Removing and Replacing the Enterprise 6500/5500 Cabinet Rear Door and Kick Panel

The rear door and kick panel can be removed to facilitate the installation of power and interface cables.

Removing the Rear Door and Kick Panel

  1. Locate the plastic key that is in the accessory box.

  2. Open the door on the left side of the top bezel to access the key switch.

    The door opens when you press on the recessed area.

  3. Turn the system key switch to Graphic

  4. (the Standby position) (Figure 2-1).

    Figure 2-1 Key Switch Standby Position

    Graphic

  5. Ensure that the AC power sequencer switch (Figure 2-2) is set to Off.

    Figure 2-2 AC Power Sequencer Power Switch

    Graphic

  6. Open the back door and take out the AC power cord that is coiled inside the server cabinet.

  7. If you are installing or rearranging interface cables, remove the kick panel (Figure 2-2) by loosening the two screws on the kick panel.

    To protect and organize the interface cables, place the cables behind the kick panel.

  8. If it is necessary to remove the rear door, pull the hinge pins out of the hinges and lift the door off.

Replacing the Rear Door and Kick Panel

  1. If you removed the panel, secure the kick panel to the cabinet (Figure 2-2).

    Interface cables should be placed between the bottom panel and the kick panel.

  2. Place the rear door on the hinges on the cabinet.

  3. Insert the hinge pins in the hinges.