1. Site Preparation

Industry Guidelines for Site Planning

Site Planning Assistance From Sun

Sun Enterprise Installation Services

Sun Environmental Services

Site Planning Considerations

Server Configurations

Planning for Maximum Server Configurations

Planning for Actual Server Configurations

Using Server Configuration Data

Data Center Location and Design

Route to the Data Center

2. Environmental Requirements

Operating Specifications

Temperature

Air Intake Temperatures

Aisle Temperatures

Rate of Change

Humidity

Troubleshooting Environmental Conditions

Facility Environmental Tests

Equipment Installation Environmental Tests

Equipment Failure Environmental Tests

Cooling and Aisle Airflow

Calculating Cooling Requirements

Measuring Aisle Airflow Speed

Acclimatization

Vibration and Shock

Contaminants

Fire Containment

3. Rackmounting the Servers

Cabinet and Rack Terminology

Cabinet Location

Creating a Hot-Aisle/Cold-Aisle Layout

Maximizing Hot-Aisle/Cold-Aisle Temperature Differences

Determining Aisle Clearances

Determining Aisle Pitch

Sun Cabinets

Cabinet, Rack, and Server Dimensions

Rack Units

Other Cabinet and Rack Features

Cabinet Doors and Panels

Load Capacity

EMI and RFI Requirements

Power Sequencers

Stabilization

Tools Required for Rackmounting the Servers

Rackmounting Guidelines

4. Server Power and Cooling Requirements

Power Requirements

Power Sources

UPS and Backup Generator

Grounding

Emergency Power Control

Power Constraints

Power Supplies

PCI Bus Power

Heat Output and Cooling

Chassis Airflow

Units of Measurement

Determining Heat Output and Cooling

Using Rack Location Units to Determine Heat Output and Cooling

5. Cabinet Specifications

Sun Cabinet Shipping Crate Specifications

Sun Cabinet Physical Specifications

Cabinet Power Sequencer Specifications

6. Site Planning Checklist