Managing Crew Scheduling

You can manage resource assignments by directly assigning resources to work orders, or you can use crew scheduling. When you use crew scheduling, you assign work orders to a crew, and the system uses the information that you set up for each crew to assign resources to the work orders.

This chapter provides an overview of crew scheduling, lists common fields, and discusses how to:

Note. Many of the resource assignment processes, such as locating resources, assigning resources to tasks, and revising resources are similar, or the same, whether you are using crew scheduling or assigning resources directly to work orders. These processes are documented in a separate chapter.

See Also

Locating Resources

Assigning Resources to Tasks

Understanding Revising Resource Assignments

Click to jump to parent topicUnderstanding Crew Scheduling

Note. Typically, the process of assigning resources to work orders manually is used only when you do not use the crew scheduling process. If you are creating crew schedules, you use the Work With Work Assignments program (P48330) to assign resources to the schedule and not directly to the work order.

However, many of the processes, such as locating resources, assigning resources to tasks, and revising resources are similar, or the same, whether or not you are using crew scheduling. Therefore, it is suggested that you review the information in this chapter even if you are implementing crew scheduling.

A common practice within a maintenance environment is the preparation of a schedule of work for a crew which has responsibilities for a particular area and craft (trade). When preparing the schedule, the maintenance scheduler must consider both supply and demand variables. The demand variables can include upcoming preventative maintenance work, reactive work orders, allowance for emergency work orders and work orders not completed in previous periods. On the supply side, the variables consist of capacity by craft for a crew, vacation and holidays, training, material availability, and special scheduling requirements.

Crews

Crews consist of groups of employees designated by crafts (trades) that work as a team and are assigned work based on the total time available for the crew/craft instead of by individual resource availability.

Crew Scheduling

The crew scheduling process establishes a realistic target of work for the crew to complete during the next schedule period and monitors how well the crew performed to the schedule. The crew availability is based on the individual resource availability within the crew/craft and is reduced by the percent load target to allow for unplanned work and break in work. Over time, as the crew's capacity to complete scheduled work increases, the percent load is adjusted to maintain a realistic target and to reduce the amount of unplanned work.

Work Order/Planning

The Work Order/Planning module supports the entry of the work request and the planning of the labor detail steps required to complete the work. It also assists the scheduler in deciding who should do the work and when. The work order includes the crew and the lead craft with overall responsibility for completing the job, and specifies the material requirements to complete the work order. The labor detail contains the work steps required to complete the work and can be used when multiple crews and schedule periods are required. Work can be scheduled either at the work order level or work order labor detail level based on the work order document type and the Resource Assignment Level (UDC 48/RL) setting.

Preventative Maintenance

The Preventive Maintenance module supports projecting the preventive maintenance schedules for a specified date range in order to include the projected work load in the crew scheduling process. The Maintenance Rules program (P1393) is used to define if an asset/service type combination is to be scheduled automatically when it comes due. When the PM Projection program (R13411) is run, the projection includes the crew, work order coding and the schedule rule based on the Maintenance Rules. If the projection is flagged to be automatically scheduled it will display on the Manage Schedule program (P48320). The projection can be unscheduled if you click theRemove from Schedule button, or can be scheduled if you click the Add to Schedule button on the PM Forecast Review program (P48324). The PM Status Update program (R12807) is run to create a work order and to create a crew schedule based on the PM projection schedule rule if it exists or the Maintenance Rules.

Maintenance Schedule Periods

The Maintenance Schedule Periods program (P48302) allows you to define a Schedule Pattern Code (13/SP) and to set the date range for the scheduling periods. The current schedule period is flagged to indicate the period the crew is currently working in. The next schedule period is where the scheduler is building the work schedule for the next period. When you set up a crew in the Resource Master program (P48310), you associate a schedule pattern code to the crew.

Schedule Metrics - Crew Availability

The Schedule Metrics program (P48315) allows you to define the crew availability by schedule period which is used as the target availability when assigning work to the crew/craft during the scheduling process. The crew availability is based on the expected availability of the individual resources within the crew then reduced by the load percent. The load percent is the target value used to reduce the expected availability for the crew to allow for unscheduled events so a realistic target is set for the crew to achieve.

Manage the Schedule

The Crew Manage Schedule program (P48320) allows you to review and manage the crew schedules. The scheduled preventive maintenance projections and current scheduled work orders will display. The scheduled work is either at the work order level or work order labor detail based on the work order document type and the Resource Assignment Level (UDC 48/RL) setting. The application displays scheduled work by crew, craft, and schedule period.

The Crew Manage Schedule program allows you to manage the schedule using the following programs:

Crew Availability by Craft

As work is assigned to the crew, the Crew Availability by Craft is refreshed displaying the target available hours, scheduled hours, variance, scheduled, and load percent to assist the scheduler in producing the schedule.

Save the Schedule

Once the next schedule has been produced and agreed on by maintenance and operations, the form option to save the schedule can be used to flag the scheduled work, total the scheduled hours by crew/craft, and update the totals to the Crew Schedule Metrics table (F48315).

Roll the Schedule

At the end of each schedule period, the current schedule period needs to be forwarded to the next period so that the work assignment and scheduling applications reflect the new schedule periods. This can be done manually from the Maintenance Schedule Period program (P48302) or by running the Crew Schedule Roll Periods program (R48325).

Crew Work Assignments

The Crew Work Assignments program (P48330) allows you to review the current schedule of work for the crew that has not been completed and assign individual resources to the crew schedule. The system displays the crew schedule for the current period, which includes the individual resources for the crew and their remaining available hours.

The Crew Work Assignment program allows you to:

Unscheduled Break in Work

During the week, if additional work is required to be carried out by the crew, access the Manage Schedule program (P48320) for the current period and review the current schedule for crew availability. Use the exit to the Unscheduled Work program (P48321) to add additional work to the current period. If required, remove existing scheduled work to provide capacity to complete unscheduled work or a break in work.

Reschedule Metrics

If a current schedule must be moved to a future period, the Reschedule Metrics program (P48316) is displayed to allow the input of a Reason Code (UDC 48/RS), and a text description as to why the task is being rescheduled. The Reschedule Metrics program also enables you to review reschedule information by crew.

Completion

To support the completion of labor detail steps, a new form has been added to the Crew Work Assignment (P48330) program to enable the input of the operation status and completion date at the labor detail step. The completion of a work order schedule will display the work order program.

Supply and Demand Inclusion Rules

The Supply and Demand Inclusion Rules program (P34004) is used to define the work order and operation status values associates with open work order and labor detail steps.

Crew Schedule Completion Metrics

The Crew Schedule Completion Metrics program (R48327) details the work completed during the schedule period and provides totals by crew and craft for the saved schedule work and the total hours completed. Processing options enable you to run the report for a past schedule period, and will include work with a completion date within that schedule period. If the report is run in final mode, it will update the schedule completion information for the crew to the Crew Schedule Metrics table (F48315).

Schedule Metrics - Schedule Compliance

The Crew Schedule Metric program (P48315) allows you to review and maintain the schedule completion information for the crew, craft and schedule period. The schedule compliance and percent scheduled metric information is also displayed. The Schedule Completion information can be updated using the Crew Schedule Completion Metrics program (R48327), or manually input using the program.

Reports

The system includes standard reports to support the scheduling and assignment processes. Reports for crew availability, crew schedule, carryover work, and unscheduled work can be generated using the Schedule Report program (R48342). Reports for the assignments by crew, supervisor, employee and sorted by schedule date can be generated using the Work Assignment Package program (R48345).

Click to jump to parent topicCommon Fields Used in This Chapter

Assigned Hours

Review the hours assigned to an individual or a crew.

