Managing BOMs and Engineering Changes for Suppliers

This chapter provides an overview of bills of material (BOMs) and engineering changes for suppliers and discusses how to:

Click to jump to parent topicUnderstanding BOMs and Engineering Changes for Suppliers

This section lists prerequisites for BOM inquiries and engineering changes for suppliers and discusses:

Click to jump to top of pageClick to jump to parent topicPrerequisites

Before your suppliers can access specific inquiries, you must:

Click to jump to top of pageClick to jump to parent topicCapabilities to Share PeopleSoft Engineering Information

Because today's business world often requires more outsourcing, there's a need to share information more effectively between customers and their suppliers. With PeopleSoft Engineering, you can:

Click to jump to top of pageClick to jump to parent topicAttachments and Email Capability

Suppliers can view, upload, and delete attachments in PeopleSoft Engineering. Following is a summary of the functionality and what you must know before starting to use attachments:

See Also

Sending Email to Vendors

Click to jump to top of pageClick to jump to parent topicFunctionality Reflected in PeopleSoft Manufacturing and PeopleSoft Engineering

The supplier-related BOM inquiry and engineering change functionality is reflected in PeopleSoft Manufacturing and PeopleSoft Engineering. Following is a list describing how to use the pages in each application:

See Also

Sending Email to Vendors

Defining Vendor Access Lists

Defining BOM Access Privileges for Vendors

Entering ECR Header Information

Click to jump to parent topicCommon Elements Used in This Chapter

Set filter options

Click to view requests for different business units or to view non-pending change requests.

Return to Vendor List

Click to return to the Select Vendor page.

Documents

This group box is accessible only if Documentum is installed.

Click to jump to parent topicViewing BOMs

To grant vendors access to BOMs, use the BOM Access by Vendor (EN_IC_BOM_PRIV) component.

Use these pages to view BOMs for all items to which you have given access with the BOM Access by Vendor page. Prior to selecting which item BOMs to view, if the user is associated with multiple vendors (that is, if the user is representing multiple vendor sites as a corporate vendor user), the supplier sees a Select Vendor page.

This section discusses how to:

See Also

Defining BOM Access Privileges for Vendors

Prerequisites

Click to jump to top of pageClick to jump to parent topicPages Used to View Supplier-Related BOMs

Page Name

Definition Name

Navigation

Usage

Select Vendor

EN_SS_VND_LIST

Review Product Design, View Bills of Material

Select the vendor whose information you want to appear on the BOM.

Select Bill of Material

EN_ICBOMVNDLST

  • Review Product Design, View Bills of Material (if not associated with multiple vendors)

  • Click one of the vendor names on the Select Vendor page (if associated with multiple vendors).

Select an item whose BOM is to be viewed.

Filter Options

EN_IC_BOM_SEARCH

Click the Set filter options link on the Select Bill of Material page.

Narrow the search for BOMs.

Bill of Material

EN_ICBOMINQ_HDR

Click an item ID on the Select Bill of Material page.

View BOMs.

Component Detail

EN_ICBOMINQ_COMP

Click an item ID on the Bill of Material page.

View BOM component detail.

Click to jump to top of pageClick to jump to parent topicSelecting a Vendor for BOMs

Access the Select Vendor page (Review Product Design, View Bills of Material).

A list of the vendors to which your suppliers are linked appears. Select the vendor whose information you want to display. The system then displays the Select Bill of Material page, which lists the items available to that vendor.

Click to jump to top of pageClick to jump to parent topicSelecting BOMs

Access the Select Bill of Material page (Review Product Design, View Bills of Material or if there are multiple vendors, click one of the vendor names on the Select Vendor page).

Item IDs

Displays the IDs to which the vendor has been granted access with the BOM Access by Vendor page.

Note. The component item identifiers displayed in the Item ID field are those of the vendor if defined for the vendor and item combination with the Purchasing Attributes component in PeopleSoft Inventory. If no vendor and item information exists, then the customer item appears. View both vendor and customer item IDs on the Component Detail page. Define vendor item IDs using the Item Vendor page in PeopleSoft Inventory.

Set filter options

Click to view rework and to view engineering bills of material (EBOMs).

See Also

Defining Attributes and Priorities for Purchasing Item Vendor Relationships

Click to jump to top of pageClick to jump to parent topicNarrowing the Search for BOMs

Access the Filter Options page (Click the Set filter options link on the Select Bill of Material page).

