Print Order Control Report (POCT)

Purpose: Use the Operations Control Report to review the flow of order activity and merchandising activity for a period of time. This report provides a high-level overview of the fulfillment process, identifies potential bottlenecks or problem areas, and delivers an audit trail of order activity.

The system uses the Order Control Summary table to track the total figures used to build this report; see Reviewing Operations Control Summary (FLSH).

Periodic function to update backorder totals: You must include the PFR0062 periodic function as part of your periodic processing to have correct and up-to-date ending order balance totals on the report. This periodic function must be run at the end of the day, when the background jobs have ended. In addition to performing this update to the table, the periodic function also submits the ORDSUM job, which generates the Order Control Report using the current date.

Order Control Report Screen

How to display this screen: Enter POCT in the Fast path field at the top of any menu, or select Print Order Control Report from a menu.

Field

Description

Start date

The first date to include on the report.

Numeric, 6 positions (in user date format); required.

End date

The last date to include on the report.

Numeric, 6 positions (in user date format); required.

Note: Both dates must be earlier than the current date. The information on the report would be incomplete if you did not run the periodic process to update backorder totals. See above.

Completing this screen: Complete the start and end date fields and select Submit. The system submits the job ORD_CONTRL, which generates the Operations Control Report.

CS06_01 OROMS 17.0 2018 OTN