Available Hours

Review the total hours available for scheduled work during the schedule period. The system multiplies the available hours by the load percent to calculate the target hours to schedule.

Backlog

Review the list of all work that has not been completed. This includes both scheduled and unscheduled work that has not been completed.

Calculated Hours

Review the calculated hours for the crew/lead craft for the schedule period date range, which is derived using the Resource Master (P48310) and Resource Working Hours (P48307) setup information. The resource master for an individual employee defines the crew and lead craft with which they are associated. The resource working hours defines their available hours.

Carryover Work

Review work orders scheduled to be completed in a previous schedule period that have not yet been completed. These work orders need to be rescheduled or returned to the unscheduled backlog.

Completed Hours

Enter the total hours completed by the crew during the schedule period.

Completed Scheduled Hours

Enter the total hours of scheduled work completed by the crew during the schedule period.

Craft

Enter the craft (trade) that is required to complete the task. When the task is scheduled, the crew/craft availability is reduced by the estimated hours on the task.

Labor Detail

Defines the tasks required to complete the work, especially for larger jobs that require multiple crews/crafts and cross multiple schedule periods. The task contains planning information such as the task description, craft, estimated hours and task status. Each work order typically only has one task however larger jobs might required multiple tasks.

Load % (load percent)

Review the portion of the available hours that will be considered for scheduling work. The load percent should be set to provide a realistic target for the crew to achieve.

Schedule Compliance

Review the percentage of estimated hours scheduled that was completed, divided by the total estimated hours scheduled to be completed in the same period. It is a measure of the crews ability to complete the work scheduled during the schedule period. This value is typically represented by a percentage and will always be less than or equal to 100 percent. The closer the percentage to 100, the better the performance for the time period.

Schedule Dates

Enter the dates when the work is currently scheduled to be completed. These dates are recorded on the crew schedule record in the Resource Assignment Detail (F48311) table.

Scheduled Hours

Enter the total hours scheduled by the crew during the schedule period.

Schedule Pattern

Enter a code used to specify a schedule pattern utilized in maintenance scheduling. For example, M could stand for a weekly scheduling pattern starting on Monday with a 7-day period; 2 could stand for biweekly with a 14-day period. The number of days utilized for display and processing is defined in the special handling code of UDC 13/SP (Schedule Pattern). The schedule pattern is associated to a crew in order to determine the scheduling periods tied to the crew when defining availability and scheduling work.

Schedule Period

Review the date range covering the maintenance scheduling periods. Current, Next and Following schedule periods are typically used when scheduling and cover the work currently being processed and the next two scheduling periods being developed. Typically a schedule period is defined as a week (Monday to Sunday). However, schedule periods are user defined and can include any number of days necessary to meet the needs of the organization.

Click to jump to parent topicEntering Work Orders and Planning for Crew Scheduling

This section provides an overview of work orders and planning for crew scheduling, and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Work Orders and Planning for Crew Scheduling

The planner/scheduler is responsible for confirming the coding on the work order and developing the job plan. The job plan includes the labor detail steps and the materials that are required to complete the job. The scheduling process is supported at both the work order and job plan levels, based on the work order document type and Resource Assignments Level (UDC 48/RL).

The work order includes the default crew and lead craft (trade) that are required to complete the work, along with the estimated hours and planned start and finish dates, which you use when scheduling work at the work order level.

The labor detail job plan can have one or more steps, depending on whether the job requires multiple crews, crafts, or schedule periods to complete. Each labor detail step has a craft, description, estimated hours, and planned start and finish dates, which you use when scheduling work at the work order labor detail level.

The system determines the materials that are required to complete the work using the parts list that is associated with the work order. Materials that are required for the work order may be stocked items or direct charge items. The stocked items will be committed to the work order and are issued out of stock. The direct charge items are ordered using a purchase requisition prior to the work order release. When the job plan is complete, the work order is available for inclusion in the scheduling process.

You use the Work Order Entry program (P13714) to add and review the work order. You use the work order to track the crew, lead craft, parts, and labor details that are associated with a job. You can set a processing option for the P13714 to enable the system to automatically populate the Crew field on the work order using the SWM address book extension record for the customer, the equipment, or the work order category codes, which you enter on the work order.

You use the Work Order Detail program (P13732) add and review labor detail steps that are required to complete the work. These steps include the craft that is required to complete the step. You can set a processing option for the P13714 to automatically create the labor detail steps. The system creates the first labor detail step based on the work order details if the lead craft is entered. If you enter labor detail steps, the system totals the estimated hours for each step and updates the work order estimated hours field, which becomes disabled.

Based on the assignment level, the system aligns the estimated hours on the work order or the labor detail steps with the crew scheduled hours and proportionally splits the work into assignments.

The work order planned start and finished dates can be used as filters when searching for unscheduled work for a crew and a particular period. Once the work order or labor detail step is scheduled, the schedule dates become the key dates when assigning resources and moving tasks to different schedule periods. Changes to the work order/labor detail planned dates will not update the crew or resource schedules. If you are not using crew scheduling, changes to the work order/labor detail steps will continue to update the assignment dates.

The system will only allow one schedule per work order, or one schedule per labor step based on the UDC 48/RL setting.

See Also

Creating Work Orders Using the Work Order Entry Programs (P48201 and P17714)

Click to jump to top of pageClick to jump to parent topicForms Used to Create Work Orders for Crew Scheduling

Form Name

FormID

Navigation

Usage

Search For Equipment Work Orders

W13700B

Crew Scheduling (G13RA12), Planning Workbench

View, add, or revise work orders.

See Creating Work Orders Using the Planning Workbench Program (P13700).

Work Order - Manage <Work Order Name>

W13714B

On the Search For Equipment Work Orders form, select a record.

View the Planning and Labor tab details

Work Order Labor - Manage <Work Order Name>

W13732A

On the Work Order - Manage <Work Order Name> form, select the Labor tab.

Review labor detail steps.

Click to jump to top of pageClick to jump to parent topicReviewing Work Order Detail (P13714)

Access the Work Order - Manage <Work Order Name> form. Select the Planning tab.

Status

Enter a user defined code (00/SS) that describes the status of a work order, rate schedule, or engineering change order.

Planned Start Date

Enter the planned start date for the order. A planning date that the system calculates using the work order parts list and labor detail steps and indicates when job should be ready for scheduling.

Planned Finish Date

Enter the planned finish date for the order. A planning date that the system calculates using the work order labor detail steps and indicates when job should be completed by.

Actual Finish Date

Enter the date that the work order or engineering change order is completed or canceled.

Status Comment

Enter a brief description to explain the status of the work order.

Crew

Enter a user defined name or number that identifies an address book record for a crew. You can use this field to enter and locate information. If you enter a value other than the address book number (AN8), such as the long address or tax ID, you must precede it with the special character that is defined in the Address Book constants. When the system locates the record, it returns the address book number into the field.

Lead Craft

Enter an alphanumeric code used to define the lead craft required to complete the work. The value entered is used as the default craft (work center) when new labor detail records are added to the work order.

Supervisor

Enter a user defined name or number that identifies an address book record for a supervisor. You can use this field to enter and locate information. If you enter a value other than the address book number (AN8), such as the long address or tax ID, you must precede it with the special character that is defined in the Address Book constants. When the system locates the record, it returns the address book number into the field.

Parent WO

Enter a number that identifies the parent work order. You can use this number to:

  • Enter default values for new work orders, such as Type, Priority, Status, and Manager.

  • Group work orders for project setup and reporting.

Click to jump to top of pageClick to jump to parent topicReviewing Labor Detail Steps (P13732)

Access the Work Order Labor - Manage <Work Order Name> form.

Review, update, and add details to the labor detail steps.

