Complete the following checklist to ensure that the access route requirements are met.
Access Route Considerations | Yes | No | N/A | Comment |
---|---|---|---|---|
Has the access route been checked for clearances of the packaged equipment? |
||||
Do all the doors and entry ways conform to the width and height requirements for transportation, including the width of the unpacked unit? |
||||
Do all the doors meet the height requirement of minimum 86 inches for packaged delivery? |
||||
Does the access route provide sufficient space for transport of the packed devices? |
||||
Are there any ramps or thresholds that are of concern? If yes, then provide details. |
||||
Are there any stairs or ramps in the moving patch for the new hardware? |
||||
Have you confirmed that all route incline angles are within the permitted range? |
||||
Have you confirmed that the access route is free of any obstacles that would expose the device to shock? |
||||
Are all the surfaces acceptable for rolling the new unpacked and packed equipment? |
||||
If a pallet jack is to be use, then have you confirmed the following:
|
||||
If there are stairs, then is a loading elevator accessible for the equipment? |
||||
If an elevator is to be used, then have you confirmed the following:
|
||||
Does the path from the receiving location to the designated data center area support the weight of the unpacked equipment? |
||||
Is the path onto the raised floor rated for dynamic loading of the server? Refer to Flooring Requirements for requirements. |