Details button.

View production transaction history details based on:

  • Completions Detail

  • Component Consumption

  • Operation Detail

Click to jump to top of pageClick to jump to parent topicRecording Completed Operations and Scrapped End Items for Production IDs

Access the Production Selection page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection).

Unit and Production ID

Enter values for the production ID that you want to record completions and scrap.

Search

Click to retrieve the selected production ID.

Click to jump to top of pageClick to jump to parent topicDefining Completions and Scrap Information for Production IDs

Access the Record Completions/Scrap page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap).

Previous Completions Information

Prdn Start Qty (production start quantity) and Prdn End Qty (production end quantity)

Displays default quantity values from the Production ID Maintenance component. These values are updated whenever the quantity completed is changed.

Prdn% Completed (production percentage completed)

Displays the percentage of the batch production quantity that has been completed prior to this transaction.

Completed Qty (completed quantity) and Scrapped Qty (scrapped quantity)

Displays a quantity that represents the quantity that has been completed at the last operation. Scrapped quantity represents the quantity that has been scrapped at all operations.

Putaway Action

Select which putaway process to use. Options are:

  • Putaway at Receipt Save Time: Select to initiate the putaway process after you have recorded completions and saved the page.

    This method creates a schedule process, which automatically initiates the putaway process.

  • Stage for Putaway at Save Time: Select to designate that these completions will use the PeopleSoft Inventory putaway process at a later time.

Note. Upon saving the page, either stage the item for putaway or initiate the putaway process.

Item completions are not allowed if the end item or a component of the end item is on hold. Similarly, item completions are prevented if a co-product or recycle by-product is on hold.

However, completions are allowed for waste by-products with a hold status.

Print at Save

Select this check box if you want to print production documents for this particular production ID at save time.

Setup Print Options

Click this link to access the Process/Output Options page to select different print criteria for the production documents.

Recording Operation Completions

Completed Qty (completed quantity)

Enter the entire production ID quantity or any portion of that quantity for each operation sequence that you want to record completions.

You can enter completions as many times as necessary to complete the production quantity for the production ID. For production IDs with a single output, this field represents the quantity completed at the operation sequence.

Op Seq (operation sequence)

Select the operation step where the end items were completed. You can record partial completions by specifying any valid operation sequence, even if prior operation completions haven't been recorded.

If you're using count points and you enter an operation sequence that is not a count point, then you can record only scrap. When using count points, completion quantities can only be entered at operations flagged as count point operations.

Update Prior Operations

Select this option if you want to automatically record completions and scrap for prior in-house operations at the same time that you're recording completions for this operation.

Back Thru Operation

Indicate how far back you want to report completions by selecting the operation sequence. The quantity that you're currently completing is added to any previously completed quantities at all prior operations specified.

If you're using count points, this field displays the operation after the previous count point.

Previous Operations

If you're recording prior operations at a later time, do not enter any information in this group box, and ensure that the Update Prior Operations check box is deselect.

Click the Refresh button to update the information in the Operations Data grid.

Viewing Operations Data

The Operations Data scroll area displays production details based on operation sequence. You can view operation-related information such as assembly starts quantity, scrap quantities, expected completed quantity, and operation yield.

Click the Work Center link to view work center-related information.

Example: Recording Completions

Production start quantity: 10

Quantity completed: 10

Completing at operation sequence: 30

In this example, you want to complete a quantity of 10 at operation sequence 30. You selected the Update Prior Operations check box on the Record Completions/Scrap page, and indicated that you wanted to update previous operations back to operation sequence 20. The system calculates any production and scrap completed at operation sequences 20 and 30:

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

10

10

0

20

10

0

0

30

0

0

0

40

0

0

0

Once you've completed 10 at operation 30 and updated back through 20, the operations appear as follows:

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

10

10

0

20

10

10

0

30

10

10

0

40

10

0

0

Warning! You cannot update prior subcontracted operations using this option. If there is a prior subcontracted operation and the Update Prior Operations check box is selected, the system ignores the subcontracted operation when recording the prior operations as completed. Use the Subcontract Receipt component to record completed operations and scrap for the subcontracted operation.

Yield by Operation Example: Completing Less Production End Quantity than Expected

When using yield by operation, the beginning production quantities at subsequent operations are affected when either good or scrap production quantities are greater than expected. This example illustrates the effect of yield by operation when you scrap more end items than you originally expected.

Operation sequence: 30

Operation start quantity: 80

Operation yield: 98 percent

Scrapped quantity: 5

Operation Sequence

Operation Start Quantity

Quantity Issued to Operation

Quantity Completed Through

Quantity Scrapped

Expected Completed Quantity

Operation Yield Percentage

10

80

80

80

0

80

100

30

80

80

70

5

75

98

40

75

70

0

0

75

100

50

75

0

0

0

67

90

In this example, a quantity of 80 was issued and completed through operation 10. Because there is a 100 percent operation yield, a quantity of 80 is expected at the end of this operation. The original quantity complete at operation 50 was 70.

However, at operation 30, there is a 98 percent operation yield, and overscrapping of a quantity of 5 also occurs. This means that out of the operation start quantity of 80, only 75 are expected to be completed. As these 75 flow through operations 40 and 50, further loss is expected at operation 50, and the expected completion quantity for the order is now 67.

Yield by Operation Example: Completing More End Items than Expected

This example illustrates the effect of yield by operation on subsequent operations when you scrap fewer end items than you originally anticipated.

Operation sequence: 30

Operation start quantity: 69

Operation yield: 98 percent

Scrapped quantity: 0

Operation Sequence

Operation Start Quantity

Quantity Issued to Operation

Quantity Completed Through

Quantity Scrapped

Expected Completed Quantity

Operation Yield Percentage

10

69

69

69

0

69

100

30

69

69

69

0

69

98

40

69

69

69

0

69

100

50

69

0

0

0

62

90

In this example, a quantity of 69 was issued and completed through operation 10. Because there is a 100 percent yield, a quantity of 69 is expected at the end of this operation. The original quantity expected complete at operation 50 was 60.

However, at operation 30, there is a 98 percent operation yield and underscrapping occurred (scrapped less than expected). Out of the operation start quantity of 69, all were completed and continue to flow through production. As these 69 flow through operations 40 and 50, further loss is expected at operation 50, and the expected completion quantity for the order is now increased to 62.

See Also

Subcontracting

Click to jump to top of pageClick to jump to parent topicRecording Scrapped End Items

Access the Production Scrap Details page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap. Click the Enter Scrap Data link).

Scrap Qty (scrap quantity)

Enter an amount if scrap was generated during production. Scrap can be recorded at any operation sequence, even if you are using count points. For production IDs with a single output, the scrap quantity represents the number of scrapped end items at the operation sequence. For production IDs with multiple outputs, this field represents the number of scrapped end items for the batch (BOM) quantity, and not for each output.

If the scrap at an operation exceeds the expected scrap quantity, you should create a new planned production order to meet the demand.

For serial genealogy production, you may enter the specific serial ID that is being scrapped. If the serial ID has not previously been associated, you are given the option to create the association.

If a routing has operation yield, a reported scrap quantity that is not equal to the expected scrap quantity changes start and end quantities at subsequent operations. It also changes the expected end quantity for the production order.

Note. If the scrap quantity is greater than the production end quantity, the system updates the production start quantity so that the ending production quantity meets demand.

Reason Code

Select a value. This field indicates why the end item was scrapped. Scrap reason codes were previously defined using the Reason Code pages in the Set Up Financials/Supply Chain navigation. This field is required when a scrap quantity is entered.

Scrap Pct (scrap production percentage)

(Optional) This field indicates the percentage that the end item was completed at the operation where the scrap occurred. For example, if the scrapped end items were 75 percent complete before they were scrapped, enter that percentage here. In this example, when calculating the cost of scrapped end items, the system allocates all prior operation costs, plus 75 percent of the runtime costs of the operation where the scrap occurred to each scrapped end item. This percentage is used to calculate the amount of conversion costs earned and scrapped at this operation.

If no value is entered, 0 appears in this field.

Distrib. Type (distribution type)

(Optional) This field indicates the transaction distribution type for the scrap transaction. The distribution type in combination with the scrap transaction determines the correct accounting entries to post the scrap loss to the general ledger. The system displays the default distribution type for the production scrap transaction group. Default distribution types are defined using the Default Distribution Types page. You can override the distribution type for each transaction.

Note. If you're scrapping production that has an operation yield less than 100 percent, the scrap cost calculation is not performed.

