You can enter duration or effort in decimal numbers in EnterpriseTrack. Note the following conditions when using fractional duration or effort:
- Fractional duration or effort is retained in the system as long the start and completion dates are not changed. If these dates are modified, the duration is changed to a whole number based on the start and completion dates. You can re-enter the fractional duration.
- When partial duration or effort is entered for activities that are sequential, EnterpriseTrack does not use the fractional duration or effort when showing the start and end dates for those activities. For example, if the first activity (Activity 1) takes 2.5 days to complete from November 1st, the start date for the second activity (Activity 2) will be shown as November 4th and not November 3rd.
- When activity dates are changed from the Project Dates page, EnterpriseTrack does not retain the partial duration. The duration is rounded off to the nearest whole number.