Creating a New Specified WB Contract

To prevent the auto-completion of subcontracts, the Head Contractor Work Breakdown (WB) must have at least two line items before you create of import a new subcontract.

See Enter Work Breakdown for instructions.

To create a specified WB contract:

  1. Create a new subcontract. See topic Creating Subcontracts Manually.
  2. Access the Edit Contract dialog box from the Subcontract List page or the Contract Maintenance page.
    1. From the Subcontract List page, select the Action icon and select Edit Settings.
    2. From the Contract Maintenance page, select Edit Settings button.
  3. From the Sub WB Option drop-down menu, select the Specified WB setting.
  4. Once you complete all necessary information on the Contract Maintenance page, select Submit Contract.

    A Status page confirms the contract has been created.

    Note: The Next Step listed on the Status page is Edit budget for project. Use this link to enter the Work Breakdown for the subcontract.