The difference in expected and actual scrap is recorded as operation yield variance.

With production IDs, you have the option of scrapping end items at any operation or at the end of production when you can complete end items to stock or another production area. If you're recording scrap at an intermediate operation on a multiple output production ID, you're recording the scrap quantity for the batch and not the individual output items.

When recording scrap at an intermediate operation, the scrap quantity is associated only to the operation where the scrap was recorded. However, if you have selected to complete back through prior operations, the scrapped quantity will be presumed to have been completed at those prior operations.

Example: Scrapping at Operation 30 and Completing Back Through Operation 10

With no prior completed quantity, if you scrap 10 units at operation 30, the operation list would look as follows:

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

10

10

0

20

10

10

0

30

10

0

10

40

0

0

0

Note. You cannot record scrap at the output level. Scrapped end items for production with multiple outputs are recorded at the batch (BOM) level.

Recording Scrap When Using Count Points

When using count points, scrap can be recorded at any operation, regardless of the count point designation. The system updates the scrap quantity for the operation where the scrap occurred. In addition, the system assumes the scrapped quantity was completed at all previous operations up to the previous count point.

Count point operations: 30, 60

Production start quantity: 15

Step 1

Production start quantity previously completed or issued: 10

Operation Sequence

Quantity Issued

Quantity Completed Thru

Quantity Scrapped

10

10

10

0

20

10

10

0

30 (count point)

10

10

0

40

10

0

0

50

0

0

0

60 (count point)

0

0

0

Step 2

Scrap quantity: 5

Scrapping at operation sequence: 30

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

15

15

0

20

15

15

0

30 (count point)

15

10

5

40

10

0

0

50

0

0

0

60 (count point)

0

0

0

Example 2

Production start quantity previously completed and issued: 10

Scrap quantity: 5

Scrapping at operation sequence: 50

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

10

10

0

20

10

10

0

30 (count point)

10

10

0

40

10

0

0

50

0

0

0

60 (count point)

0

0

0

In this example, you have recorded scrap at a noncount point operation. In this case, the system records completions for any previous operations back to the operation after the previous count point (operation 40):

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

10

10

0

20

10

10

0

30 (count point)

10

10

0

40

10

5

0

50

5

0

5

60 (count point)

0

0

0

Once an end item is scrapped, the scrap end item value is calculated and expensed. Item costs for expensed and floor stock items are not included in the end item scrap cost. The end item, including the components used to that point, and the labor, machine, and overhead costs earned to that point are no longer accounted for in WIP inventory.

Note. If you record scrap for an operation that precedes a subcontracted operation, and the purchase order has already been generated for the production quantity, the system sends a purchase order change request to PeopleSoft Purchasing, indicating a change in production quantity. This change must be processed before the end items are sent to the subcontractor.

See Also

Subcontracting

Click to jump to top of pageClick to jump to parent topicGenerating Serial Numbers

Access the Rapid Serial Numbers page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap. Click the Generate Serial IDs link).

Serial Number Count

Displays the number of completed end items that the system assigns serial numbers. A serial number is assigned to all the end items indicated as completed on the Record Completions/Scrap page.

Serial ID Parameters

Displays default information from the Automatic Serial Number page.

Serial Number Prefix, Multiplier, Serial Number Length, and Zero Pad

You can use the default values for the business unit or item or you can override these defaults here.

The serial number prefix can contain up to three alphabetic and numeric characters.

The Multiplier field indicates the increment in which to assign serial numbers. For example, a multiplier of 1 increments each serial number that the system assigns by one. If the last serial number assigned was MFG00001, then the next serial number is MFG00002.

Select Zero Pad if you want to use zeroes as placeholders for the serial number length that you defined.

Use the Start Num (start number) field to specify the first serial number that you want to assign to the completed end items. If you enter a specific starting number, the serial numbers begins with that starting number. The default for this field is blank, and you do not have to enter a starting number. If you leave the field blank and click OK, you receive a warning that the starting serial number is blank and zero appears by default. In this case, the starting serial number is MFG00000. If you enter 1 in this field, the starting serial number is MFG00001.

OK

When you click this button, each completed end item, along with the corresponding serial number, appears in the Route-To PID/Stor Locations scroll area on the Record Completions/Scrap page.

Click to jump to top of pageClick to jump to parent topicRecording End Item Completions Using Count Points

You can use count points to record end item completions.

To record completions and scrap for production IDs using count points:

  1. Access the Record Completions/Scrap page.

  2. Enter the Completed Quantity for the operation sequence.

    If you enter the completed quantity first, only the count point operation steps are available.

  3. Select the Op Seq (operation sequence) that is a count point.

    If you click the operation sequence look up without entering a completed quantity, all operation sequences appear.

    Note. When you record completions at the last operation (which must be a count point), the system assumes that you have or will complete at all prior count points. Therefore, the completed quantity is updated only back to the prior count point.

    Because the system automatically completes back to the operation after the previous count point, the Update Prior Operations and the Back Thru Operation fields are unavailable and the operation after the prior count point (operation sequence) appears by default. This indicates that the quantity completed will also be recorded for operations up to, but not including, the prior count point. If you're recording completions at the first count point, the system automatically completes back through and including the first operation.

  4. All other processes, such as entering scrap data and routing completed end items, remain the same as those used with completing production IDs at intermediate operations.

Example: Recording Completions Using Count Points

Count point operations: 30, 50

Production start quantity: 10

Step 1

Quantity completed: 10

Count point at operation sequence: 30

In this example, you want to complete a quantity of 10 at operation sequence 30, which is a count point. The system calculates any production and scrap completed at operation sequences 10, 20, and 30:

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

10

10

0

20

10

10

0

30 (count point)

10

10

0

40

10

0

0

50 (count point)

0

0

0

Step 2

Quantity completed: 5

Count point at operation sequence: 50

In this example, you want to complete production for a quantity of 5 at operation sequence 50, which is a production ID count point. The system doesn't include operation sequence 30 because it is the prior count point:

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

10

10

0

20

10

10

0

30 (count point)

10

10

0

40

10

5

0

50 (count point)

5

5

0

Click to jump to top of pageClick to jump to parent topicRecording End Item Completions at the Last Operation

To record completions at the last operation:

  1. Access the Record Completions/Scrap page.

  2. Enter the last operation on the operation list in the Op Seq (operation sequence) field if you want to complete all operations for the production ID and all of the operations are performed in-house.

  3. Select Update Prior Operations, then select the first operation from the Back Thru Operation options.

  4. Enter the number of completed end items in the Completed Qty (completed quantity) field.

    You can record completions for the entire production quantity for the production ID or any portion of the quantity.

  5. All other processes, such as entering scrap data and routing completed end items, remain the same as those used with completing production IDs at intermediate operations.

    Note. Co-products can only be completed at the last operation.

See Also

Moving Completed End Items and Assigning Serial and Lot Numbers

Click to jump to top of pageClick to jump to parent topicMoving Completed End items for Production IDs with a Single Output

Access the Record Completions/Scrap page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap).

When completing end items at the last operation, the Route-To PID/Stor Locations scroll area on the Record Completions/Scrap page becomes available. You can route the completed end items to a storage area, another production ID, or to a WIP location. Additionally, if the end item is lot- or serial-controlled, or if you're utilizing containers, you can assign serial numbers, lot IDs, or container IDs to the completed end items.

If a default putaway location is defined for the end item, you can route the completed end items to that location using the routing portion of the page.

Click Apply Defaults to indicate that you want to put away the end items to the default putaway location.

Note. The completions process puts away items in their standard UOMs.

Click to jump to parent topicMoving Completed End Items and Assigning Serial and Lot Numbers

To define default putaway locations, use the Default Putaway Locations (DEFAULT_LOCATION) component. Use the DEFAULT_LOCATION_CI to load data into the tables for this component.

Once you have recorded completions for the last operation sequence on the operation list, you can move the completed end items:

In addition, select the serial number for the appropriate assembly that is being completed and moved.

For serial genealogy production, you must enter the specific serial ID that is being completed. If the serial ID has not previously been associated, you are given the option to create the association.

If you're assigning a lot or serial number for teardown outputs that were based on an original production ID's components, the system compares the new lot or serial number to the original component serial or lot numbers and issues a warning if they are different.

Note. If the assembly is serial in production and you are tearing out a serial ID that has not been issued to this assembly, you receive this message: "Tearing out more than has been issued to the original assembly serial. Okay to continue?" Double-check the quantity and serial ID. Click OK to continue or cancel to change information. The edit check is only looking one level deep, not through all the nested subassemblies.

