Adding the Specified SoV Setting to a New Subcontract

To add the Specified SoV setting to a new subcontract so you can manage the budget for a Subcontractor:

  1. Create the General Contractor Schedule of Values (SoV).

    To prevent the subcontract from auto-completing, create at least two line items in the General Contractor SoV.

  2. Create a new subcontract. See topic Creating Subcontracts Manually.
  3. From the Sub SoV Option drop-down, select the Specified SoV setting.
  4. Select the Save button.

    Status page confirms the contract has been created. The Subcontractor must accept or decline the subcontract to participate on the project.