This chapter contains the topic:
From Material Planning Operations (G34), choose Periodic Multi-Facility Planning
From Multi-Facility Periodic Planning Operations (G3423), choose MPS Regeneration
After you have set up the supply and demand relationships among your branch/plants, you can use MPS Regeneration to generate a multi-facility schedule. Alternatively, you can use MPS Net Change to generate a multi-facility schedule.
When you generate a multi-facility schedule, the system evaluates selected information, performs calculations, and recommends a time-phased planning schedule for all selected items.
Set up DRP/MPS multi-facility scheduling. See Section 32.1, "Setting Up Multi-Facility Schedules."