Route-To PID/Stor Locations

When you route to a production ID, the system checks that:

  1. The item being completed is a component of the production ID parent item.

  2. The issue method is Kit.

  3. The production ID status is Released or In Process.

  4. The shortage quantity is greater than zero.

When routing an end item to another production ID from a production ID, you needn't run any putaway processes. The system automatically updates the issue quantity for the component on the target production ID as well as the quantity completed for the source production ID.

However, if you're routing the end item to a production ID from a production schedule, you still need to run the Completions Update process to update the production information for the production schedule, either at save time or as a deferred process.

Note. You cannot route waste by-products. They are expensed in the same manner as scrapped end items.

Capacity Checking

You activate weight and volume capacity checking on the PeopleSoft Inventory Options page. You can define the capacity for each storage location on the Volume/Weight Capacity page, which you can access from the Material Storage Locations page.

If the item is designated as an isolate item on the Inventory-Shipping/Handling page in the Define Business Unit Item component, the item can only be put away or transferred to empty storage locations or to locations containing stock with the same item ID. The system prevents you from putting away an isolate item to a location with other items.

If you designate a storage location as storing only one item on the Volume/Weight Capacity page, the system only puts away material with that item ID in the location. If you do not specify an item ID for a single-item storage location, the first putaway transaction to the empty storage location defines the only item ID that the location can contain until the item quantity has been fully depleted.

Click to jump to top of pageClick to jump to parent topicPrerequisites

Before you move the items to another WIP location, production ID, or inventory stores location:

Click to jump to top of pageClick to jump to parent topicPages Used to Move Completed End Items and Assign Serial and Lot Numbers

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_COMPL_SELECTION

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection

Select a production ID or production schedule.

Record Completions/Scrap page - Route-To PID/Stor Locations scroll area

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap

Enter a completed quantity and the last operation sequence to access the Route-To/PID Stor Locations (route to production ID and storage locations) scroll area.

Move completed end items to a production ID or to a storage location.

Shortages

SF_COMPL_SHORTAGE

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap

Click the Shortages button in the Route to PID/Storage Locations scroll area.

Select a production ID to which you want to route a completed end item.

Click to jump to top of pageClick to jump to parent topicMoving End Items for Completed Production

Access the Route-To PID/Stor Locations scroll area on the Record Completions/Scrap page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap).

You can move the completed end items to a storage area, another production ID, or a WIP location. In addition, if the end item is lot- or serial-controlled or if you're using containers, you can assign serial numbers, a lot ID, or a container ID to the completed end items using this portion of the page.

Note. If you're completing operations at an operation sequence where a by-product is generated, the Route-to PID/Stor Locations scroll area appears. However, the operation sequence for all end items, except by-products, is unavailable.

Click the Shortages button on the Route-To PID/Stor Locations scroll area on the Record Completions/Scrap page.

See Viewing Production Shortages.

Storage Areas

You can choose different storage areas by different levels such as Area, Lev 1, Lev 2, and Lev 3.

Click the Storage Location Search button and click the Storage Location Search link to select a different storage location.

Quantity

Enter the number of completed end items being routed.

Click to jump to top of pageClick to jump to parent topicViewing Production Shortages

Access the Shortages page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap. Click the Shortages button in the Route to PID/Storage Locations scroll area).

A component is considered short if the pending consumed quantity or the pending yield loss quantity is greater than zero. The production ID is In Process or Pending Complete if the issue quantity is less than the current scheduled quantity.

Route-To Production ID

Selection

Select this option to use the completed end items on the production ID with shortages.

OK

Click this button to cause the production ID to appear in the To Prdn ID (to production ID) field in the Route-To PID/Stor Locations scroll area on the Record Completions/Scrap page.

Routing to IDs and Storage Areas

You can apply the default storage location or production ID to the entire production quantity or to each output, or you can route multiple quantities to different locations or production IDs by adding rows. For each row, you can only select either a storage location or a production ID for the entered quantity. If a storage location is specified, you cannot route end items to a production ID. If you route to a production ID, you cannot route to a specific storage location.

Quantity

Enter the number of end items to be routed.

Orig Comp ID (original component ID)

Displays the original component ID if the end item is a substitute.

Save

Click to route completed end items.

Click to jump to top of pageClick to jump to parent topicSelecting Default Putaway Storage Locations

Access the Apply Defaults page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap. Click the Apply Defaults link).

Deft Storage Loc (default storage location)

Displays the default putaway location for the completed end items, if defined. When you accept the defaults in these fields, the completed end items are automatically moved to the default putaway location for the item when you run the PeopleSoft Inventory putaway process.

If you are not going to move the completed end items to the default storage location, you can select a specific location or route them to another WIP location where they can be used on a higher-level end item.

The system displays the number of storage levels, such as Aisle, Level 1, Level 2 Level 3, and Level 4, that have been defined for each storage area.

Note. The completions process puts away items in their standard UOMs.

Directed Putaway

If you do not enter a storage location, you are not routing to a production ID, and you have activated Directed Putaway for the business unit, the system uses the Directed Putaway method to select a storage location. While running the Load Stage process, the system determines the location that best meets the predefined rules for Directed Putaway. You activate Directed Putaway and set up putaway rules on the Putaway Rules page in PeopleSoft Inventory.

Click to jump to top of pageClick to jump to parent topicAssigning Containers

Access the Record Completions/Scrap page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap).

Container ID

Select a value in the Output Details scroll area if you want to complete to a container. The system assigns this container ID to all the end items that are indicated as completed on the Record Completions/Scrap page. You can select from existing containers, or you can create a new container ID.

If the container ID is specified, you cannot route end items to a production ID, and the default To Prdn ID (to production ID) and Area fields are unavailable.

Click to jump to top of pageClick to jump to parent topicSelecting a Lot ID

If an end item is lot-controlled, select the lot ID to which you're assigning the completed end items. The system assigns the specified lot ID to all the end items indicated as completed on the Record Completions/Scrap page. You can select from existing lots, or you can create a new lot ID.

Click to jump to top of pageClick to jump to parent topicStaging End Items for Putaway

To move completed end items to a stores or other inventory location, complete these tasks using PeopleSoft Inventory:

  1. Run the Load Staged Items process.

    The system suggests the location where the end item should be put away. If you have entered a location on the Route-To PID/Stor Locations scroll area, the system stocks the completed end items in the specified location. If you select Flag Items for Autoputaway, you can bypass the Stockroom Feedback process and run the Putaway page. To streamline the process, you can run the multistep process using PeopleSoft Inventory Auto Putaway.

  2. Run the Stockroom Feedback process.

    This page enables you to change the location suggested by the load staged items process.

  3. Run the Putaway page.

    This processing page updates the stock location with the quantity received from the WIP location.

Putaway at Receipt Save Time

Use this option to initiate the putaway process after you have recorded completions and saved the page. This method creates a schedule process that automatically initiates the putaway process.

Click to jump to parent topicRecording Completions and Scrap for Production IDs with Multiple Outputs

You use the Record Completions/Scrap component to record completions and scrap for production that generated multiple outputs: primary items, co-products, and recycle and waste by-products.

See Also

Receiving and Putting Away Stock

Click to jump to top of pageClick to jump to parent topicPages Used to Record Completions and Scrap for Production IDs with Multiple Outputs

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_COMPL_SELECTION

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection

Select a production ID with multiple outputs.

You must define at least one production ID.

Record Completions/Scrap - Output Details scroll area

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap

Enter completions and scrap information for production IDs with multiple outputs.

This scroll area on the Record Completions/Scrap page becomes available when you select a production ID with multiple outputs. Enter an operation sequence, and then press the Tab key.

Click to jump to top of pageClick to jump to parent topicEntering Completions Quantities for Production IDs with Multiple Outputs

Access the Output Details scroll area on the Record Completions/Scrap page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap).

To enter batch completions quantities (for production IDs with multiple outputs):

  1. Access the Record Completions/Scrap page.

  2. Enter a completed quantity and select an operation sequence.

    The Output Details scroll area becomes available.

    Note. If you're recording completions at an intermediate operation, the system displays all by-products. If you're completing operations at the last operation, the system displays all outputs: primary, co-products, and by-products.

  3. (Optional) ClickView All to display all end items being completed.

  4. Enter the completed quantity for each output.

    The completed quantity for each end item is calculated based on the batch (BOM) quantity. You can, however, override the output quantity for each end item.

