Creating a New Specified Billing Contract
To add the Specified Billing setting to a new subcontract so you can create and edit progress claims for the Subcontractor:
- Create the Head Contractor Work Breakdown (WB).
To prevent the subcontract from auto-completing, create at least two line items in the Head Contractor WB.
- Create a new subcontract. See topic Creating Subcontracts Manually.
- Select the Use Specified Billing setting.
- Select the Save button.
A Status page confirms the contract has been created. The Subcontractor must accept or decline the subcontract to participate on the project.