Deleting an Accepted Subcontract
There are certain instances in which you may need to delete a subcontract linked to your project. Since Textura holds legal documents and facilitates Subcontractor claiming, Project Managers can only delete a confirmed subcontract after meeting the following criteria:
- The Subcontractor who accepted the subcontract was not included in any periods
- There are no legal documents uploaded for the subcontract; if there are any documents, you will need to delete them from the Edit Document Status page
Note: In order to delete a document, you must change the document status to Note Received.
- The Subcontractor did not receive any payments through TPM.
As long as the subcontract fits the above criteria, a user with a Project Manager role can delete the subcontract from the Contract Maintenance page.
Accidentally assign a subcontract to an incorrect Subcontractor organisation and the Subcontractor has not yet accepted project participation? You can reassign the subcontract instead.
See the Reassigning Contracts topic for a step-by-step guide on reassigning a subcontract to a different organisation.
To delete an accepted subcontract:
- Navigate to the Variations Page
- From the My Contract menu at the top of any project page, select the My Variations link.
- If you are a Prime Subcontractor with an on-system Sub-Tier Subcontractor working for you, select the Subcontract Variations link from the Subcontracts menu at the top of any page to go to the Subcontract Variations tab of the Variations page. You can only access the page in this way if you have Sub-Tiers with a contract on the application.
- From the Variations page, select the +Add button.
- Create a negative variation to bring the subcontract value to zero.
See the Creating a Subcontract Variation for Head Contractors topic for a step-by-step guide on creating a subcontract variation (SV).
- Navigate to the Contract Maintenance Page
- From the Subcontract List page, select the Pencil icon.
- From the Edit Contracts tab of the Edit Work Breakdown page, select the New link for the budget line the subcontract will bill against.
- If your subcontract meets the criteria listed above, a Delete Subcontract button displays. Select the Delete Subcontract button.
A Delete Subcontract dialogue box displays.
- In the dialogue box, select a reason for deleting a subcontract from the drop-down list. This is a mandatory step and you cannot delete a subcontract without selecting an option.
- Select the Delete button.
After you delete the project, the following will happen:
- If the you or the Subcontractor already paid the usage fees for the subcontract, a refund of these fees will occur in 5-7 business days
- The Subcontractor receives an email about the deleted contract.