Creating a New Specified WB Contract
To prevent the auto-completion of subcontracts, the Head Contractor Work Breakdown (WB) must have at least two line items before you create of import a new subcontract.
See Enter Work Breakdown for instructions.
To create a specified WB contract:
- Create a new subcontract. See topic Creating Subcontracts Manually.
- Access the Edit Contract dialog box from the Subcontract List page or the Contract Maintenance page.
- From the Subcontract List page, select the Action icon and select Edit Settings.
- From the Contract Maintenance page, select Edit Settings button.
- From the Sub WB Option drop-down menu, select the Specified WB setting.
- Once you complete all necessary information on the Contract Maintenance page, select Submit Contract.
A Status page confirms the contract has been created.
Note: The Next Step listed on the Status page is Edit budget for project. Use this link to enter the Work Breakdown for the subcontract.