Work Center

Enter an alphanumeric code that identifies the lead craft that is required to complete the individual steps on a work order. Typically a work center represents a business unit, which might be a warehouse location, job, project, work center, branch, or plant, or maintenance work group (craft).

Operation Sequence # (operation sequence number)

Enter a number used to indicate an order of succession.

In routing instructions, a number that sequences the fabrication or assembly steps in the manufacture of an item. You can track costs and charge time by operation.

In bills of material, a number that designates the routing step in the fabrication or assembly process that requires a specified component part. You define the operation sequence after you create the routing instructions for the item. The Shop Floor Management system uses this number in the backflush/preflush by operation process.

Description

Enter brief information about the labor detail step; a remark or an explanation.

Estimated Hours

Enter the standard hours of labor that you expect to incur in the normal production of this item. The run labor hours in the Routing Master table (F3003) are the total hours that it takes the specified crew size to complete the operation. The hours are multiplied by the crew size during shop floor release and product costing.

Click to jump to parent topicWorking with Crew Availability

This section provides an overview of crew availability, lists prerequisites, and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Crew Availability

One of the first processes performed each schedule period is estimating the available capacity of the crew to complete scheduled work during the schedule period. The crew capacity is typically broken down into a number of lead crafts indicating availability to work on the backlog of unscheduled work.

The crew availability is based on the expected availability of the individual resources within the crew/craft and reduced by a load percent. The load percent is a target value used to reduce the expected availability of the crew/craft work group to allow for unscheduled events in order to achieve a realistic target for the work group. As the crew/crafts estimating and capacity to complete scheduled work improves, the load percent is adjusted to maintain a realistic target.

The Crew Schedule Metrics program (P48315) will be used to define crew availability. When defining availability, the system populates the schedule pattern and the next schedule period that needs to be defined for the crew. As you proceed to enter data for the crew, the system creates a line for each lead craft defined in the resource master for each individual associated with the crew. The system will calculate the resource available hours for the crew/craft by totaling the working hours for the individuals with the same crew/craft combination for the schedule period. The crew standard hours, available hours, and load percent can then be entered for each lead craft. At a minimum, you should maintain the current, next, and following crew/craft availability metric information. The copy option will copy the details for the selected row and populate the dates for the next schedule period not currently defined.

Click to jump to top of pageClick to jump to parent topicPrerequisites

Complete these steps prior to creating the Crew Availability:

  1. Set up Schedule Periods (P48302) and current period.

  2. Set up crews using Resource Master (P48310) associating the schedule period code.

  3. Set up individuals within each crew, specifying the lead craft for each individual.

  4. Set up resource hours for individuals using Resource Working Hours (P48307).

See Also

Defining Crew Maintenance Schedule Periods

Assigning Resources to a Crew

Defining Resource Working Hours

Click to jump to top of pageClick to jump to parent topicForms Used to Work with Crew Availability

Form Name

FormID

Navigation

Usage

Work With Maintenance Schedule Metrics

W48315A

Periodic Resource Assignment Processing (G13RA20), Crew Schedule Metric

Access forms to view and update crew schedule metrics.

Crew Availability Revisions

W48315B

On the Work With Maintenance Schedule Metrics form, select a record.

View and update crew schedule metrics.

Click to jump to top of pageClick to jump to parent topicSetting Processing Options for Crew Schedule Metric (P48315)

Use these processing options to set default values for the Crew Schedule Metric program.

Defaults

Use this processing option to determine whether or not a manual update to the schedule compliance program is allowed.

Allow Update of Schedule Compliance

Specify whether or not the user is allowed to update the schedule compliance data using the Schedule Compliance row exit. Values are:

Blank: Do not allow.

1: Allow.

Click to jump to top of pageClick to jump to parent topicDefining Crew Availability

Access the Work With Maintenance Schedule Metrics form.

Lead Craft

Enter an alphanumeric code used to define the lead craft required to complete the work. The value entered is used as the default craft (work center) when new labor detail records are added to the work order.

Standard Hours

Enter the total hours that should be available to carry out work during the schedule period based on all the resources in the crew being fully available for scheduled work.

Available Hours

Enter the total hours available for scheduled work during the schedule period. The available hours is multiplied by the load percent to calculate the target hours to schedule.

Load % (load percentage)

Enter a numeric value that represents the percentage of the available hours that is to be considered for scheduling work. The load percent should be set to provide a realistic target for the crew to achieve.

Target Hours

Enter the target hours available for scheduling work. The value is the product of the available hours multiplied by the load percent.

Calculated Hours

Enter the calculated hours for the crew or lead craft for the schedule period date range is derived using the Resource Master (P48310) and Resource Working Hours (P48307) setup information. The resource master for an individual employee defines which crew or lead craft they belong. The resource working hours defines their available hours.

Click to jump to parent topicCreating the Crew Schedule

This section provides an overview of the crew schedule and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding the Crew Schedule

The Manage Schedule program (P48320) is used to review the work orders and PM projections scheduled for the current schedule period or to select a different schedule period to review. The processing options determine the default schedule period that will be used to review the crew schedule. The scheduled work can either be removed from the schedule or moved to a different schedule period or a particular date.

Work is added to the schedule using the following search links:

As work is scheduled to the crew, the Crew Availability by Craft is refreshed displaying the target available hours, scheduled hours, variance, scheduled and load percent to assist the scheduler in producing the schedule.

The schedule for the next and future schedule periods can include the projected PM work load prior to the actual work order being created. The planner can review the PM work load and decide if it should be included in the schedule period when due. Prior to saving the schedule, the PM schedule needs to be triggered due so the actual assigned work order is included in the schedule.

Once the schedule for the next period has been finalized and approved, the Save Metrics form action is used to save the schedule detail and update the scheduled compliance information to the F48315 metrics table.

Click to jump to top of pageClick to jump to parent topicForms Used to Work with the Crew Schedule

Form Name

FormID

Navigation

Usage

Manage Schedule

W48320B

Crew Scheduling (G13RA12), Crew Scheduling Workbench

View work orders in a specified schedule period by crew, supervisor, or craft.

Save Metrics Confirmation

W48320C

On the Manage Schedule form, select Save Metrics from the options in the More Form Actions field.

Saves schedules agreed to for the next schedule period.

Click to jump to top of pageClick to jump to parent topicReviewing the Crew Schedule

Access the Manage Schedule form.

Review schedule periods by crew, supervisor, or craft.

Select work orders and then click the Remove from Schedule button to remove the order from the schedule and put it into the unscheduled backlog. Use the Move To selection to move orders to a different schedule period or date.

Click to jump to top of pageClick to jump to parent topicSaving Schedule Changes

Access the Save Metrics Confirmation form.

From Manage Schedule, select the next period and select the Save Metrics option on the More Form Actions menu.

Click to jump to parent topicSearching for Unscheduled Work for Crew Scheduling

This section provides an overview of the search for unscheduled work and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding the Search for Unscheduled Work

One of the main sources of work when creating the next schedule is searching through the work in the backlog that is currently not scheduled. Once a work order is in the backlog, the job plan is developed to support the scheduling of the tasks required to complete the work. During the scheduling meeting, the unscheduled backlog of work is reviewed and selected work is agreed to be included in the next schedule. After the meeting, the scheduler searches through the list of unscheduled jobs and selects those that were agreed to be included. This can involve doing multiple searches by work order number or work order coding to find and select the work orders or labor detail steps. As work is selected for inclusion in the schedule, the crew/craft availability is refreshed.