  5. (Optional) Click Add to add by-products.

    1. Select the output type; you can only add Recycle or Waste by-products.

    2. Select the output item.

    3. Select the operation sequence where the by-product is being generated.

      The default operation sequence is zero, and if you do not change the default, the system treats it as the last operation.

    4. Enter the output quantity based on per end item or per order.

  6. Click Save to process the multiple output completion.

Output Details

Qty Compl to Date (quantity completed to date)

Displays the output production quantities completed prior to this transaction.

Output Schd Qty (output scheduled quantity)

Displays the total scheduled output production end quantity. This is the output quantity that you expect to produce for each output. This field is display-only for primary items and co-products.

Output Quantity

Displays the output production quantities based on per assembly or per order. You can adjust this field for by-products. You cannot change the output quantity for primary or co-products on this page.

Quantity Per

Indicates whether the quantity required is per assembly or per production order.

Res % (resource allocation percentage)

Determines how much of the BOM batch quantity the primary items and co-product represent. It is used during completions to determine what percentage of the components should be consumed for the primary and co-product. The total resource allocation percentage should always equal 100 percent.

Example: Batch Calculation

If you entered a completed quantity of 5 on the Record Completions/Scrap page, the system calculated each output quantity based on this quantity of 5. However, you can change the completed quantity for any of the outputs in the Output Detail scroll area. Overriding the completed quantity at the output level for primary and co-products recalculates the batch completed quantity using the resource percentages defined on the BOM.

Over-Completing Production IDs

There may be situations when you need to over-complete expected production ID quantities. For example, perhaps the oranges that you used to make orange juice were a bit juicier than normal, and instead of producing 75 gallons of orange juice, you actually produced 80. If this is the case, you would enter 80 in the Completed Qty (completed quantity) field on the Record Completions/Scrap page. When you tab out of the field, you receive a message indicating that the output item's completed quantity is greater than the production quantity.

When you click OK, the system recalculates the completed quantity for all output items based on this new quantity.

Note. If you want to change the production quantities for the batch, which changes the primary and co-product quantities, change the production start quantity or production end quantity for the production ID on the Production ID Maintenance page.

Click to jump to top of pageClick to jump to parent topicMoving Completed End Items for Production IDs with Multiple Outputs

After recording completions for production IDs with multiple outputs, you can route each completed output to a storage area, another production ID, or a WIP location.

See Moving End Items for Completed Production.

Click to jump to top of pageClick to jump to parent topicEditing or Issuing Components During the Completions Process

Use the Edit/Issue Components pages if you want to modify or view the components that will be consumed based on the quantity completed or scrapped, or if you need to select the serial or lot numbers for those components that were consumed when you recorded the completion.

See Editing Component Lists.

Click to jump to parent topicRecording Completed and Scrapped End Items for Production Schedules

For production schedules, you can record partial production completions, or you can complete the entire schedule.

Use the Record Completions/Scrap component to:

If you have enabled PeopleSoft Workflow, when you record end item scrap, the system sends a notification by using the Assembly Prdn Schedule Scrap Notification workflow to selected roles defined by you. These roles could include a quality manager or a production control manager.

Using this component, you can record in-house operation or end item completions and scrap for production schedules with a status of:

If you're using production issue or production kit method for regular production, you still must issue material to the WIP locations using the Pick Plan and Material Release components. If you're using the production replenishment method, ensure that sufficient inventory exists in the WIP location.

Note. Quantities of an item that are stored in a nettable, available WIP location and reserved for production use are not available for other purposes.

You can record in-house operation or end item completions and scrap for production quantities that haven't been previously entered as scheduled quantities.

In this case, the system prompts you for the schedule quantity and the production schedule is automatically created with a status of In Process. You can then backflush a partial quantity or the entire production quantity and record any scrap.

This section lists common elements and discusses how to:

Click to jump to top of pageClick to jump to parent topicCommon Elements Used in This Section

Prdn Start Date (production start date)

The date on which the production is due to begin.

Prdn Due Date (production due date)

The date on which the production is due to be completed.

Date Type

The date used as a sort option for the production schedule—either by production start or production due date.

Sch Method (scheduling method)

For production schedules, Backward always appears.

Click to jump to top of pageClick to jump to parent topicPages Used to Record Completions and Scrap for Production Schedules

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_COMPL_SELECTION

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection

Select a production schedule to record completions and scrap.

You must define at least one production schedule.

Note. The production status should be Released or In Process.

Schedule Selection

SF_PA_SCH_PEG_SP

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection

Enter the production area and item, and then click the Complete to a Specific Schedule link.

Peg completions to a specific production schedule row.

Record Completions/Scrap

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap

Enter completions and scrap information.

In addition, use this page to move end items for production schedules with a single output or multiple outputs.

Production Scrap Details

SF_COMPL_SCRAP

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap

Click the Enter Scrap Data link.

Enter any scrap quantities.

Apply Defaults

SF_COMPL_DEFAULTS

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap

Click the Apply Defaults link.

Select the putaway locations for the completed end items.

Rapid Serial Numbers

MG_SERIALRG_PG_SBP

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap

Click the Generate Serial IDs link.

(Optional) Automatically generate serial numbers for production end items that are serial-controlled.

Note. You must define serial-controlled items in PeopleSoft Inventory.

Work Center Details

SF_WORK_CTR_SP

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap

Click a Work Centerlink in the Operations Data scroll area.

View work center-related information such as WIP locations.

Lot/Serial Number Selection

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Select the serial numbers of the serial-controlled components to be consumed during the completions process.

You must enter a pending quantity greater than zero before the Lot/Serial scroll area becomes available.

Lot/Serial Number Selection scroll area

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Identify the lots from which you want to consume lot-controlled components. Lots can be automatically assigned during backflush depending on your setting for the backflush lot selection rule.

You must enter a pending quantity greater than zero before the Lot/Serial scroll area is available.

Production History

SF_TRANSHIST

Production Control, Define Production, Review Production Information, Production History

View production transaction history for production schedules.

Transaction History Details inquiry

SF_TXN_HIST_SP

Production Control, Define Production, Review Production Information, Production History

Click the Details button.

View completions details based on the selection criteria.

Click to jump to top of pageClick to jump to parent topicRecording Completed and Scrapped End Items for Production Schedules

Access the Production Selection page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection).

Unit, Production Area, and Item ID

Enter values for the production schedule.

Click the Item Search button to access the Item Search Criteria page to locate a different item.

Complete to a Specific Schedule

Click this link if you want to select a specific production schedule.

BOM/Rtg Code Effective Dates

Because only one active BOM/routing combination is valid for an area at any one time, select the valid BOM/routing combination for accurate component consumption. By selecting an effective date in the BOM/Rtg Effdt (BOM/routing effective date) field, you determine the particular BOM/routing combination for which you want to complete. The BOM/routing effective date, which is the current date by default, determines which combination the system selects and displays in the BOM Code and Routing Code fields.

For non-revision-controlled items, this BOM/routing date is used to decide which BOM/routing combination will be used and a second effective date that will be used for the components and outputs. If the item is revision-controlled, then both an item revision code and BOM/routing effective date must be selected.

Note. Because you can create multiple schedules per area with only one combination effective at any one time, production schedules for prior effective date ranges may not be consumed if the effective date range for the combination has passed. For example, if you have BOM code 1 and routing code 2 valid from January 1, 2001, but BOM code 2 and routing code 2 is valid from June 1, 2001 for the same production area, then you could create production schedules for the 1/2 combination prior to June 1, 2001 but completing them after this date. In this case, the system is unable to consume for them because the new BOM/routing combination has taken effect. In addition, you get an auto-add message when you attempt to complete because no schedules currently exist for the 2 /2 combination. However, if you change the BOM/routing effective date back to a date prior to June 1, 2001, the system accesses the correct combination.

Click the Select BOM/Routing button to access the Select BOM/Routing page to select a different BOM/routing combination. This selection also displays the effective dates of the BOM/routing combinations.

Revision

You can change the revision code if you're building to a different revision. If the item is not revision-controlled, the current date is displayed in the effective date BOM configuration used to create the component list.

Negative Completions

Select this check box if you are reversing a previous completions or scrap transaction.

See Creating Reversing Entries to Correct Data Entry Errors.

Search

Click to retrieve the selected production schedule.

Click to jump to top of pageClick to jump to parent topicPegging to a Specific Production Schedule

Access the Schedule Selection page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection. Enter the production area and item, and then click the Complete to a Specific Schedule link).

