You can manually refresh earned value sheets so that they reflect the latest data, depending on their source: information from cost sheet columns or cash flow curves, or information such as earned progress from schedule sheets. Earned value sheets are automatically refreshed if you make changes to the Properties window, Settings tab.
To refresh an earned value sheet
| 1 | Select a sheet in the Earned Value log. |
| 2 | Click the Refresh button. |
As data is refreshed, the Last Update column in the log will display In Progress. This may take a few moments. When the update is complete, the current date will display in the column. You will not be able to access the sheet while the update is in progress.