Earned Value (EV)

Earned value analysis is an industry standard designed to help project managers quantify project performance through:

Measuring project performance and progress
Analyzing schedule and budget variances
Forecasting schedule and cost overruns

Available in Primavera Unifier’s standard projects and WBS-based shells, you can create any number of earned value sheets. Data collection sources are cost or schedule sheets, and each have different settings and prerequisites.

When the source is a cost sheet:

Primavera Unifier uses budget information from a WBS cash flow curve to calculate a BCWS curve.

When the source is the schedule manager:

The detail-level selection display schedule sheet activity progress.
The summary-level selection compares rows from other earned value sheets.
Primavera Unifier users progress dates to calculate BCWS, BCWP, ACWP, and EAC.
Progress dates are calculated as of the current date. In a schedule imported from Primavera, Primavera Unifier honors the Current Data Date entry as the latest progress date. This date may be a future date that you might use in project modeling. Primavera Unifier will calculate curves up to the entered date.

 

About Earned Value Sheets

Access earned value sheets

Creating and Managing Earned Value Sheets

Working with Earned Value Sheets

 

 

 


Oracle Corporation

Primavera Unifier 9.10 • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved.

Copyright Information