You may want to complete for a specific production schedule because a substitution was made or a data entry error needs to be corrected. In addition, by pegging to a production schedule, you update the specific production schedule when you run the Completions Update process.

Date Range

Enter the date range.

Date Type

Displays how you want to view the production schedules. Values are:

  • Prdn Start (production start)

  • Prdn Due (production due)

Click to refresh the data if you made any changes to the date range or date type.

Sel (selection)

Select the specific production schedule that you want to record completions and scrap.

OK

Click this button to return to the Production Selection process page.

Click to jump to top of pageClick to jump to parent topicAdding a New Production Schedule During Completions

If the system indicates that no current outstanding production schedule quantities exist for this production area/item combination as of the BOM/routing effective date or effective date, you receive a warning message indicating that no outstanding production quantities exist for an area or item.

If you click Yes, the system creates a new production schedule. The system checks for any outstanding production schedules by comparing any unprocessed BCTP detailed transaction logs (BCT_DTLs) (Completed + Scrapped ) quantities and netting them against those matching open production schedules (production end quantity > completed + scrapped quantity) in the system.

The default rate quantity per shift from the production area or item definition appears as Production Rate Quantity. Click OK to accept this quantity or change the quantity to the quantity that you're currently producing.

Recording Completions and Scrap for Production Schedules That Haven't Been Released

You can also record completions and scrap for production schedules that have not been released.

To release Entered production schedules, use the Prod Schedule Status Change page or the Production Status Change process (SFPARELS). This process looks for production schedules that match the date, shift, BOM code, routing code, and primary end item of the selection criteria. The system releases all the production schedules with a status of Entered that match the selection criteria. You can then record completions and scrap for the production schedules.

Firmed production schedules are automatically released during the completions process.

Click to jump to top of pageClick to jump to parent topicDefining Completions and Scrap Information for Production Schedules

Access the Record Completions/Scrap page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap).

The process for recording completions and scrap for production schedules is similar to the process used for production IDs. However, there are a few differences:

Click to jump to top of pageClick to jump to parent topicRecording Completions and Scrap for Production Schedules with Multiple Outputs

Access the Record Completions/Scrap page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completions/Scrap).

To record completions and scrap for production schedules with multiple outputs:

  1. Enter the completed quantity that represents the batch (BOM) production end quantity.

    This quantity doesn't represent completed quantities for each output in the Output Details area. You can enter a quantity here or optionally enter the quantity of each output. If you enter specific output completions, the system determines the quantity of the batch completed.

  2. The Op Seq field is unavailable and the last operation step appears.

    Note. Because you're completing a production schedule, the Update Prior Operations check box is unavailable, and the first operation step appears by default in the Back Thru Operation field. These fields are display-only and cannot be changed.

  3. Click the Enter Scrap Data link to make corrections to the scrapped component quantities.

  4. Access the Output Details scroll area on the Record Completions/Scrap page.

  5. Enter the completed quantity for each output.

    The system calculates the multiple output quantities based on the batch completed quantity from the Record Completions/Scrap page. For example, if you entered a completed quantity of 5 on the Record Completions/Scrap page, the system would calculate each output quantity based on this quantity of 5. However, you can change the completed quantity for any of the outputs on the Output Details scroll area.

    Note. If you want to change the production quantities for the batch, which changes the primary and co-product quantities, change the production end quantity for the production schedule on the Production by Area Summary or Production by Area Details pages.

  6. (Optional) Click Add to add recycle or waste by-products.

    1. Select the output type and output item.

    2. Select the operation sequence where the additional by-product is being generated.

    3. Enter the completed quantity, which is the output quantity that you're currently completing.

    4. Enter the output quantity.

      This quantity represents the output production end quantity based on per end item or per order.

  7. Click Save to record the completions and scrap.

Click to jump to top of pageClick to jump to parent topicMoving End Items for Production Schedules

With production schedules, you can only complete end items at the last operation. When you enter the completed quantity on the Record Completions/Scrap page, the Route-To PID/Stor Locations scroll area becomes available. You use the Route-To-PID/Stor Locations scroll area to route completed end items for production schedules with a single output or multiple outputs.

Click to jump to parent topicEditing Component Lists

At some point while recording operation completions and scrap, you may need to view or modify the component list or select the lot and or serial numbers for the consumed components. Using the Edit/Issue Components pages, you can:

In addition to using this page to record the consumption of components in the process of recording completions or scrap, you can also use this page to:

Keep these in mind when editing component lists:

Note. If you need to add a phantom component to the component list, you must enter all of the items that make up the phantom component. A substitute component cannot be a phantom or a component of a phantom. Where substitutes exist for a component, the component cannot be changed to a phantom.

Editing or Issuing Components for Production Schedules

You can also use the Edit/Issue process to consume existing pending quantities for a production schedule. After selecting the area or item and dates of the production schedule and clicking the Search button, a message appears if there are any existing pending quantities for production schedules that match the selection criteria. If Yes, then the components with existing pending quantities appear.

Workflow Notification

If you have enabled PeopleSoft Workflow, you can use the Replenishment Notification workflow to notify the stockroom when the quantity on hand for components with a component issue method of Production Replenishment falls below its minimum stocking quantity in that location. This notification indicates that the location must be replenished.

Note. When you're editing or issuing components, the system doesn't allow you to modify component information for components whose issue method is Kit. Use the Kit Issue/Return Component to edit or issue these components. Additionally, you can view but cannot modify components whose source code is Floor Stock.

Issuing Components and Effects on Quantities

Action

Results to Quantities

Issuing components to production

Decreases the business unit's on-hand quantity.

Returning components to inventory

Increases the business unit's on-hand quantity.

Issuing material from a nettable, available WIP location

Decreases the business unit's reserved quantity.

Returning components to a nettable, available WIP location

Increases the business unit's reserved quantity.

For owned items, issuing components to production

Decreases the business unit's owned quantity.

Returning owned components to inventory

Increases the business unit's owned quantity.

Issuing components to production

Decreases the storage location's quantity.

Returning components to inventory

Increases the storage location's quantity.

Issuing lot-controlled components to production

Decreases the lot quantity on-hand.

Returning lot-controlled components to inventory

Increases the lot quantity on-hand.

Capacity Checking

You activate weight and volume capacity checking on the PeopleSoft Inventory Options page, and define the capacity for each storage location on the Volume/Weight Capacity page accessible from the Material Storage Locations page.

If the item is designated as an isolate item on the Inventory-Shipping/Handling page in the Define Business Unit Item component, it can only be put away or transferred to empty storage locations or to locations containing stock with the same item ID. The system prevents you from moving an isolate item to a WIP location with other items.

If you designate a WIP location as storing only one item on the Volume/Weight Capacity page that is accessible from the Material Storage Locations page, the system only issues material with that item ID to that location. If you do not specify an item ID for a single-item WIP location, the first issue transaction to the empty WIP location defines the only item ID that the location can contain until the item quantity has been fully depleted.

Click to jump to top of pageClick to jump to parent topicPages Used to Edit or Issue Components

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_ED_COMPS_SELECT

Production Control, Process Production, Issue Materials, Edit/Issue Components, Production Selection

Select the production ID or production schedule for which you want to edit or issue components.

Components must have an issue method of Issue or Replenish to use this page.

Edit/Issue Components Summary

SF_EDIT_COMPS_EDIT

  • Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Components Summary if you are editing or issuing components during the completions process

  • Production Control, Process Production, Issue Materials, Edit/Issue Components, Edit/Issue Components Summary if you are editing or issuing components after you've recorded completions and scrap

Edit or view components.

In addition, use this page to edit or issue components during the Record Completions and Scrap process or after the Record Completions/Scrap process has been run.

Edit/Issue Express

SF_EDIT_COMPS_EXPR

  • Production Control, Process Production, Issue Materials, Edit/Issue Components, Edit/Issue Express. Click the Edit/Issue Express link.

  • Production Control, Process Production, Complete Production, Record Completions/Scrap, Edit/Issue Express. Click the Edit/Issue Express link on the Edit/Issue Components Summary process page.

(Optional) Select lot- or serial-controlled components that have pending issue or pending loss quantities. You can view or change lots assigned to lot-controlled components by the backflush lot selection rule.

Lot/Serial Number Selection

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Select the lot or serial numbers or both of the lot- or serial-controlled components to be consumed during the completions process.

You must enter a pending quantity greater than zero for a serial-controlled or lot-controlled component before the Lot/Serial scroll area is available.

