How to Verify the HA for WebLogic Server Installation and Configuration for Failover Services

To verify that you have installed and configured HA for WebLogic Server correctly for a failover configuration, perform the following steps:

  1. Ensure that you can successfully connect to the WebLogic Servers from a client and that both the Administration Server and the Managed Server are in the RUNNING mode.
  2. Switch the resource groups to cluster-node2.
    # clresourcegroup switch cluster-node2 RG1
    # clresourcegroup switch cluster-node2 RG2

    The WebLogic Administration and Managed Servers must go offline on cluster-node1 and go online on cluster-node2. Ensure that the WebLogic Server processes on cluster-node1 are stopped. Because smooth shutdown is not enabled, the WebLogic Server process will be killed by the HA for WebLogic Server STOP method instead of being shut down smoothly. Refer to Creating a Resource That Shuts Down Smoothly for the configuration that enables smooth shutdown. For more information, see STOP Method for the configuration that enables smooth shutdown.

  3. Ensure that you can successfully connect to the WebLogic Servers from the client and that both the Administration Server and the Managed Server are in the RUNNING mode.

    Note -  The client sessions might be lost when the WebLogic Servers go offline on cluster-node1 and come online on cluster-node2.
  4. On cluster-node2, kill the Administration Server process.

    The fault monitor must detect the killed process and restart the Administration Server.

  5. Kill the Administration Server process repeatedly.

    The Administration Server Resource group fails over after the number of retries exceeds the retry count within the retry interval.

  6. On cluster-node2, kill the Managed Server process.

    The fault monitor must detect the killed process and restart the Managed Server.

  7. Kill the Managed Server process repeatedly.

    The Managed Server Resource group fails over after the number of retries exceeds the retry count within the retry interval.

    If the previous steps are successful, you have correctly configured the HA for WebLogic Server.

Troubleshooting