Search Criteria

Enter your search criteria, including BOM state (Manufacturing or Engineering) and BOM type (Production or Rework).

Click to jump to top of pageClick to jump to parent topicViewing BOMs

Access the Bill of Material page (Click an item ID on the Select Bill of Material page).

As of Revision

Select to limit your search if the item is revision-controlled.

Level

Select a level to display components in that level.

Refresh button

Click to refresh the Components list after supplier changes the value for As of Revision and/or Level fields.

Quantity Per

Displays the quantity per order or assembly.

Item ID

Click to view component details for this item.

Return to Selected Bill of Material

Click to return to the Select Bill of Material page.

Send Email

Click to send email. The email will contain a URL to this specific Bill of Material page, as well as a URL to the BOM Maintenance - Summary page in PeopleSoft Manufacturing (if the BOM is a manufacturing BOM) or the Engineering BOM Maintenance - Summary page in PeopleSoft Engineering (if the BOM is an EBOM).

See Also

Sending Email to Vendors

Maintaining Bills of Material

Click to jump to top of pageClick to jump to parent topicViewing Component Details

Access the Component Detail page (Click an item ID on the Bill of Material page).

This page displays the dimensions, reference designators, attachments, substitute items, and manufacturer's information of the component.

Return to Bill of Material

Click to return to the Bill of Material page.

Click to jump to parent topicViewing, Adding, or Updating ECRs

Using these pages, your suppliers can view and even add or update ECRs to which you have given them access using the BOM Access by Vendor page. If the login role is associated with multiple vendors, prior to selecting the ECRs in which the supplier is interested, the supplier sees a Select Vendor page.

This section discusses how to:

See Also

Defining BOM Access Privileges for Vendors

Click to jump to top of pageClick to jump to parent topicPages Used to View, Add, or Update Supplier-Related ECRs

Page Name

Definition Name

Navigation

Usage

Select Vendor

EG_SS_VND_LIST

  • Select Review Product Design, Engineering Change Request (if not associated with multiple vendors)

  • Click one of the vendor names on the Select Vendor page (if associated with multiple vendors).

Select a vendor for ECRs.

Select Change Request

EG_IC_ECR_LIST

Review Product Design, Engineering Change Request

Select ECRs to view and, if given the appropriate privileges, update.

Filter Options

EG_IC_ECR_SEARCH

Click the Set filter options link on the Select Change Request page.

Narrow the search for ECRs.

Change Request Detail

EG_IC_ECR_HDR

Click a request number, click the Add a Change Request button, or click the Edit button on the Select Change Request page.

View ECR detail information.

Engineering Change Request - Item Affected Detail

EG_IC_ECR_ASSY_RES

Click the Item Details button in the Items Affected group box on the Change Request Detail page.

View ECR item-affected information.

Click to jump to top of pageClick to jump to parent topicSelecting a Vendor for ECRs

Access the Select Vendor page (Select Review Product Design, Engineering Change Request, or, if associated with multiple vendors, click one of the vendor names on the Select Vendor page).

A list of the vendors to which your suppliers are linked appears. Your suppliers can select the vendor whose information they want to view. The system then opens the Select Change Request page, which displays the ECRs available to that vendor.

Click to jump to top of pageClick to jump to parent topicSelecting ECRs

Access the Select Change Request page (Review Product Design, Engineering Change Request).

A list of all pending change requests appears for the default business unit to which the access has been granted.

Item ID

The component identifiers that appear in this column are those of the supplier if they are defined for the vendor and item combination with the Purchasing Attributes component in PeopleSoft Inventory. If no vendor and item information exists, then the customer item appears. You can define vendor item IDs using the Item Vendor page in PeopleSoft Inventory.

Suppliers can view a particular ECR if they created the ECR or if they have been given access to at least one of the affected items that the ECR impacts. If a supplier has ECR update privileges, then the supplier can submit new ECRs and update change requests created by the supplier. The supplier owns any request added by the supplier and can modify only change requests that the supplier owns. Suppliers can edit their ECRs but not your internally created ECRs. If the supplier doesn't have update privileges, then the supplier can only view ECRs; all change request fields are display-only, and all Add, Upload an Attachment, Delete, and Save buttons on the Change Request Detail page are unavailable.

Add a Change Request and Edit

If you have granted update ECR privileges to a supplier, then the system displays these buttons, enabling the supplier to add a new ECR or edit an existing ECR. These buttons access the Change Request Detail page.