Edit/Issue Components Detail

SF_EDIT_COMPS_DET

  • Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Components Detail

  • Production Control, Process Production, Issue Materials, Edit/Issue Components, Edit/Issue Components Summary. Click the Detail button next to the component you want to edit or view.

View detailed information for each component for selected production.

Production History

SF_TRANSHIST

Production Control, Define Production, Review Production Information, Production History

View production transaction history for components.

Transaction History Details inquiry

SF_TXN_HIST_SP

Production Control, Define Production, Review Production Information, Production History

Click the Details button.

View completions details based on the selection criteria.

Click to jump to top of pageClick to jump to parent topicSelecting Production for Editing or Issuing Components

Access the Edit Components - Production Selection page (Production Control, Process Production, Issue Materials, Edit/Issue Components, Production Selection. Select the production ID or production schedule for which you want to edit or issue components. Components must have an issue method of Issue or Replenish to use this page).

Production ID

Enter a value to edit or issue components for a production ID.

Production Area and Item ID

Enter values to edit or issue components for a production schedule.

Revision

Displays if the item entered is revision-controlled. You can change the revision code if you're building to a different revision.

Eff Date (effective date)

Displays the current date if the item is not revision-controlled. The revision or effective date determines the BOM configuration used to create the component list.

BOM/Rtg Effdt

Select a value if you have predefined specific BOM and routing combinations with the Production Options maintenance pages.

Click the Select BOM/Routing button next to the BOM/Rtg Effdt field to access the Select BOM/Routing page to select a different BOM and routing combination.

BOM Code and Routing Code

Displays valid codes for the BOM and routing code combination.

Search

Click the Search button to retrieve the information associated with the production ID or production schedule.

See Also

Defining Production Options

Click to jump to top of pageClick to jump to parent topicEditing or Issuing Component Summaries

Access the Edit/Issue Components Summary page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Components Summary).

Print at Save

Select this check box if you want to print production documents for a particular production ID at save time.

Setup Print Options

Click this link to access the Process/Output Options page to select different print criteria for the production documents.

Click the Express Page button to access the Edit/Issue Express page to view or assign serial and lot numbers.

Click the Detail button to access the Edit/Issue Component Detail page.

Click the Item Search button to access the Item Search, Item Availability, or Item Substitution pages.

Op Seq (operation sequence)

Determines the WIP inventory location to which the components are issued and from which they are consumed. When you add a new component to the component list, the operation sequence defaults to zero. When recording end item completions and scrap, the system consumes a component with an operation sequence of zero at the first operation and decrements the component quantity on hand in the production area's default WIP location.

You can change the operation sequence to any valid operation on the end item's operation list. When you select an operation sequence, the component must be issued to and is consumed from the WIP location associated with the operations work center.

Per

Indicates whether the quantity required is per assembly (Asy) or per order (Ord). Per assembly indicates the quantity required to complete one end item. Per order indicates the amount required, regardless of the end items that will be produced.

  • If the component is per assembly, the system calculates the consumed quantity by multiplying the quantity per by the end item completion and scrapped quantity.

  • If the component is per order, and you're recording completions for a production ID, the system consumes the full order quantity during the first recorded backflush.

    Once consumed, it will not be consumed again during any subsequent backflushes. If you're recording completions for a production schedule, the consumption of a per order quantity depends on the Manufacturing Options setting for Calc Per Order for Production Schedules.

Pending Issue Qty (pending issue quantity)

The system calculates this value for those components whose operations have had end item completions or scrap reported.

Enter a new pending issue quantity if you consumed more or less than the quantity calculated.

The pending issue quantity is based on the quantity completed plus the quantity scrapped multiplied by the quantity per assembly. If the quantity on the component list is expressed in terms of quantity per order, the full quantity appears. This quantity is consumed only at the time of the first backflush for production ID. For production schedules, the Calc Per Order for Production Schedules option on the Manufacturing Business Unit Option page determines how the quantity is displayed.

If you have enabled PeopleSoft Workflow, the system sends a notice to the production supervisor that there is a nonzero quantity for this component. PeopleSoft Manufacturing uses the Identify Production with Pending Quantities workflow for this notification.

  • If the option is set to Calc Per Order for Prdn Sched, the system displays the per order quantity for every production schedule completion.

    If you have already consumed the order quantity for the production run, you must zero out this amount.

  • If the option is set to do not Calc Per Ord on Prdn Sched, the system doesn't display any per order quantity for any production schedule completion.

    In this instance, you must enter the order quantity when the material is consumed for the production run.

Pending Yield Loss Qty

If the quantity of components lost is more or less than planned, indicate the new pending yield loss quantity here. If the item's yield loss is set to calculate the pending yield loss quantity, then the system calculates the pending yield loss for those components whose operations have had end item completions or scrap reported. You define whether or not you want the system to calculate pending yield loss quantity at the business unit or item level. If you do not want the system to calculate pending yield loss quantity, then you manually record the yield loss at the appropriate times.

The system uses this formula to calculate the pending yield loss quantity:

(Quantity Completed + Quantity Scrapped) x Expected Yield Loss Percentage

Expected Yield Loss Percentage = (1 - Component Yield / 100)

Adding or Substituting Components

Component ID, Op Seq (operation sequence), Per Asy (assembly) or Ord (order), Pending Issue Qty (pending issue quantity), and Pending Yield Loss Qty (pending yield loss quantity)

Enter values for these fields if you're adding or substituting components.

Note. Pending issue and pending yield loss quantities are not calculated for expensed or floor stock items. In addition, you cannot enter values for components with an issue method of Kit.

To change or enter the quantity per, yield, or scheduled quantity, use the Edit/Issue Component Detail page.

If you're substituting a component, zero out the pending issue and pending yield loss quantity for the original component.

Allowing Negative On Hand Inventory

If the PeopleSoft Inventory business unit parameter allows negative inventory balances and there is not enough material in the WIP location to cover the pending issue or pending yield loss quantity, the quantity on hand in the WIP location will become negative. Another business unit parameter determines when the system issues a warning message prior to driving quantity on hand negative. This message allows you to decide whether to continue with the completion transaction or to wait until the inventory is moved into the WIP location before continuing. If you do not allow the inventory to go negative, the quantity that couldn't be consumed remains in the pending issue or pending yield loss fields. These must be reconciled once the WIP location has sufficient quantity on hand.

Note. If the item that you're consuming is serial-controlled, you cannot drive the quantity on hand negative, regardless of the PeopleSoft Inventory business unit setting.

Click to jump to top of pageClick to jump to parent topicUsing the Edit/Issue Express Page

Access the Edit/Issue Express page (Production Control, Process Production, Issue Materials, Edit/Issue Components, Edit/Issue Express. Click the Edit/Issue Express link).

Component Details

You can change any of this information on this page:

  • Component ID

  • Pending issue quantity

  • Operation sequence

  • Pending loss

Click to jump to top of pageClick to jump to parent topicConsuming Serial-Controlled Components

Access the Lot/Serial Number Selection page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Express. Click the Select Lot/Serial link).

Sel (select)

Select the serial-numbered components that you want to consume by selecting one or more check boxes.

Click to jump to top of pageClick to jump to parent topicConsuming Lot-Controlled Components

Access the Lot/Serial scroll area on the Edit/Issue Express page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Express).

Lot ID

Select a lot if you're editing or issuing lot-controlled components. You can view or change lots assigned by the backflush lot selection rule.

Qty Req (required quantity)

Specify the amount of components that you want to consume from each lot. This field can be automatically populated during backflush using the backflush lot selection rule.

See Also

Automatically Consuming Lot-Controlled Stock During a Backflush

Click to jump to top of pageClick to jump to parent topicEditing or Viewing Component Detail

Access the Edit/Issue Components Detail page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Components Detail).

Component Details

Component ID, Op Seq (operation sequence), Qty (quantity), quantity Per, Yield, and Sched Qty (scheduled quantity)

Enter or modify values for these fields.

Work Center Detail

Click this link to access work center-related information.

Qty (quantity)

The calculated quantity per is next to this field. The system calculates the quantity per by dividing the quantity per assembly by the bill of material's BOM quantity. You designate the level of precision for the calculated quantity per on the Manufacturing installation options page.

Pending Issue Qty (pending issue quantity) and Pending Yield Loss Qty (pending yield loss quantity)

Although these values appear by default from the Edit/Issue Components Summary page, you can change them here.