You use the Manage Schedule program (P48320) to review work for a specific crew and schedule period. You access the search for unscheduled work (backlog) by clicking the link to the Unscheduled Work program (P48321). You can select unscheduled work and add it to the crew and schedule period described at the top of the form. To schedule backlog work to a different crew or period than you originally accessed, you must return to the Manage Schedule program and change the crew and schedule period, or use the Schedule by Work Order program (P48326).

You can use the filters in the header section of the Unscheduled Work program to search for work orders. You can use the craft to additionally filter to the labor detail level. As work is selected, click the Add to Schedule button. The system displays each order that you add to the schedule in the Selected Unscheduled Work grid. You can review the list and remove work if necessary.

A processing option setting enables you to select a work order that has a document type requiring scheduling at the labor detail level. The system does not display an error, but instead schedules all of the labor detail steps associated with the selected work order. All unscheduled labor steps are scheduled, even if they are not displayed due to filtering.

The Crew Availability by Craft at the bottom of the form can be used to confirm that the target and scheduled hours are as expected prior to the when you click the Save and Close button that updates the tables with the work selected.

Click to jump to top of pageClick to jump to parent topicForms Used to Search for Unscheduled Work

Form Name

FormID

Navigation

Usage

Manage Schedule

W48320B

Crew Scheduling (G13RA12), Crew Scheduling Workbench

Scroll to the Crew Availability by Craft to view the target hours, scheduled hours, variance, and calculated schedule and load percent.

Search for Unscheduled Work

W48321A

On the Manage Schedule form, click the Unscheduled Work link.

Review and schedule backlog.

See Also

Managing Large Jobs in Crew Scheduling

Click to jump to top of pageClick to jump to parent topicReviewing Unscheduled Work

Access the Search for Unscheduled Work form.

  1. Review the unscheduled work.

  2. Scroll to the Selected Unscheduled Work region.

  3. Select work orders and click the Add to Schedule button to include in Selected Unscheduled Work grid

  4. Click the Save and Close button to include the orders on the schedule.

  5. Click the Remove button to remove orders selected to be included on the schedule.

Click to jump to top of pageClick to jump to parent topicReviewing Crew Availability by Craft

Access the Manage Schedule form. Scroll to the Crew Availability by Craft group box.

Scroll to the bottom of the screen to review the crew target hours, scheduled hours, variance, and calculated schedule and load percent for each craft.

Target Hours

Enter the target hours available for scheduling work. The value is the product of the available hours multiplied by the load percent.

Scheduled Hours

Enter the total hours scheduled by the crew during the schedule period.

Variance

Enter the hours available by craft. Negative hours will highlight as a warning.

Scheduled % (scheduled percentage)

Review this value to determine the percent scheduled. This is the percentage of scheduled hours to target hours.

Load % (load percentage)

Review this value to determine the load percent, which is the portion of the available hours that is to be considered for scheduling work. The load percent should be set to provide a realistic target for the crew to achieve.

Click to jump to parent topicRescheduling Work Not Completed

This section provides an overview of rescheduling work not completed and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Rescheduling Work Not Completed

To reschedule work users must review the work that was previously scheduled but not completed, and move that work to the current schedule period, to a future schedule period, or back to the unscheduled backlog. When you reschedule work, the system displays the rescheduling details form where you can enter the reason code and text explanation as to why the work is being rescheduled. The rescheduling details form is available from the Carryover Work program (P48323) when moving work, and from the Manage Schedule (P48320) and Work Assignments (P48330) programs when moving work from the current period.

When a crew schedule is moved to another schedule period, the start and finish dates on the crew schedule are updated to the start and finish dates of the schedule period it is moved to. If any resource assignments are associated with the crew schedule, they are also updated to the start date of the new schedule period.

The processing option for the Carryover Work program (P48323) is used to define the Supply and Demand Inclusion rule to be used to determine what work order and labor detail step status values are still open.

To conclude the process, you can go to the Maintenance Rescheduling Metrics Revisions program (P48316) in order to review reasons for rescheduling by crew, rescheduling code and date range.

Click to jump to top of pageClick to jump to parent topicForms Used to Reschedule Work Orders

Form Name

FormID

Navigation

Usage

Search for Carryover Work

W48323A

Crew Scheduling (G13RA12), Crew Scheduling Workbench.

On the Manage Schedule form, click the Carryover Work link.

Select the work orders not completed in previous periods to include in the current crew schedule or to move to a different schedule period.

Maintenance Rescheduling Metrics Revisions

W48316B

On the Manage Schedule form, select the work order to remove and click the Remove From Schedule button

Select a Rescheduling Code and enter additional text to track changes made to the schedule.

Click to jump to top of pageClick to jump to parent topicReviewing Carryover Work

Access the Search for Carryover Work form.

  1. Select the work orders to reschedule.

  2. To remove the work order, click the Remove from Schedule button.

  3. To move the work order to another period, select one of the options from the Move Todrop-down list box, and then click the Go button.

Click to jump to top of pageClick to jump to parent topicEntering Reason Codes to Track Rescheduling Metrics

Access the Maintenance Rescheduling Metrics Revisions form.

Rescheduling Code

Enter a user defined code (48/RS) that indicates the reason why a task has been rescheduled.

Click to jump to parent topicWorking with PM Forecasts in Crew Scheduling

This section provides an overview of preventive maintenance (PM) forecasts in crew scheduling and discusses how to review PM forecasts.

Click to jump to top of pageClick to jump to parent topicUnderstanding PM Forecasts in Crew Scheduling

PM projections are another component of creating the crew schedule. You use PM forecasts to include the PM work load on the crew schedule prior to creating the assigned work order. The maintenance schedule flag, which is set in the maintenance rules table, is used to determine if the PM projection is to be scheduled when due or added to the unscheduled work backlog. Scheduled PM projections are displayed on the crew schedule either as the projection if scheduling at the work order level, or as the labor detail steps from the associated labor master setup using the Standard Routing program (P3003). The PM projections, both scheduled and unscheduled, can be reviewed and the maintenance schedule flag changed from the maintenance rules table default value if required. When the work comes due, a work order is generated and can either be added to the crew schedule or unscheduled backlog based on the maintenance schedule flag on the projection.

The crew schedule process is initiated by running the PM Projection program (R13411) which creates the forecast table. The Manage Schedule program (P48320) is used to review and remove the PM projections generated from the crew schedule. The Remove from Schedule button will remove the PM projection from the schedule period by updating the maintenance schedule flag on the projection to unscheduled. The PM Forecast Search & Select program (P48324) is used to review the PM projection based on the selected crew, schedule date range, and the maintenance schedule flag. This program will allow you to review the PM projections by schedule period that are currently flagged for inclusion on the crew schedule, or the unscheduled backlog when the work order is created. The unscheduled PM projections that are new, or originally removed from the schedule, can be moved to the crew schedule if you click the Add to Schedule button.

When the PM comes due, a work order must be created by running a version of the PM Update Status program (R12807) which has the PM forecast type defined as a processing option. The PM Update Status program can be run in batch or for selected PM projections. Click the PM Forecast link to review the PM projections for the current schedule. The work order can be generated if you click the Create Work Orderbutton to convert the PM projection to an active work order. The work order number is displayed on the current schedule instead of the PM projection.

When the PM Update Status program is run and a work order is created, the system will first check for a matching PM projection if a forecast type is defined in the processing option, or it will use the maintenance schedule flag in the maintenance rules table to determine if a crew schedule should be created. If the PM projection is found for the equipment/service type, the PM forecast will be deleted.

See Also

Setting Up PM Rules for Schedules

Working with Preventive Maintenance Schedules

Working with Maintenance Forecasts

Click to jump to top of pageClick to jump to parent topicForm Used to Work With PM Forecasts in Crew Scheduling

Form Name

FormID

Navigation

Usage

Search for PM Forecasts

W48324A

Crew Scheduling (G13RA12), Crew Scheduling Workbench.