Note. Suppliers are not prompted for business units when adding new requests. All change requests created by suppliers are created for the default business unit defined on the User Preferences page for the supplier user.

Note. The ECR Maintenance - Header page has a Not Accessible by Vendors check box, which, if selected, blocks vendor access to specific ECRs. Therefore, even if vendors have been granted access on the BOM Access by Vendor page, you can prevent vendor access to specific ECRs.

See Also

Creating and Maintaining ECRs

Defining BOM Access Privileges for Vendors

Defining Attributes and Priorities for Purchasing Item Vendor Relationships

Click to jump to top of pageClick to jump to parent topicSetting ECR Filter Options

Access the Filter Options page (Click the Set filter options link on the Select Change Request page).

Search for additional change requests by description, status, priority, and item.

Click to jump to top of pageClick to jump to parent topicViewing Change Request Detail

Access the Change Request Detail page (Click a request number, click the Add a Change Request button, or click the Edit button on the Select Change Request page).

Upload an Attachment, Delete, and Add

These buttons are available if a supplier clicked the Add a Change Request or Edit buttons to access this page. These buttons enable suppliers to add, upload, or delete data on this page.

If the supplier has add ECR attachments capability (defined with the BOM Access by Vendor page), the supplier can upload new attachments or delete attachments as part of adding or modifying an ECR.

If the supplier accessed this page by selecting a specific request number on the Select Change Request page, this page is display-only, and these buttons are unavailable.

Items Affected

If the supplier owns the change request, then the supplier can enter any item in this group box. The supplier has limited access to the item prompt table; the system displays only items to which the supplier has been granted access. Any valid item entered is accepted by the system. To enter a brand new item, the supplier must select New in the Type column.

Reasons and Actions

If the supplier owns the change request, then the supplier can add or delete items in these group boxes.

Return to Select Change Request

Click to return to the Select Change Request page.

Send Email

Click to send email. The email contains a URL back to this specific Change Request Detail page, as well as a URL to the ECR Maintenance - Header page in PeopleSoft Engineering.

Save

This button is available if the supplier clicks the Add a Change Request or Edit buttons on the Select Change Request page.

See Also

Defining BOM Access Privileges for Vendors

Sending Email to Vendors

Click to jump to top of pageClick to jump to parent topicViewing Item-Affected Details

Access the Engineering Change Request - Item Affected Detail page (Click the Item Details button in the Items Affected group box on the Change Request Detail page).

Add, Upload an Attachment, and Delete

These buttons are available if the supplier clicked the Add a Change Request or Edit buttons on the Select Change Request page to access the Item Affected Detail page. These buttons enable the supplier to add, upload, or delete data on this page.

If the supplier accessed the Change Request Detail page (the page used to access the Item Affected Detail page) by selecting a specific request number on the Select Change Request page, then both the Change Request Detail page and the Item Affected Detail page are display-only.

Return to Change Request Detail

Click to return to the Change Request Detail page.

View Production BOM and View Engineering BOM

If the supplier clicks these links, the system displays the Bill of Material page, which lists the current affected item. These links are unavailable if the affected item doesn't have a BOM or if the supplier doesn't have access to the BOM.

See Also

Defining BOM Access Privileges for Vendors

Click to jump to parent topicViewing ECOs/Workflow

Using these pages, your suppliers can view ECOs to which you have given them access. If a supplier is associated with multiple vendors, prior to selecting the ECOs in which the supplier is interested, the supplier sees a Select Vendor page.

This section discusses how to:

See Also

Creating Engineering Change Orders (ECOs)

Defining BOM Access Privileges for Vendors

Click to jump to top of pageClick to jump to parent topicPages Used to View Supplier-Related ECOs/Workflow

Page Name

Definition Name

Navigation

Usage

Select Vendor

EG_SS_VND_LIST

Review Product Design, Engineering Change Order

Select the vendor whose information you want to view on ECOs.

Your vendor must be linked to more than one vendor for the system to display this page. Otherwise, it goes directly to the Select Change Order page.

Select Change Order

EG_IC_ECO_LIST

  • Select Review Product Design, Engineering Change Order (if not associated with multiple vendors)

  • Click one of the vendor names on the Select Vendor page (if associated with multiple vendors).

Select an ECO from a list of all pending change orders for the default business unit to which access has been granted. Suppliers can view a specific ECO if granted access to at least one affected item on the order. A supplier can also view a change order if the supplier is one of the approvers of the order. When the supplier is an approver, it isn't required that the affected items be set up on the BOM Access by Vendor page.