Note. If you are not completing end items, a pending issue or pending yield loss quantity greater than zero indicates that the components couldn't be consumed from the appropriate WIP location from a previous completions or edit components transaction. This is due to a shortage of the component in the WIP location associated with the component's operation sequence.

Issue Qty (issue quantity)

This field represents the quantity consumed that was issued from the WIP location for the component and was charged to WIP. For items using the Kit issue method, this is the quantity that was issued during Material Release of a production Pick Plan or issued using the Issue/Return Kit Components page. You cannot modify kitted components here. This field is used for production IDs only.

Yield Loss Qty (yield loss quantity)

This field represents the component quantity that was scrapped during end item completion and issued from the WIP location. This field is used for production IDs only.

Issue Method

This field indicates the component replenishment issue method.

Note. Quantities of an item that are stored in a nettable, available WIP location and reserved for production use are not available for other purposes.

Click to jump to top of pageClick to jump to parent topicIdentifying Material Shortages

An Application Engine process queries the production component table for any outstanding pending component quantities for production with a status of In Process or Pending Complete. If the system finds outstanding quantities, the system issues a worklist notification for each of the qualified production orders to relieve the component. When you work the worklist entry, you're transferred to the Edit/Issue Components Summary page. Once you consume material to relieve the shortages, the worklist entry is marked as completed.

Click to jump to parent topicRunning the Completions Update COBOL/SQR Process (SFPDCDRV)

The Prdn Compl/Scrap (SFPDCDRV) process (Production Completions and Scrap process) updates completions transactions that are staged by other processes, such as Edit Components updates, production completions, or subcontracted completions recorded through electronic data collection. In addition, you run this process to update production quantities for production schedule completions and scrap. You run this process if you selected Stage Compltns/Putaway on Save as the completions action on the Record Completions/Scrap page.

Click to jump to top of pageClick to jump to parent topicPage Used to Run the Completions Update COBOL/SQR Process (SFPDCDRV)

Page Name

Definition Name

Navigation

Usage

Prdn Cmpl/Scrap

BCT_MG_REQCOMP

  • Production Control, Process Production, Complete Production, Process Completions and Scrap, Prdn Cmpl/Scrap

  • SCM Integrations, Process Transactions, Manufacturing, Production Completions/Scrap, Prdn Cmpl/Scrap

Update completions transactions that are staged by other processes and for production schedules.

Click to jump to top of pageClick to jump to parent topicRunning the Completions Update Process

Access the Prdn Cmpl/Scrap page (Production Control, Process Production, Complete Production, Process Completions and Scrap, Prdn Cmpl/Scrap).

Unit and Request ID

Enter values for this process.

Run

Click to run this request. Process Scheduler runs the Completions/Scrap Update process at user-defined intervals.

Click to jump to parent topicCreating Reversing Entries to Correct Data Entry Errors

Use the Record Completions/Scrap component to create reversing entries to correct data entry errors made when recording end item completions or scrap.

Enter a negative number to reverse the completion or scrap entry. For example, suppose that an entry was made to record a completion of 8 end items at operation 20, but only 6 end items were actually completed. You can enter a -2 in the Completed Qty (completed quantity) field to reverse the original entry of 8. This brings the completed quantity balance for that operation to 6.

This reversing entry:

Click to jump to top of pageClick to jump to parent topicPages Used to Create Reversing Entries to Correct Data Entry Errors

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_COMPL_SELECTION

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection

Select a production ID or production schedule to create reversing entries.

Record Completions/Scrap

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap

Enter reversing entries for selected production.

Production Scrap Details

SF_COMPL_SCRAP

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap

Click the Enter Scrap Data link.

Enter any reversing entries to scrapped quantities, if applicable.

Apply Defaults

SF_COMPL_DEFAULTS

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap

Click the Apply Defaults link.

Select the putaway locations for the reversing entries.

Lot/Serial Number Selection

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Select the serial numbers of the serial-controlled components to be returned.

Lot/Serial Number Selection scroll area

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Complete Production, Record Completions and Scrap, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Identify the lots from which you want to return lot-controlled components.

Click to jump to top of pageClick to jump to parent topicIdentifying Production for Data Entry Error Corrections

Access the Record Completions/Scrap - Production Selection page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection).

Negative Completions

Select this option to create reversing entries to correct data entry errors.

Unit and Production ID

Select values to reverse entries for a production ID.

Unit, Production Area, and Item

Select values to reverse entries for a production schedule.

BOM/Rtg Effdt

Enter an effective date to determine the particular BOM and routing combination for which you want to complete.

Peg Schedule

Click this link if you want to select a specific production schedule.

Search

Click this button to retrieve the selected production information.

Note. If you attempt to perform negative completions and you haven't recorded any positive completions, the system displays an error message. If you click Yes to continue, you are able to record positive completions. If you click No, the system returns you to the Production Selection process page.

If you attempt to perform negative completions and you cannot find the quantity in the location you expected, you may not have run the Completions Update process and the putaway process.

Click to jump to top of pageClick to jump to parent topicEntering Negative Completions Quantities

Access the Record Completions/Scrap page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap).

Completed Qty (completed quantity)

Enter a negative return quantity in this field.

Note. If you enter a negative quantity in the Completed Qty (completed quantity) field, and you didn't select the negative completion on the Record Completions/Scrap - Production Selection page, you receive a message asking if you're doing a negative transaction. If Yes, then the transaction automatically selects the Negative Completions option for you, and you do not have to return to the Production Selection page and select the Negative Completions check box.

Enter Scrap Data

Click this link to correct the scrapped component quantities.

Quality

Click the Quality link to initiate a data entry session and to transfer to either the Data Entry - Subgroup Method page or the Data Entry - Sample Method page in PeopleSoft Quality, depending on the data entry method that you specified when creating the quality control plan.

Note. The Quality link is available for each end item in the Output Details scroll area. You can transfer completions data to PeopleSoft Quality for each end item.

Update Prior Operations and Back Thru Operation

You can enter values for these fields if you're creating a reversing entry for production IDs.

Lot ID

Select a value if you're creating a reversing entry for lot-controlled end items.

Area

Specify the storage area and inventory locations from which you want to pull the completed end items.

Return Qty (return quantity)

Enter a negative number in this field.

Serial IDs

Click this link if you're correcting data entry errors for serial-controlled components. Select each serialized item that you want to move back into production by selecting one or more serial IDs.

Note. Reversing entries are processed when you save the Record Completions/Scrap page.

Creating a Reversing Entry for the First Operation, an Intermediate Operation, a Count Point, or for Scrap at Any Operation

If you're creating a reversing entry for the first operation, an intermediate operation, count point, or for scrap at any operation, the system reverses the earned production costs or the scrap costs for those end items at that operation and moves them back to the specified prior operation or count point. In addition, the system returns all consumed components to the WIP location.

Example: Negative Completions When Using Count Points

Count point operations: 30, 50

Production start quantity: 10

Step 1

Production start quantity completed: 10

Completing at operation sequence: 30

Back through operation sequence: 10

In this example, you're completing operations and scrap for a quantity of 10 at operation sequence 30, which is a production ID count point. You selected the Update Prior Operations check box on the Record Completions/Scrap page, and indicated that you wanted to update previous operations back to operation sequence 10. The system calculates the production completed at operation sequences 10, 20, and 30:

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

10

10

0

20

10

10

0

30 (count point)

10

10

0

40

10

0

0

50 (count point)

0

0

0

Step 2

Production start quantity issued or returned: -5

Reversing end item completions at operation sequence: 3

Update previous back through operation sequence: 10

In this example, you're returning a quantity of 5 at operation sequence 30, which is a count point. You selected the Update Prior Operations check box on the Record Completions/Scrap page, and indicated that you wanted to update previous operations back to operation sequence 10. The system recalculates and reverses the quantity issued to the operation at operation sequence 40:

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

5

5

0

20

5

5

0

30 (count point)

5

5

0

40

5

0

0

50 (count point)

0

0

0

Example: Negative Completions When Not Using Count Points

Production start quantity: 10

Step 1

Production start quantity completed: 10

Completing at operation sequence: 30

Back through operation sequence: 10

In this example, you're completing operations and scrap for a quantity of 10 at operation sequence 30. You selected the Update Prior Operations check box on the Record Completions/Scrap page, and indicated that you wanted to update previous operations back to operation sequence 10. The system recalculates and reverses the production completed at operation sequences 10, 20, and 30:

Operation Sequence

Quantity Issued

Quantity Completed Through

Quantity Scrapped

10

10

10

0

20

10

10

0

30

10

10

0

40

10

0

0

50

0

0

0

Creating a Reversing Entry at the Last Operation for Completed End Items

If you're creating a reversing entry for the last operation, the system reverses the earned production costs for those end items at the last operation.