On the Manage Schedule form, click the PM Forecasts link.

View the unscheduled or scheduled PM work by crew, supervisor, lead craft, and the schedule period to include in the schedule or to create a work order.

Click to jump to top of pageClick to jump to parent topicReviewing PM Forecasts

Access the Search for PM Forecasts form.

Review PM forecasts for a specific schedule period and click the Add to Schedule button to add the work order to the crew schedule.

Click the Create Work Order button to generate a work order for the PM forecast.

Click to jump to parent topicReviewing the Crew Schedule

This section provides an overview of crew schedule review, lists a prerequisite, and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Crew Schedule Review

You review the crew schedule to verify the work that is to be completed by the crew/craft for the schedule period. Multiple searches can be conducted using the crew, craft, supervisor, and schedule period combinations. The schedule period allows the scheduled work to be displayed for the current, next, following, or specific period in the future. The Manage Schedule program (P48320) displays the following crew/craft scheduling details:

The Manage Schedule program (P48320) is used to review, add, and update the work on the schedule for the crew and selected schedule period. From this form, there are a number of form and row exits to perform updates to the schedule based on the requirements. These will be discussed in more detail in the following sections.

The Schedule Inquiry program (P48328) is a useful application to review all future and historical work scheduled for a crew for a specified date range. Once you know the date when it was scheduled, you can review that specific schedule period if required.

Click to jump to top of pageClick to jump to parent topicPrerequisite

Set the Crew Scheduling Workbench (P48320) processing option to designate the schedule period to display.

Click to jump to top of pageClick to jump to parent topicForms Used to Review the Crew Schedule

Form Name

FormID

Navigation

Usage

Manage Schedule

W48320B

Crew Scheduling (G13RA12), Crew Scheduling Workbench.

View work orders and PM work orders by crew/craft for a specified schedule period.

Scheduled Work Inquiry

W48328A

On the Manage Schedule form, select the More Form Actions option Schedule Inquiry.

View work completed and work scheduled in future periods.

Click to jump to top of pageClick to jump to parent topicSetting Processing Options for the Crew Scheduling Workbench Program

Use these processing options to specify the defaults for the Manage Schedule program (P48320).

Defaults

Access the Defaults tab.

1. Schedule Period

Specify the default schedule period the system uses when displaying the maintenance schedule. Values are:

1: Current Period (default)

2: Next Period

3: Following Period

2. Crew

Specify the default crew the system uses when displaying the maintenance schedule.

3. Supervisor

Specify the default supervisor the system uses when displaying the maintenance schedule.

4. Craft

Specify the default craft the system uses when displaying the maintenance schedule.

Process

Access the Process tab. Use this processing option to determine the forecast type to define the PM Projection to be considered for display on the crew schedule review.

1. Forecast Type

Specify the forecast type used to retrieve the preventive maintenance forecast records from the PM Projections (F13411) file. Enter a value from UDC 34/DF (Forecast Type). If you leave this option blank, the system uses MF as the forecast type.

Versions

Access the Versions tab. Use these processing options to set versions for these programs.

1. Unscheduled Work Search and Select (P48321) Version

Specify the version that the system uses for the Unscheduled Work Search and Select program (P48321). If you leave this processing option blank, the system uses the ZJDE0001 version.

2. Carryover Work Search and Select (P48323) Version

Specify the version that the system uses for the Carryover Work Search and Select program (P48323). If you leave this processing option blank, the system uses the ZJDE0001 version.

3. PM Forecast Search and Select (P48324) Version

Specify the version that the system uses for the PM Forecast Search and Select program (P48324). If you leave this processing option blank, the system uses the ZJDE0001 version.

4. Work Order Parts List Inquiry (P3121) Version

Specify the version that the system uses for the Work Order Parts List Inquiry program (P3121). If you leave this processing option blank, the system uses the ZJDE0001 version.

5. Work with Bill of Material (P3002) Version

Specify the version that the system uses for the Work with Bill of Material program (P3002). If you leave this processing option blank, the system uses the ZJDE0002 version.

6. Open Order Inquiry (P4310) Version

Specify the version that the system uses for the Open Order Inquiry program (P4310). If you leave this processing option blank, the system uses the ZJDE0013 version.

7. Maintenance Schedule Metrics (P48315) Version

Specify the version that the system uses for the Maintenance Schedule Metrics program (P48315). If you leave this processing option blank, the system uses the ZJDE0001 version.

8. Work Order Parts Detail (P17730) Version

Specify the version that the system uses for the Work Order Parts Detail program (P17730). If you leave this processing option blank, the system uses the ZJDE0001 version.

9. Work Order Labor Detail (P17732) Version

Specify the version that the system uses for the Work Order Labor Detail program (P17732). If you leave this processing option blank, the system uses the ZJDE0001 version.

10. Parts List (P3111) Version

Specify the version that the system uses for the Parts List program (P3111). If you leave this processing option blank, the system uses the ZJDE0001 version.

11. Routing Instructions (P3112) Version

Specify the version that the system uses for the Routing Instructions program (P3112). If you leave this processing option blank, the system uses the ZJDE0001 version.

12. Maintenance Work Assignments (P48330) Version

Specify the version that the system uses for the Maintenance Work Assignments program (P48330). If you leave this processing option blank, the system uses the ZJDE0001 version.

13. Scheduled Work Inquiry (P48328) Version

Specify the version that the system uses for the Scheduled Work Inquiry program (P48328). If you leave this processing option blank, the system uses the ZJDE0001 version.

WO Entry

Access the WO Entry tab.

1. Work Order Program

Specify the work order program that the system uses when you select a work order to review. Values are:

1: CAM Work Order Revisions (P13714).

2: Work Order Revisions (P17714).

3: Manufacturing Work Order Revisions (P48013).

Note. This processing option also specifies the labor and parts details programs that the system will use. Values 1 and 2 use the Work Order Labor Detail program (P17732) and the Work Order Parts Detail program (P48013); otherwise, the Work Order Routing program (P3112) and the Work Order Parts List program (P3111) is used.

2. Work Order Program Version

Specify the version of the selected work order program. If this option is left blank, the default version (ZJDE0001), will be used.

Click to jump to top of pageClick to jump to parent topicReviewing Future and Historical Work Scheduled

Access the Scheduled Work Inquiry form.

Search for future and historical orders by crew, supervisor, craft, and specified date range.

Click to jump to parent topicManaging Large Jobs in Crew Scheduling

This section provides an overview of large jobs in crew scheduling and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Large Jobs in Crew Scheduling

The scheduling of large jobs typically covers multiple work orders, labor detail steps, crews and or schedule periods. With this type of job, the work has been broken down into smaller tasks that are managed and scheduled separately, but need to be viewed together to illustrate the relationship between the tasks and the schedule periods. You can use two methods to individually track smaller parts of a large job.

First, you can use parent/child work orders. The parent/child work order structure is used to create a group of related work orders that are to be carried out against different business units or equipment for tracking costs and history. Multiple child work orders are created, each representing a part of the larger job. These work orders are all grouped under a parent work order, which represents the larger job as a whole.

Secondly, you can break down the pieces of a large job on a single work order using labor detail steps. Each step on the work order can be scheduled separately, using different crews and equipment. It is necessary to be able to search and filter by the parent work order number and view the associated child work orders and associated labor detail steps if scheduling at that level. The Schedule by Work Order program enables you to view projects using parent/child associations, and also to view labor detail steps associated with a work order.