Filter Option

EG_IC_ECO_SEARCH

Click the Set filter options link on the Select Change Order page.

Set ECO filter options to narrow the search for ECOs.

Change Order Detail

EG_IC_ECO_HEADER

Click an order number on the Select Change Order page.

View ECO detail information.

Engineering Change Order - Item Affected Detail

EG_IC_ECO_ASSY_RES

Click an item ID in the Items Affected group box on the Change Order Detail page.

View ECO item-affected information.

Click to jump to top of pageClick to jump to parent topicSelecting a Vendor for ECOs

Access the Select Vendor page (Review Product Design, Engineering Change Order. Select the vendor whose information you want to view on ECOs).

Select the vendor whose item information you want to appear. The system then opens the Select Change Order page, which displays the ECOs available to that vendor.

Click to jump to top of pageClick to jump to parent topicSelecting ECOs

Access the Select Change Order page (Select Review Product Design, Engineering Change Order or if associated with multiple vendors, click one of the vendor names on the Select Vendor page).

Item ID

The component item identifiers in this column are those of the supplier if they are defined for the vendor and item combination using the Purchasing Attributes component in PeopleSoft Inventory. If no vendor and item information exists, then the customer item appears. You can define vendor item IDs using the Item Vendor page in PeopleSoft Inventory.

Note. The ECO Maintenance - Header page contains a Not Accessible by Vendors check box, which, if selected, blocks access to specific ECOs. Therefore, even if suppliers have been granted access on the BOM Access by Vendor page, you can prevent supplier access to specific ECOs.

Click to jump to top of pageClick to jump to parent topicViewing Change Order Detail

Access the Change Order Detail page (Click an order number on the Select Change Order page).

Upload an Attachment

If a supplier has the capability to add ECO attachments (defined with the BOM Access by Vendor page), the supplier can upload new attachments. If the privilege is granted, the Save button is available. While in the same session, the supplier can also delete attachments prior to saving. Once an attachment is uploaded and the ECO is saved, the supplier can't delete the attachment.

Return to Select Change Order

Click to return to the Select Change Order page.

Send Email

Click to send email. The email contains a URL to this specific Change Order Detail page, and a URL to the ECO Maintenance - Header page in PeopleSoft Engineering.

Approval Action

If a supplier is listed in the Approval Process group box as the current approver, then the Approval Action group box becomes visible, and the supplier can approve, deny, or recycle the ECOs. Otherwise, this group box is unavailable.

When the supplier is included as an approver within a workflow step, the supplier can be automatically notified by email. This email contains a URL to the originating ECO page for the specific ECO requiring approval. When PeopleSoft Engineering is enabled for suppliers, the supplier can also access pertinent workflow information by using the task worklist pagelet functionality.

Comments

After reviewing the ECO, a supplier can enter text in this field. Then, if the vendor step is the next step for approval, the supplier can approve, deny, or recycle the ECO by clicking the appropriate buttons.

Approve button

If a supplier clicks this button, the approver in the next step of the approval process is notified by email and worklist entry.

Deny and Recycle buttons

If the supplier clicks either of these buttons, the approver in the previous step is notified. Furthermore, when denied or recycled, the current action is reset, and the originator of the ECO is notified by email. To indicate when the originator (the person who submitted the ECO for workflow) should be notified in the approval process, use the System Workflow Rules page in the General Options navigation.

Click to jump to top of pageClick to jump to parent topicViewing Item-Affected Detail

Access the Engineering Change Order - Item Affected Detail page (Click an item ID in the Items Affected group box on the Change Order Detail page).

Upload an Attachment

If a supplier has the capability to add ECO attachments (defined with the BOM Access by Vendor page), the supplier can upload new attachments. If the privilege is granted, the Save button is available. While in the same session, the supplier can also delete attachments prior to saving. Once an attachment is uploaded and the ECO is saved, the supplier can't delete the attachment.

Return to Change Order Detail

Click to return to the Change Order Detail page.

View Production BOM and View Engineering BOM

If a supplier clicks either of these links, the system opens the Bill of Material page, which displays the current affected item. These links are unavailable if the affected item doesn't have a BOM or if the supplier doesn't have access to the BOM.

See Also

Creating and Maintaining ECOs

Defining BOM Access Privileges for Vendors