To create a reversing entry for the last operation, you must specify the storage area or production area from which you're removing the previously completed end items. You also must complete these:

Click to jump to parent topicCompleting Production

For production IDs, use the Complete Production page to indicate that:

Click to jump to top of pageClick to jump to parent topicPages Used to Complete Production

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_COMPL_SELECTION

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection

Select a production ID to record completions and scrap.

Record Completions/Scrap

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap

Enter completions and scrap information for the production ID.

Complete Production

SF_COMPL_PRDN

Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap

Click the Complete Production link.

Indicate that production at all operation sequences has been completed.

Click to jump to top of pageClick to jump to parent topicRunning the Complete Production Process

Access the Complete Production page (Production Control, Process Production, Complete Production, Record Completions and Scrap, Record Completion/Scrap. Select the Complete Production link).

Update Set Up Costs

Select this check box if you want to indicate that setup work has been completed without recording the completion of any end items.

Update Post Production Costs

Select this check box if the post production work is complete. Post production is not automatically earned even if all end items have been recorded as complete at the operation. By selecting either check box, you earn the setup and post production time, and the labor, machine, and overhead value are included as part of the WIP inventory value.

You can earn setup and post-production costs only once. Also, you can earn setup costs automatically when the first completion is recorded at the operation. You cannot earn setup costs with any subsequent operation completions.

To reverse any previously earned setup or post-production costs, select the check boxes again. This creates a reversing entry for any setup or post-production time previously earned.

Production Completed

Select this check box to indicate that all production is complete at all operations and that no additional end item completions or scrap will be recorded. Selecting this option changes the status of the production ID to Pending Complete.

Return

Click to return to the Record Completions/Scrap page.

Save

Click to run the Complete Production process.

Click to jump to parent topicMoving Excess Inventory Back to a Stores Location

When the last end item is completed or the production run is finished, move any excess WIP components with an issue method of issue or replenish back to their appropriate stores location. Once you've identified the excess WIP inventory, run a transfer transaction using PeopleSoft Inventory. The transfer process moves the excess WIP components from the WIP location back to the stores location.

Use Kit Issues/Return to return excess components whose issue method is Kit.

Click to jump to parent topicViewing and Reporting Material Shortages

PeopleSoft Manufacturing provides a shortage report, which enables you to view, at a glance, the shortages for each production order or production run sorted by production ID or components. The system tells you where shortages exist, so you can move inventory to those areas to relieve production shortages.

Click to jump to top of pageClick to jump to parent topicPages Used to View and Report Material Shortages

Page Name

Definition Name

Navigation

Usage

Review Material Shortage - Selection

SF_MTL_SHORT_SEL

Production Control, Close and Analyze Production, Review Material Shortage, Selection

Select production to view material shortage information.

Shortages

SF_MTL_SHORT_GRD

Production Control, Close and Analyze Production, Review Material Shortage, Shortages

View material shortage information.

Shortage Report Selection

RUN_SFS2001

Production Control, Close and Analyze Production, Shortage Report, Shortage Report Selection

Select production with shortages to generate a shortage report.

Production Selection

RUN_SFS2001B

Production Control, Close and Analyze Production, Shortage Report, Production Selection

Define additional shortage report criteria.

Click to jump to parent topicViewing Scrap and Earned Conversion Cost Information

On a periodic basis, you want to monitor scrap and earned conversion costs associated with production. Viewing this information gives you a good idea of how the manufacturing floor is performing. PeopleSoft Manufacturing provides you with the ability to view scrap and earned conversion costs for production IDs and schedules in the production environment.

Click to jump to top of pageClick to jump to parent topicPages Used to View Scrap and Earned Conversion Cost Information

Page Name

Definition Name

Navigation

Usage

Review Scrap Costs

SF_SCRAP_INQUIRY

Production Control, Close and Analyze Production, Review Scrap Costs

Select production with scrap costs for a particular production ID or production schedule.

Scrap List by Operation

SF_SCRAP_INQ_OP

Production Control, Close and Analyze Production, Review Scrap Costs, Scrap List by Operation

View scrap information by operation sequence for a specific production ID or production schedule.

Scrap Cost Detail

SF_SCRAP_INQ

Production Control, Close and Analyze Production, Review Scrap Costs, Scrap Cost Detail

View detailed scrap costs for the production ID or schedule broken down by operation sequence.

Production Selection

SF_EARNCON_INQUIRY

Production Control, Close and Analyze Production, Review Earned Conversion Costs, Production Selection

Select a particular production ID or production schedule to view earned conversion costs.

Earned Conversion Cost by Operation

SF_EARNCON_INQ_OP

Production Control, Close and Analyze Production, Review Earned Conversion Costs, Production Selection, Earned Cost by Operation

View conversion cost information by operation sequence for a specific production ID or production schedule.

Earned Conversion Cost Detail

SF_EARNCON_INQ

Production Control, Close and Analyze Production, Review Earned Conversion Costs, Production Selection, Earned Cost Detail

View earned conversion cost detail for production.

Click to jump to parent topicRecording and Viewing Actual Machine and Labor Hours

PeopleSoft Manufacturing provides you with the ability to record and view actual labor and machine hours incurred during the manufacturing process.

Click to jump to top of pageClick to jump to parent topicPages Used to Record and View Actual Machine and Labor Hours

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_ACTHR_SELECTION

Production Control, Process Production, Complete Production, Record Actual Hours, Production Selection

Select the production that you want to record actual machine and labor hours incurred during the production process.

Record Actual Hours

SF_ACTHRS_NEW

Production Control, Process Production, Complete Production, Record Actual Hours, Record Actual Hours

Enter labor and machine hours for the selected production.

Review Actual Hours - Production Selection

SF_ACTHRS_INQUIRY

Production Control, Close and Analyze Production, Review Actual Hours

Select a specific production ID or production schedule to view actual labor and labor information.

Actual Hours by Operation

SF_ACTHRS_INQ_GRD

Production Control, Close and Analyze Production, Review Actual Hours, Actual Hours by Operation

View actual labor and machine hours for a production ID or schedule by operation.

Actual Hours Detail

SF_ACTHRS_INQ

Production Control, Close and Analyze Production, Review Actual Hours, Actual Hours Detail

View detailed information on actual labor and machine hours for a production ID or schedule by operation.

Crew/Machine Resources Detail

SF_ACTHRS_INQ_SEC

Production Control, Close and Analyze Production, Review Actual Hours, Actual Hours Detail

Click the Show Crew/Machine Resources button.

View the resource details for the crew or machine.

Click to jump to top of pageClick to jump to parent topicEntering Actual Hours Information

Access the Record Actual Hours page (Production Control, Process Production, Complete Production, Record Actual Hours, Record Actual Hours).

Op Seq (operation sequence) and Work Center

Select values for either field. If you select the operation sequence, the work center, crew, and machine information associated with the operation sequence appears on the page.

You can, however, change these values.

For production IDs, the operation sequences listed are from the production ID's operation list. The operation sequences for production schedules are the item's routing for the routing code specified for the area or item.

If you select the work center, you can select from all available work centers to accommodate any changes that might have occurred on the routing during production. Once you select the work center, the default crew and machine information appears based on the work center information. You can accept or change these defaults.

Note. If you then enter an operation sequence, the work center information is changed to the work center associated with the operation sequence, if it is different.

Crew Reporting

If you select this option, the system multiplies the actual labor hours that you record by the crew size to determine the total number of actual labor hours for performance reporting.

Machine Reporting

If you select this option, the system multiplies the actual machine hours that you record by the number of machines to determine the total number of actual machine hours for performance reporting.

Labor Hours or Machine Hours

Enter the number of hours based on:

  • Setup

  • Run

  • Fixed run

  • Post production

Note. Enter negative hours in these fields to correct data entry errors.

Scheduled

Enter any number of scheduled hours when there is known downtime for the work center. Scheduled hours are used to calculate labor and machine utilization. If no scheduled hours are entered, the system calculates the available hours based on either the work center or production calendar.

Note. You can enter actual hours for any labor or machine time type even if the time type wasn't included for planning or costing purposes. For example, if no costing postproduction time was specified for the operation, but actual time was spent cleaning up the work center once production was completed, you can still enter those actual hours.