During the planning or scheduling process, it becomes apparent that the work shall require multiple crews or schedule periods to complete the work. This will required the scheduler to access the work order labor detail program and create new steps for the work and split the estimated hours based on the scope for each new step. By splitting the labor detail steps, the scheduler then has the ability to assign a crew and or resources to the individual steps and monitor progress and schedule compliance at this level.

You use the Manage Schedule program to locate work orders and to break down the labor detail steps. You can use the link to the Unscheduled Work program (P48321), where you can select either the first step or all current steps planned on the job. You can use the More Row Actions option to access the Labor Detail program (P17732) in order to break a job down into multiple steps. To break a job into multiple steps, you can create a new operation step and split the estimated hours as required. Each step should have a clear description so that verifying the completion of a step can be easily verified, especially if you are splitting work over multiple schedule periods.

Once the labor detail steps are defined, you can click the Work Order link from the Manage Schedule program to access the Schedule By Work Order program (P48326). Use this program to review and schedule the labor detail steps for a work order, and to review the parent/child work order relationships. Select the each labor detail line to assign a crew and schedule period to the task.

Work already scheduled can be moved to a different crew or schedule period by selecting the labor detail step and updating the crew or schedule period.

Click to jump to top of pageClick to jump to parent topicForms Used for Managing Large Jobs in Crew Scheduling

Form Name

FormID

Navigation

Usage

Manage Schedule

W48320B

Crew Scheduling (G13RA12), Crew Scheduling Workbench.

Review the schedule for a crew.

Work Order Labor Details

W17732D

On the Manage Schedule form, select the More Row Action: Labor Detail.

View, split, or add new labor detail steps.

Scheduling by Work Order

W48326A

On the Manage Schedule form, click the link to the Order Number.

View and update Crew and Schedule Period.

View parent/child work order relationship and labor detail steps.

Click to jump to top of pageClick to jump to parent topicSplitting a Labor Detail Step

Access the Work Order Labor Details form.

  1. On the existing labor detail step, update the estimated hours to a value that represents a portion of the total hours for the step.

    For example, if the existing step includes 20 estimated hours, and you want to split the work equally between two resources, update the estimated hours field to 10.

  2. Enter one or more new labor detail lines, and include the number of estimated hours for each resource.

    For example, if you are splitting an existing labor detail line equally between two resources, and the original labor detail line included 20 estimated hours, you update the original line to include 10 estimated hours, and enter one additional line that includes 10 estimated hours.

    When you complete this process, the total number of estimated hours from all lines should be equal to the number of estimated hours from the original labor detail line before it was updated.

    Note. Each grid line should include the craft (work center), operation sequence number, description, and remaining hours.

Click to jump to top of pageClick to jump to parent topicScheduling Parent/Child Work Order Jobs

Access the Scheduling by Work Order form.

Review the parent work order number and the associated child order number.

Remove or move the work order to a different crew or schedule period.

Select the work order/labor detail step and either Remove from Schedule, Add or Change Crew or Move To a schedule period.

Note. If the header record is selected, the option to add a crew and schedule period is not available.

Click to jump to parent topicRevising the Current Crew Schedule

This section provides an overview of crew schedule revisions and discusses how to add unplanned items to the crew schedule.

Click to jump to top of pageClick to jump to parent topicUnderstanding Crew Schedule Revisions

After the schedule has been created the system must allow for scheduling emergency, unplanned, or minor work that was not originally scheduled. The planner/supervisor is typically responsible for initiating and managing breaks in work. You initiate this process from the Manage Schedule program by reviewing the current schedule and then accessing the link to Unscheduled Work program (P48321), which you use to select additional work to add to the schedule. The work selected is added to the current schedule and appears on the Work Assignments program (P48330) under the current period for the crew to carry out.

During this process, you can review the work in the current schedule and remove work to allow capacity to take on the new jobs added. When removing work from the current schedule, the Maintenance Rescheduling Metrics Revision program (P48316) appears, enabling you to enter the reason for rescheduling. Work can be removed from the current schedule if you click the Remove from Schedule or Move To buttons. The Remove from Schedule button moves the work back to the unscheduled backlog for rescheduling. Using the Move To options, you can move the work to the next period, the following period, or to a specific period in the future.

See Also

Searching for Unscheduled Work for Crew Scheduling

Rescheduling Work Not Completed

Click to jump to top of pageClick to jump to parent topicForm Used to Revise the Crew Schedule

Form Name

FormID

Navigation

Usage

Manage Schedule

W48320B

Crew Scheduling (G13RA12), Crew Scheduling Workbench

View and revise the work orders on the crew schedule for the current period.

Click the Unscheduled Work link to include unplanned or minor items on the schedule.

Click to jump to top of pageClick to jump to parent topicAdding Unplanned Items to the Crew Schedule

Access the Manage Schedule form.

Review the current schedule of work for the crew.

Click the Unscheduled Work link to search and select additional work for the current schedule.

Click to jump to parent topicChecking Inventory Availability for the Crew Schedule

This section provides an overview of inventory availability for crew scheduling and discusses how to check inventory availability for the crew schedule.

Click to jump to top of pageClick to jump to parent topicUnderstanding Inventory Availability for Crew Scheduling

As the job planning process continues, the system checks availability for the materials required for the orders in the schedule period. During the review of the crew schedule, a parts availability flag is displayed for each task on the schedule. The flag indicates:

A material shortage warning is displayed if there is a negative stock availability for an open part on the parts list, or an open purchase order exists for the work order. The parts availability screen can be accessed to review the availability for the individual parts on the work order, or to review the open order inquiry displaying open purchase orders required for the work order.

Click to jump to top of pageClick to jump to parent topicForm Used to Work with Parts Availability

Form Name

FormID

Navigation

Usage

Manage Schedule

W48320B

Crew Scheduling (G13RA12), Crew Scheduling Workbench

View the information as allowed by the following More Row Actions:

  • Open Orders

  • Parts Inquiry

Click to jump to top of pageClick to jump to parent topicChecking Inventory Availability for the Crew Schedule

Access the Manage Schedule form.

Review the Parts Availability column for warnings.

Select a record, then select the Parts Inquiry or Order Details option from the More Row Actions menu, and then click the Go button to review quantity details.

Click to jump to parent topicPrinting the Crew Schedule Report (R48342)

This section provides an overview of the print schedule program.

Click to jump to top of pageClick to jump to parent topicUnderstanding the Print Schedule Program

Prior to the scheduling meetings between maintenance and operations, it is necessary to run the Crew Schedule Reports program (R48342) and distribute for review prior to the meeting. Once corrections have been marked on the printed report, the maintenance scheduler can update the schedule and backlog to prepare the planned schedule for the following week. The reports that can be printed for the crew selected include:

The different sections of the schedule report the same information that is available using the online applications or individual report menu options. When this report is run for multiple crews, all sections for each crew are printed prior to processing the next crew. Therefore, the report can be split and issued to each crew efficiently.

See Also

JD Edwards EnterpriseOne Resource Assignments Reports

Click to jump to parent topicRolling the Schedule

This section provides an overview of rolling schedules and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Rolling Schedules

When the current schedule has ended, the schedule period needs to be rolled to the next period so the work assignment and scheduling programs display the new schedule period. The schedule for the next period is reviewed by the scheduler prior to rolling the schedule to ensure that it is complete and that it has been saved.

You run the Maintenance Schedule Roll Periods program (R48325) to move the Current Period flag in the Maintenance Schedule Period program to the next schedule period. This program is typically run for a schedule period and checks the date range of the current schedule with the through date in the processing options. If the through date is greater than the current period date range, the system increments the current period to the next period. The through date is automatically populated with the system date if left blank. You can also manually reset the current period using the Maintenance Schedule Periods program (P48302).

Note. The Maintenance Schedule Roll Periods program (R48325) is typically run on a regular schedule utilizing a system date to initiate the roll of the current period.

