Introduction to Site Planning

Customer Obligations

System Configuration

Site Planning Checklist

Preparing the Site for System Installation

Load-Bearing and Handling Precautions

Power and Electrical Requirements

Power Consumption

Power Budgeting

Electrical Requirements

Power Cords

Grid Redundancy

Cooling Requirements

Temperature and Humidity Requirements

Airflow Requirements

Clearance for Service and Aisle Requirements

Route to the Data Center

Rackmounting Considerations

Mounting the Chassis in a Rack

Compatible Cabinets

Number of Chassis Supported in a Rack

Facility Safety

Secure Installation Requirements

Placement of Product

Hazardous Conditions Precaution

Specifications

Shipping Crate Physical Specifications

Chassis and Components Dimensions and Weights

AC Power Requirements

Environmental Specifications

Thermal Design Specifications

Acoustic Noise Emissions

Regulatory Compliance

Glossary

Index

Clearance for Service and Aisle Requirements

To enable installation and servicing of the system, including access to system cables, follow these space restrictions.

Location
Service Access Requirement
System extended from rack
3 feet (0.9 m) on both sides of the system to facilitate installation
Front cold aisle
5 feet (1.5 m); required for rackmounting
Back hot aisle
3 feet (0.9 m); required for cable access

Arrange racks in a hot aisle–cold aisle layout. This layout enables cool air to flow through the aisles to the system’s front air intake and enables heated air to flow from the system’s back exhaust. A hot aisle–cold aisle layout eliminates the direct transfer of hot exhaust air from one system into the intake air of another system.