Enabling the OPERA PMS Interface for a Revenue Center

You must enable the OPERA PMS interface for each revenue center that uses OPERA.

  1. Select the revenue center, click Setup, and then click RVC Parameters
  2. Click the Interfaces tab.
  3. Select the PMS interface to enable the OPERA PMS interface for the revenue center.

    Figure 55-12 Revenue Center Parameters Interfaces Tab


    This figure shows the RVC Parameters module and where interfaces are assigned to revenue centers.
  4. Click Save.
  5. Repeat Steps 1 through 4 for each revenue center that uses the OPERA PMS interface.