Click to jump to top of pageClick to jump to parent topicForm Used to Roll the Schedule for Crew Scheduling

Form Name

FormID

Navigation

Usage

Work With Maintenance Schedule Periods

W48302A

Resource Assignments Setup (G13RA41), Maintenance Schedule Periods

View the maintenance schedule periods.

Select the row exit Set Current to set the next schedule period.

Click to jump to top of pageClick to jump to parent topicSetting the Current Period Manually

Access the Work With Maintenance Schedule Periods form.

Select the period that you want to mark as the current period, and then select Set Current from the Row menu.

Click to jump to top of pageClick to jump to parent topicRunning the Maintenance Schedule Roll Periods Program (R48325)

Select Crew Scheduling (G13RA12), Crew Schedule Roll Periods.

Click to jump to top of pageClick to jump to parent topicSetting Processing Options for Maintenance Schedule Roll Periods (R48325)

Use these processing options to specify the schedule roll requirements.

Process

Use these processing option to run the program in proof or final mode; to determine where the report will write errors; to enter the address number of the message recipient; and to enter the through date to process the program.

1. Proof or Final Mode

Specify if the program results will be reviewed first, or if the system will be updated with the changes. Values are:

Blank: Proof Mode

1: Final Mode

2. Work Center Or Report

Specify where the system will publish messages. Values are:

Blank: Write errors to Work Center.

1: Write errors to Report.

3. Job Status Recipient

Specify the address book number of the recipient for receiving job status messages.

Note. If this processing option is left blank, the system will enter the address book number of the current user.

4. Through Date

Specify the through date the system will use to process selected schedule periods that will be rolled. The schedule periods that are defined as current and that have a period end date that is less than the date in the processing options, will be selected.

Note. If this processing option is blank, the system date is used.

Click to jump to parent topicAssigning Resources to Crew Schedules

This section provides an overview of resource assignments using crew scheduling and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Resource Assignments Using Crew Scheduling

After the crew schedule has been agreed to and saved by the scheduler, and the schedule period is rolled, the crew can begin to execute on the schedule. Resources are assigned or removed from the current crew schedule based on availability and competency for the work to be completed during the schedule period and in a scheduled day. If the work cannot be completed, or if it is determined that additional resources are required, adjustments can be made to the crew schedule to split the hours and resources required to complete the task.

Crew Work Assignments

The crew reviews the current schedule for the period and begins to assign resources to the current schedule based on the availability of the resources in the crew. Crew resources and availability are displayed in the resource search window following the list of scheduled work. Tasks on the schedule can be moved to allow for plant outages or balancing of individual resource availability for a particular day. During the schedule period, additional work can be added to the current schedule and the crew can revise their work assignments to allow for the changes. You can also move and reschedule existing work. When the scheduled work is done, the work order and schedule is reported as complete. If work is not completed for the schedule period or schedule day, the work is rescheduled.

The Work With Work Assignments program (P48330) allows you to review, assign, or remove resources to and from the schedule of work based on the resource availability for the period and day. The top section of the form supports the filtering and display of the work scheduled for the crew for the schedule period. The supply and demand inclusion rule defined in the processing options of the P48330 enables you to remove the completed work for the list during the schedule period.

The bottom section of the form supports filtering and display of resources that are available within the crew to complete the work. This section of the form displays the current available hours for each resource for the days within the schedule. You can access the Advanced Resource Search and Select (P48310S) using the visual assist on the Resource Number field. This program enables you to search using resource competencies. After you complete a resource search, the system displays the detailed availability and current assignments for the selected resource.

When assigning resources, the selected resource is added to the crew schedule task's selected using the crew assigned hours which is the same as the work order or labor detail estimated hours. For example, you can create a work order with a labor detail step that includes 12 estimated hours. You then schedule that work order detail step to a crew which currently has 12 available hours. You then assign resources to that crew. If you assign two resources to the crew, the system evenly distributes the assigned work between the resources, and assigns each of them 6 hours. You can then adjust the number of hours for each resource using Assignment Detail form (W48331B). If multiple resources are assigned to a crew schedule, the hours are split evenly between the resources. You can access the Assignment Detail (W48331B) form and adjust the individual assigned hours and dates as required using the link in the assignment column for the More Row options.

Note. If you change the estimated hours on the work order/labor detail steps, the crew schedule assigned hours is updated to reflect this change and the resource assignment hours are updated proportionally. If you change the planned start/finish dates on the work order/labor detail, they will not update the crew schedule or assignment dates. Changing crew schedule dates must be done using the Crew Scheduling programs.

When reviewing work assignments, you can also review the work order details, assignment details, and run the Assignment Work Sheet report (P48342), which lists the assignment details by crew, supervisor, and individual resource for the schedule period.

After the scheduled work is complete, you use row action options to access either the work order header or work order labor detail, where you can report the status as complete. Work orders not completed for the previous day, or orders that may not get done in the current period schedule can be moved to a specific date or a different schedule period.

Note. The crew assignment process follows the same general rules as the Resource Assignment program (P48331), the only difference is that the assignment is to the crew schedule and not directly to the work order/labor detail. Both applications create resource assignments in the Resource Assignments table (F48331).

See Also

Locating Resources

Assigning Resources to Tasks

Revising Resource Assignments

Click to jump to top of pageClick to jump to parent topicForms Used to Assign Resources to the Schedule

Form Name

FormID

Navigation

Usage

Work With Work Assignments

W48330E

Crew Scheduling (G13RA12), Crew Schedule Assignments

View the work orders on the weekly crew schedule for the specified period.

Select work order number and click Assign Resource to assign a resource to the order or move to a different schedule period or date.

View and revise Resource Search region for resource availability.

Availability and Assignments tabs

W48330ES1

On the Work with Work Assignments form, view the Availability and Assignments tabs.

View resource capacity, load, and availability.

Manage Schedule

W48320B

On the Work with Work Assignments form, select Go to: Manage Schedule

Click the application link to Unscheduled Work to include break in work on the schedule.

Click to jump to top of pageClick to jump to parent topicSetting Processing Options for Crew Schedule Assignments (P48330)

Use these processing options to specify the defaults for the Crew Schedule Assignments program (P48330).

Defaults

Use these processing options to specify default values on the Work With Assignments form.

1. Schedule Period

Specify the default value for the schedule period. Values are:

1: Current Period (default)

2: Next Period

3: Following Period

2. Crew, 3. Supervisor, 4. Craft, and 5. Resource Type

Specify the default value for the crew, supervisor, craft, and resource type.

6. Load Profile Method

Specify how the work will be distributed across the duration of an assignment when a resource is assigned. For example, when using the flat load profile the load is evenly distributed for the assignment across the duration. Current default value is:

1: Flat Load Profile

Process

Use these processing options to designate the number of periods; to select a default period type; to enter the supply and demand inclusion rules; to update the work order assigned to field; and to determine the operation status completion code.

1. Number of Periods

Specify the number of periods to calculate availability and assignment load. The periods are expressed as days or weeks based on the Period Typefield.

Note. If the Number of Periodsis set beyond 52, the system uses 14.

2. Period Type

Specify the Period Type to group the display of assigned hours and capacity hours for a resource. UDC 48/PT (Period Types) will be used to select values. The default value is Blank: Days.

3. Set Default for Supply/Demand Inclusion Rules

Specify the default value from UDC 40/RV.

4. Update Work Order Assigned To Field

Specify of the system will automatically update the Assigned Tofield on the work order header when the Resource Assignments program (P48331) is run. The system will also update the Assigned Tofield when it is blank or when you change the assignment resource number, which is the same as the number on the work order. Values are:

Blank: Do not update.

1: Update.

5. Operation Completion Status

Specify the operation completion status that the system uses to update the labor detail step when completed. Select the default value from UDC 31/OS (Operation Status).

Note. This processing option only applies when you assign resources at the work order level.

Versions

Use these processing options to set versions for these programs:

1. Maintenance Schedule Review (P48320) Version, 2. Work Order Labor Details (P17732) Version, 3. Routing Instructions (P3112) Version, and 4. Assignment Detail (P48331) Version

Specify the version of the corresponding program that the system uses during resource assignment. If you leave these options blank, the system uses the default version ZJDE0001.

5. Assignment Work Sheet (R48345) Version

Specify the version of the Assignment Work Sheet that the system uses during resource assignment. If you leave these options blank, the system uses the default version XJDE0001.

Work Order Entry

Use these processing options to set the work order program to be used and the default version.

1. Work Order Program

Specify the work order default program. Values are:

1: CAM work order (P13714) (default)

2: Work Order (P17714)

3: Manufacturing Work Order (P48013)

2. Work Order Program Version

Specify the work order default version by entering a version or using the default value of ZJDE0001.

Click to jump to top of pageClick to jump to parent topicAssigning Resources to Crew Schedule

Access the Work With Work Assignments form.

Search for assignments by crew, supervisor, or craft and schedule period.

Scroll to the Resource Search region.

Review and select the work order to assign a resource to, select the resource, and click the Assign Resource button.

Note. If an incorrect resource is assigned, select Remove Resources from the More Row Actions menu to remove the assigned resources.

Click to jump to parent topicCompleting Orders on the Schedule

This section provides an overview of completing orders on the schedule and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Completing Orders on the Schedule

It is important for the current schedule to be updated to reflect the work that has been completed to ensure that only the current remaining work is displayed on the schedule. The Work With Work Assignments program (P48330) contains a Row Action to Complete a scheduled task, which could be at the work order or labor detail step.

Scheduling completions can be executed either at the work order level or the labor detail level. If completions are performed at the work order level, the system displays the work order program, enabling you to update the work order status and completion date. Scheduling completed at the labor detail level will display the labor detail completion program, enabling you to update the operation status and completion date for the labor step. Completing multiple labor detail steps can be accomplished using the Work Order Labor Detail program (P13732) and updating the operation status and completion date on the required steps. The system uses the supply and demand inclusion rules, as defined in the processing options of the P48330 program, to determine whether to display completed work orders or labor detail steps on the Work Assignments form.

You run the Crew Schedule Completion Metrics program (R48327) to report the work that was completed and to update the crew metrics. If the schedule is at the work order detail level, the report will support the completion of the labor detail step and the work order.

The Crew Schedule Completion Report lists all work orders/labor detail steps with a crew schedule that has a work order or labor detail completion date within the schedule period defined in the processing option. The report is grouped by crew schedule and lead craft and lists both the saved schedule and total hour of work completed. The information can be used to automatically update the Crew Schedule Completion metric information stored in the Crew Schedule Metrics table (F48315).

Click to jump to top of pageClick to jump to parent topicForms Used to Complete Work Orders on the Schedule

Form Name

FormID

Navigation

Usage

Work With Work Assignments

W48330E

Crew Scheduling (G13RA12), Crew Schedule Assignments

Check the work order to complete and select Complete from the More Row Actions menu.

Labor Step Completion

W48330A

On the Work With Work Assignments form, select and view the Labor tab.

Check the labor step to complete and select Complete from the More Row Actions menu.

Click to jump to top of pageClick to jump to parent topicCompleting Work Orders on the Schedule

Access the Work Order - Manage <Work Order Description (Order Number)> form.

Status

Enter a user defined code (00/SS) that describes the status of a work order, rate schedule, or engineering change order.

Actual Finish Date

Enter the date that the work order or engineering change order is completed or canceled.

Status Comment

Enter a brief description to explain the status of the work order.

Actual Hours

Enter the actual hours accumulated for the work order.

Following the Save Changes, the Change Status form will display.

Remark

Enter a remark, description, name, or address.

Change Component

Enter a value that determines whether an Equipment Component Changeout was done on the work order. Values are:

0: Component Changeout was not done.

1: Component Changeout was done.

Click to jump to top of pageClick to jump to parent topicCompleting Labor Detail Steps on the Schedule

Access the Labor Step Completion form.

Operation Status

User defined code system 31, type OS. The operation status code that identifies the current status of a work order or engineering change order as the operation steps in the routing are completed. A processing option is available to specify the default operation status for completed.

Actual Finish Date

Enter the date that the work order or engineering change order is completed or canceled.

Click to jump to top of pageClick to jump to parent topicRunning the Crew Schedule Completion Metrics Program (R48327)

Select Crew Scheduling (G13RA12), Crew Schedule Completion Metrics.

See Also

JD Edwards EnterpriseOne Resource Assignments Reports

Click to jump to parent topicReviewing Schedule Metrics

This section provides an overview of schedule metrics, lists prerequisites, and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Schedule Metrics

The schedule metrics table contains all of the crew/craft availability and schedule compliance metric information that is supported throughout the crew scheduling process. The schedule compliance metric measures the performance of the crew in the process of creating a schedule of work and then completing that work. The following information is maintained by crew/craft for a schedule period:

The Manage Schedule program (P48320) creates a schedule for the crew in the next period and allows you to view current, following, and future scheduled work. After you review and update the schedule, you can use the Save Metrics option to save the schedule and update the scheduled hours for the crew/craft in the Schedule Metrics table (F48315).

The Schedule Completion Metrics report (R48327) is run after orders on the schedule are completed. The report updates the Completed Scheduled Hours and Completed Hours fields in the F48315 table. This report is typically run one to two weeks after the work has been completed to capture the completion metrics for the crew/craft.

The Schedule Metrics program (P48315) provides an aggregate view of the metric information. The two key scheduling metrics that the report calculates are:

You use the Crew Reschedule Metrics program (P48316) to review the reasons why work is rescheduled. You can review this data by crew or craft and date range. The reason codes and text descriptions by work order are available for review and analysis.

Click to jump to top of pageClick to jump to parent topicPrerequisites

Before you complete the tasks in this section:

  1. Set up Crew Availability for the next period.

  2. Create and save the schedule of work for the crew in the next period.

  3. Report completions of the work scheduled and other unscheduled work completed during the schedule period.

See Also

Working with Crew Availability

Saving Schedule Changes

Completing Orders on the Schedule

Click to jump to top of pageClick to jump to parent topicForms Used to Review Schedule Metrics

Form Name

FormID

Navigation

Usage

Work With Maintenance Schedule Metrics

W48315A

Periodic Resource Assignment Processing (G13RA20), Crew Schedule Metric

View schedule metrics by crew and schedule period.

Work With Maintenance Rescheduling Metrics

W48316A

Periodic Resource Assignment Processing (G13RA20), Crew Reschedule Metric

View reschedule metrics by crew, craft, reason code, and schedule period.

Click to jump to top of pageClick to jump to parent topicReviewing Schedule Achievement

Access the Work With Maintenance Schedule Metrics form.

Review the schedule completion performance compared to the total amount of work scheduled. The data on this form is summarized for the entire crew. You can select a crew to view detailed metrics for each lead craft. You can then select a lead craft to view detailed information about each resource in that craft. The average load percentage that the system displays on the Work With Maintenance Schedule Metrics form is a calculated value based on all of the resources in that crew.

Click to jump to top of pageClick to jump to parent topicReviewing Reason for Reschedule

Access the Work With Maintenance Rescheduling Metrics form.

Review the rescheduling reason codes by crew, craft, rescheduling code, and date range.